GoConqr hat ein neues Design! Sag uns, wie es dir gefällt.

Mindmap

T016 CONTRACT ADMINSTRATION

chrissi.cowan Englisch

Mind map for contract administration: roles and responsibilities, relationship with the employer and other considerations

Mind map: contract administration

Inhalt der Mindmap

T016 CONTRACT ADMINSTRATION

  1. ROLES/RESPONSIBILITES

    • GENERAL ADMINSTRATION
      • PROVISION OF INFO
        • ENSURE: - clause 2.10 requires the CA to issue 2 copies of the information referred in the information release schedule
        • SUPPLY: documents etc clause 2.8
        • PROVIDE: additional info clause 2.11
      • FINANCIAL
        • Certify: Clause 4.6 - the amount of interim payments
        • Consider: Clause 4.6 - interim valuations
        • Send: Clause 2.4 - send computations of the adjusted contract sum to the contractor
      • SUPERVISION
        • APPROVE: Clause 2.2.1 - quality of materials, goods and workmanship
        • INSTRUCT: (3.10)
        • OBTAIN: the contractors consent
        • ISSUE: (2.25)
        • (2.17 & 3.5) Consent to the removal of unfixed materials on site 'in writing' or sub letting
        • MAKE: (2.19) a fair and reasonable EOT in writing
      • MISC
        • UNDERTAKE: the role of CDMC
        • UNDERTAKE: the role of the QS
        • GIVE NOTICE: (8.4) identifying default by the contractor prior to termination
        • DIRECT: contractors design portion
    • RECORDS
      • NOTES OF SITE INSPECTIONS
      • OFFICE FILES
      • PHOTOS
    • SITE INSPECTIONS
      • Frequency is determined by:
        • Complexity
        • Calibre of contractor
        • Progress and stages
        • CA's terms
      • Not determined by value
      • recording of information
        • date/time
        • weather
        • nr & type of operatives on site
        • onsite instructions
        • progress
      • review of quality of workmanship. The CA needs to know whats in the prelims & spec & be familar with codes of practice
      • review of progress made in relation to the contract programme
      • check materials against specified
      • check the works conform to the spec & drawings
      • records of any measurement of work that may be needed for certification
      • health & safety
      • confirm outcomes in writing
    • SITE MEETINGS
      • formal
        • progress to date/expected completion/associated risks
        • contractor reported delays
        • instructions required
        • health &safety
        • employer changes
        • information required
        • sequencing of works
        • input by others i.e. specialists
        • queries relating to drawings/specification
        • EOT
        • claims for loss/expense
        • valuations
        • payments
        • dayworks
        • quality
        • review of subcontractors
        • effectiveness of communications
      • informal
        • held on site, with operatives, contracts managers, suppliers, employer
      • Pre-contract
        • contacts, intros, emergency info, responsibilites
        • general matters
          • confirmation of general arrangements i.e. access, egress, emergency procedures
            • enabling works i.e. asbestos, scaffolding etc
          • licenses & obligations under the Party Wall etc. Act 1996
          • working hours
          • site arrangements i.e. welfare
          • schedule of condition
          • employer & contractor insurance obligations
          • VAT status confirmation
        • Statutory matters
          • CDM/F10/construction phase plan
          • fire precautions/means of escape (Regulatory Reform (Fire Safety) Order
          • confirmation of planning/listed consent
          • confirmation of building control
          • confirmation of obligations relating to environmental legislation i.e. site waste, noise, flora/fauna protection, land conttamination
        • Programme
          • stages
          • meetings
          • payments
          • valuations
    • REPORTING TO EMPLOYER
    • INSTRUCTIONS
    • TIME
    • VALUATIONS
    • INSTRUCTIONS/VARIATIONS
    • COMPLETION
    • LOSS/EXPENSE
    • ADJUSTED CONTRACT SUM
    • INSOLVENCY OF CONTRACTOR
  2. RELATIONSHIP WITH THE EMPLOYER

  3. OTHER CONSIDERATIONS

Informationen

Beschreibung
Mindmap am T016 CONTRACT ADMINSTRATION, erstellt von chrissi.cowan am 25/08/2014.
Erstellt von
chrissi.cowan
Aufrufe
36
Bewertung

Feedback

Worum geht es?

Wie gefällt dir das neue Design?

Dein Eindruck