The RIBA Plan of Work 2013 Unit 5 M1 Preparation

Frage 1 von 20

1

How may stages are in the RIBA Plan of work 2013

Wähle eine der folgenden:

  • 7

  • 5

  • 10

  • 8

  • 12

Erklärung

Frage 2 von 20

1

Which part of the stage of the RIBA Plan of Work 2013 is particularly relevant in the context of sustainability.

Wähle eine der folgenden:

  • Stage 4

  • Stage 1

  • Stage 0

  • Stage 7

  • Stage 5

Erklärung

Frage 3 von 20

1

Stage 6 is primarily concerned with?

Wähle eine der folgenden:

  • Post occupancy

  • Concept design

  • Preparation and brief

  • Hand over and close out

  • Developed design maps

Erklärung

Frage 4 von 20

1

What does BIM stand for

Wähle eine der folgenden:

  • Building Information Modelling

  • Business Information Modelling

  • Built Individual Model

  • Building In Materials

Erklärung

Frage 5 von 20

1

Which stage is a new stage in which a project is strategically appraised and defined before a detailed brief is created?

Wähle eine der folgenden:

  • Stage 4 Technical Design

  • Stage 5 Construction

  • Stage 0 Strategic Definition

  • Stage 3 Developed Design

Erklärung

Frage 6 von 20

1

Which stage of the RIBA plan of Work focuses on making sure the that the initial business case matches the desired outcomes.

Wähle eine der folgenden:

  • Stage 7 In use

  • Stage 0 Strategic definition

  • Stage 6 Handover and close out

  • Stage 3 Developed design

  • Stage 5 Construction

Erklärung

Frage 7 von 20

1

What is meant by the term procurement?

Wähle eine der folgenden:

  • The design and execution of the infrastructure .

  • The construction of an object or a system.

  • The acquisition of goods, services or works from an outside external source.

  • Preparing for and forming building systems.

Erklärung

Frage 8 von 20

1

Is The RIBA Plan of Work 2013 itself a contractual document?

Wähle eine der folgenden:

  • Yes

  • No

Erklärung

Frage 9 von 20

1

Within the RIBA Plan of work which task bars are fixed and always present?

Wähle eine der folgenden:

  • Task Bar 1 Core Objectives, Task Bar 3 Programme & Task Bar 8 Government Gateways.

  • Task Bar 8 Government Gateways, Task Bar 6 Sustainability Checkpoints & Task Bar 3 Programme

  • Task Bar 1 Core Objectives,Task Bar 5 Key Support Tasks, & Task Bar 7 Information Exchanges

  • Task Bar 6 Sustainability Checkpoints,Task Bar 4 (Town) Planning &Task Bar 2 Procurement

Erklärung

Frage 10 von 20

1

Which two task-bars can be switched on or off in The RIBA Plan of Work 2013?

Wähle eine der folgenden:

  • Task Bar 6 Sustainability Checkpoints & Task Bar 8 Government Gateways.

  • Task Bar 3 Programme & Task Bar 1 Core Objectives.

  • Task Bar 2 Procurement & Task Bar 5 Key Support Tasks,

  • Task Bar 8 UK Government Information Exchanges & Task Bar 6 Sustainability Checkpoints.

Erklärung

Frage 11 von 20

1

Which three task-bars are variable in The RIBA Plan of Work 2013?

Wähle eine der folgenden:

  • Task Bar 4 (Town) Planning, Task Bar 5 Key Support Tasks & Task Bar 1 Core Objectives.

  • Task Bar 2 Procurement ,Task Bar 3 Programme & Task Bar 8 Government Gateways.

  • Task Bar 3 Programme ,Task Bar 2 Procurement & Task Bar 4 (Town) Planning

  • Task Bar 6 Sustainability Checkpoints, Task Bar 1 Core Objectives & Task Bar 5 Key Support Tasks.

Erklärung

Frage 12 von 20

1

Why has the UK Government Information Exchanges task bar has been introduced?

Wähle eine der folgenden:

  • To encourage consideration of the stages that the UK Government requires information to be exchanged.

  • To provide guidance on the information that would typically be delivered at the Information Exchanges at the end of each stage.

  • To allow for a number of forms of procurement.

  • To underline the need on every project for a Project Programme that sets out the duration of each stage and any supporting activities.

Erklärung

Frage 13 von 20

1

What has been a core requirement of collaborative contracts for some time as it ensures that each party is involved in the process of agreeing timescales and is fully aware of the risks that the programme generates in relation to their specific Schedule of Services?

Wähle eine der folgenden:

  • Construction Programme

  • Design Programme

  • Building Contract

  • Project Programme.

Erklärung

Frage 14 von 20

1

On certain projects, where it is uncertain that consent will be granted, can the client appoint all of the designers or may appoint them on a restricted Stage 2 Schedule of Services?

Wähle eine der folgenden:

  • Yes

  • No

Erklärung

Frage 15 von 20

1

The Sustainability Checkpoints task bar is selectable and can be switched off?

Wähle eins der folgenden:

  • WAHR
  • FALSCH

Erklärung

Frage 16 von 20

1

Where detailed circumstances specific to a given project require an alternative approach, what should used to deal with this?

Wähle eine der folgenden:

  • Building Contract

  • Health and Safety Strategy

  • Project Programme.

  • Design Responsibility Matrix

Erklärung

Frage 17 von 20

1

What does the UK Government recognise that a client does not need to be involved in?

Wähle eine der folgenden:

  • Every Information Exchange

  • Data-rich information that can be used post- occupancy to manage its entire estate and to allow stringent benchmarking activities to occur.

Erklärung

Frage 18 von 20

1

Which task-bar sets out key tasks in relation to statutory requirements, such as those relating to Building Regulations submissions and project and design management protocols, roles and responsibilities?

Wähle eine der folgenden:

  • Task Bar 7 Information Exchanges

  • Task Bar 5 Key Support Tasks

  • Task Bar 1 Core Objectives

  • Task Bar 8 Government Gateways

Erklärung

Frage 19 von 20

1

It is also acknowledged that on certain projects (conservation projects, for example) other planning matters may have to be concluded during which other stage?

Wähle eine der folgenden:

  • Task Bar 5 Key Support Tasks

  • Task Bar 4 (Town) Planning

  • Task Bar 3 Programme

  • Task Bar 2 Procurement

Erklärung

Frage 20 von 20

1

The RIBA Plan of Work 2013 does all of the following Acts across the full range of sectors and project sizes: Provides straight-forward mapping for all forms of procurement.
Integrates sustainable design processes. Maps Building Information Modelling (BIM) processes and provides flexible around (town) planning procedures.

Wähle eins der folgenden:

  • WAHR
  • FALSCH

Erklärung