Frage 1 von 150

1

Which of the following is NOT an organizational process asset update during Close Project or Phase Process?

Wähle eine der folgenden:

  • a. Historical information.

  • b. Final deliverable.

  • c. Formal acceptance forms.

  • d. Project files.

Erklärung

Frage 2 von 150

1

Project Manager and Operations can intersect during:

Wähle eine der folgenden:

  • a. Ending of each phase or iteration.

  • c. During each project team evaluation.

  • d. Only during final training.

Erklärung

Frage 3 von 150

1

A project manager wants to determine how his Project is doing at the end of sixth month. The actual total expense of the Project is $720,000. He have work for $620,000. The planned Budget for this length of time was $600,000. He finds that:

Wähle eine der folgenden:

  • a. There is not enough information to determine how the Project is doing.

  • b. The project is slightly ahead and cost overrun.

  • c. The Project is behind schedule and with savings.

  • d. The Project is on track.

Erklärung

Frage 4 von 150

1

Influencing and Negotiation are examples of:

Wähle eine der folgenden:

  • a. Conflict management.

  • b. Project performance appraisals

  • c. .Interpersonal skills.

  • d. Problem solving

Erklärung

Frage 5 von 150

1

You are the Project manager for employee time management Project. As part of the work, the Project team is considering four different applications providing different functionality and reports. Which of the following will be you biggest concern?

Wähle eine der folgenden:

  • a. Schedule delay.

  • b. Scope creep.

  • c. Low quality.

  • d. Over Budget.

Erklärung

Frage 6 von 150

1

An estimating technique that uses a statistical relationship between historical data and other variables (for example, square footage in construction, lines of code in software development) is known as:

Wähle eine der folgenden:

  • a. Parametric Estimating

  • b. Analogous Estimating

  • c. Bottom-up Estimating

  • d. Historical Analysis

Erklärung

Frage 7 von 150

1

Success of which of the following is measured in terms of benefits realization?

Wähle eine der folgenden:

  • a. Operations

  • b. Portfolios

  • c. Programs

  • d. Projects

Erklärung

Frage 8 von 150

1

Which of the following is NOT a valid tool for risk identification??

Wähle eine der folgenden:

  • a. The Delphi Technique

  • b. Assumptions analysis

  • c. Pareto chart

  • d. SWOT analysis

Erklärung

Frage 9 von 150

1

While a Project management plan is one of the primary documents, other documents are used to direct support it. Some of them are:

Wähle eine der folgenden:

  • a. Quality management plan

  • b. Basis of estimates, cost and schedule forecast, Issue log.

  • c. Process improvement plan

  • d. Requirements management plan and Configuration management plan.

Erklärung

Frage 10 von 150

1

You are the Project manager of a software development project that has an approved Budget of $2,000,000. The Project started six months ago and has a total actual cost of $650,000 till now. After six months, the project suffered a really big change. The team must begin again analysis phase. The $650,000 is:

Wähle eine der folgenden:

  • a. Design cost.

  • b. Earned Value.

  • c. Sunk cost.

  • d. Cost variance.

Erklärung

Frage 11 von 150

1

All of the following are required to establish cost baseline EXCEPT:?

Wähle eine der folgenden:

  • a. Estimate Activity Resources

  • b. Control Cost

  • c. Estimate Cost

  • d. Determine Budget

Erklärung

Frage 12 von 150

1

You were invited to a meeting by a manager. When you entered the room you saw sitting there the key user working on your Project. The manager tells you that she has discusssed with the key user a change to the functionality being developed by your Project: they both agree that it should be changed from manual entry to system generated entry. He then asks you to fill out the required form and get it signed. What is going on?

Wähle eine der folgenden:

  • a. You are working like Coordinator

  • b. The management is actively involved in the Project.

  • c. This is a good example of integrated change control.

  • d. Manager is concerned with satisfying key stakeholders.

Erklärung

Frage 13 von 150

1

Thinking about identification of stakeholders for a project, which of the following statements is incorrect?

Wähle eine der folgenden:

  • a. Project may get into trouble if negative stakeholders are ignored.

  • b. Stakeholders with a positive approach help project manager succeed.

  • c. Stakeholders only can be individuals who participate in project task, like project team.

  • d. Various stakeholders may have opposing views on a project.

Erklärung

Frage 14 von 150

1

A project manager works with various stakeholders including stakeholders who do not support the project, mainly to overcome the resistance and gain the trust of those stakeholders. Which of the following skills did he use?

Wähle eine der folgenden:

  • a. Management

  • b. Negotiating

  • c. Interpersonal.

  • d. Writing

Erklärung

Frage 15 von 150

1

Which of the following BEST describes the difference between Project management process groups and Project life cycle phases?

Wähle eine der folgenden:

  • a. Project phases are repeated in Project management process groups but may also continue from one Project management process group to another.

  • b. Project management process groups are used in waterfall while Project phases are used in iterative.

  • c. Project management process groups are repeated in Project phases

  • d. Project management process groups and Project phases are the same thing.

Erklärung

Frage 16 von 150

1

The configuration management system with integrated change control provides a standaridized, effective and efficient way to centrally manage approved changes and baselines within a project. Configuration control is focused on:?

Wähle eine der folgenden:

  • a. Identification and correction of problems arising in functional areas of project implementation.

  • b. Specification of both the deliverables and de processes while change control is focused on identifying, documenting and controlling changes to the project and the product baselines.

  • c. Test new systems.

  • d. Identifying, documenting, and controlling changes to the project and the product baselines while change control is focused on the specification of both the deliverables and the processes.

Erklärung

Frage 17 von 150

1

A organizational structure is

Wähle eine der folgenden:

  • a. Part of the operation processes.

  • b. Part of the organizational system

  • c. An Organizational Process Asset.

  • d. A topic which depends of the project.

Erklärung

Frage 18 von 150

1

If you are looking at the work performance data to determine the project’s performance, what should you do NEXT?

Wähle eine der folgenden:

  • a. Update the lessons learned document.

  • b. Identify areas of improvement and create corrective actions.

  • c. Send the information to project sponsor

  • d. Compare the information you receive of the team performance with baselines and identify variances.

Erklärung

Frage 19 von 150

1

A project manager has just started a newly selected project and going through initial meeting with sponsor and other key stakeholders. One VicePresident (VP) who is a key stakeholder wants to know in this moment how much the project will cost and how long it will take. The project manager has just initiated the project and does not have details but still provides an estimate to the VP. Which technique did he use?

Wähle eine der folgenden:

  • a. Parametric estimate

  • b. Analogous estimate

  • c. Bottom- Up estimate

  • d. Ball park or personal estimate

Erklärung

Frage 20 von 150

1

To maintain the project scope under control, the project manager need to use:

Wähle eine der folgenden:

  • a. Documentation.

  • b. Inspection

  • c. Audits

  • d. Variance Analysis

Erklärung

Frage 21 von 150

1

A Project manager is in a meeting, trying to understand the governmental regulations use of water in this region. This is an example of:

Wähle eine der folgenden:

  • a. Enterprise environmental factor.

  • b. A Project.

  • c. Government requirement.

  • d. A program.

Erklärung

Frage 22 von 150

1

There is a serious defect in the finished product of a project that was completed a few months back and this results in a recall campaign to recall the defective products. What would be the best classification for these types of costs?

Wähle eine der folgenden:

  • a. Cost of Defects

  • b. Replacement of Costs

  • c. Recall Costs

  • d. Cost of Quality

Erklärung

Frage 23 von 150

1

Which of the following is NOT an input to the Conduct Procurements?

Wähle eine der folgenden:

  • a. Activity Cost Estimating.

  • b. Source selection criteria.

  • c. Procurement statement of work.

  • d. Make -or-buy analysis.

Erklärung

Frage 24 von 150

1

All of the following activities are included in Direct and Manage Project Work except:

Wähle eine der folgenden:

  • a. Create project deliverables.

  • b. Obtain, manage and use resources.

  • c. Establish communication channels external and internal to the project team.

  • d. Determine stakeholder communication requirements according to organizational culture.

Erklärung

Frage 25 von 150

1

Which process includes the implementation of the approved changes to achieve the project objectives?

Wähle eine der folgenden:

  • a. Perform Integrated Change Control

  • b. Monitor and Control Project Work

  • c. Direct and Manage Project Work

  • d. Develop Project Management Plan

Erklärung

Frage 26 von 150

1

Which of the following is an input to Control Stakeholder Engagement process?

Wähle eine der folgenden:

  • a. Work performance report

  • b. Work performance information

  • c. Work performance data

  • d. Work performance analysis.

Erklärung

Frage 27 von 150

1

In order to calculate the estimate at completion (EAC), the following is typically needed:?

Wähle eine der folgenden:

  • a. Cost Performance Index (CPI) and the Actual Cost (AC)

  • b. Actual Cost (AC) and Estimate to Complete (ETC) the unfinished work.

  • c. Earned Value (EV) and the Actual Cost (AC).

  • d. Cost Performance Index (CPI), actual cost (AC), and the Earned Value (EV).

Erklärung

Frage 28 von 150

1

The project team has just started breaking down the components of the Web development project in to smaller pieces that can easier manage. After doing this, what level of decomposition will they ultimately stop at:

Wähle eine der folgenden:

  • a. Validate Scope

  • b. Define Scope

  • c. Work packages

  • d. Define activities

Erklärung

Frage 29 von 150

1

A Project manager have the responsability to satisfy the needs of?

Wähle eine der folgenden:

  • a. Task needs, team needs and individual needs.

  • b. Excursively the customer needs.

  • c. The needs that sponsor defined.

  • d. The needs of team.

Erklärung

Frage 30 von 150

1

You have a seller working on a Time and Material contract. As per contract, two resources will work for 12 months on the project for a total cost of $180,000. However, the project took longer than expected and by the time it was completed, the two resources have been on the project for 18 months with a total cost of $250,000. What went wrong?

Wähle eine der folgenden:

  • a. Just like an initiative for finishing earlier, a penalty should have been proposed for delay

  • b. A maximum amount and time limit should have been established under the contract.

  • c. Fixed price contract, which is good for these kind of situations, should have been used.

  • d. Nothing went wrong since this was Time and Material contract under which resources charged for the time they worked on the project.

Erklärung

Frage 31 von 150

1

What is an histogram?

Wähle eine der folgenden:

  • a. An Histogram is the same as a Pareto chart and shows the aggregation of defects

  • b. An Histogram is a pie chart that shows the distribution of inspections during the execution phase

  • c. An Histogram is a bar graph that shows data out of control

  • d. An Histogram can show the number of defects by source or by component.

Erklärung

Frage 32 von 150

1

Which of the following is the information about the group of stakeholders included in the project charter?

Wähle eine der folgenden:

  • a. Stakeholders who are very interested in the project.

  • b. Stakeholders who will be directly involved in the project work.

  • c. Stakeholders who are affected by the project.

  • d. Executive level stakeholders.

Erklärung

Frage 33 von 150

1

A project manager is analyzing and evaluating non-conformities. He is planning to use the 80/20 principle. What does this represent?

Wähle eine der folgenden:

  • a. 80% of the problems are caused by 20% of the causes

  • b. 80% of the problems can be resolved while the remaining 20% have no solution

  • c. 20% of the problems can be resolved while the remaining 80% have no solution

  • d. 20% of the problems are caused by 80% of the causes

Erklärung

Frage 34 von 150

1

A project implemented several steps to improve customer satisfaction but the result from the next survey remained the same as before. How can the results be analyzed to find out why the steps did not make any improvement?

Wähle eine der folgenden:

  • a. Draw a control chart to see how many surveys results are outside limits.

  • b. Using root cause analysis to find what is still causing customer dissatisfaction.

  • c. Create a Pareto Chart to see what is the biggest dissatisfaction customer is having.

  • d. Perform quality audit to verify quality measurements.

Erklärung

Frage 35 von 150

1

You are the project manager of a project and have come up with a bar graph of problems and their frequencies. This kind of chart is called a :?

Wähle eine der folgenden:

  • a. Deming chart

  • b. Pareto chart

  • c. Ishikawa diagram

  • d. Control chart

Erklärung

Frage 36 von 150

1

A project-s approved Budget is $250,000 and planned Budget to date is $150,000, Actual Cost is $130,000. What will be the Cost Performance Index when Schedule Performance Index is 0.8?

Wähle eine der folgenden:

  • a. 120,000

  • b. 30,000

  • c. 1.08

  • d. 0.92

Erklärung

Frage 37 von 150

1

Disputes may arise between a buyer and a seller on a contract. There are several techniques that can be used to resolve such disputes. Which of the following is the sequence from most favorable to leas favorable technique to be used?

Wähle eine der folgenden:

  • a. Litigation, Mediation, Arbitration, Confirmation,

  • b. Negotiation, Mediation, Arbitration, Litigation.

  • c. Negotiation, Escalation, Mediation, Arbitration.

  • d. Negotiation, Arbitration, Mediation, Litigation.

Erklärung

Frage 38 von 150

1

Which of the following is an input to Manage Team?

Wähle eine der folgenden:

  • a. Project assignments defining the specific roles of the team.

  • b. Change request.

  • c. Work performance data.

  • d. Work performance standards.

Erklärung

Frage 39 von 150

1

A common way of representing the stakeholder management strategy is a _____________.?

Wähle eine der folgenden:

  • a. Communication strategy

  • b. Stakeholder register

  • c. Stakeholder analysis matrix

  • d. Power/interest grid

Erklärung

Frage 40 von 150

1

You are managing a gas pipeline river crossing project. The project involves drilling piles in the river bed to build a bridge to cross the gas pipeline over the river. The company have three large trailers for project execution. This trailers are consider:

Wähle eine der folgenden:

  • a. An organizational process asset of Direct and Manage Project Work.

  • b. Part of the seller equipment.

  • c. An Enterprise Environmental Factor of Direct and Manage Project Work.

  • d. A contingency reserve.

Erklärung

Frage 41 von 150

1

A market demand, a business need, and/or legal requirement are examples of:

Wähle eine der folgenden:

  • a. Reasons to hire a project manager

  • b. Reasons projects are iniciated

  • c. Reasons people or businesses become stakeholders

  • d. Reasons to sponsor a project

Erklärung

Frage 42 von 150

1

A project schedule has activities and milestones. What do you know about milestones?

Wähle eine der folgenden:

  • a. Activities are summed up into milestones.

  • b. Milestones are required to created a valid schedule.

  • c. WBS work packages are also know as milestones.

  • d. Milestones can be a sponsor’s requirements.

Erklärung

Frage 43 von 150

1

Which of the following normally provides the summary milestone schedule?

Wähle eine der folgenden:

  • a. Project requirements document.

  • b. Business case.

  • c. Project scope statement.

  • d. Project charter.

Erklärung

Frage 44 von 150

1

Mr. PM has been working on the Enterprise learning management system Project for 10 months with a fairly large team. Yesterday, the new system was made available to the whole organization with only one glitch viz. The mass email with incorrect login and password was sent out to all the employees. The Project team worked on the issue diligently and within 4 hours sent out the correct email to everyone. Mr. PM met his manager on his way to the office this morning. The manager remarked “I am very disappointed”. What could be the reason?

Wähle eine der folgenden:

  • a. Mr. PM did not go through Integrated Change Control Process to fix the issue.

  • b. Mr. PM did not mention his manager«s name in the email sent out to the whole organization thanking the team for hard work.

  • c. The manager had received regular updates from Mr. PM on the preventive measures being taken to ensure email goes out smoothly to the whole organization but still a supposedly prevented defect occurred.

  • d. Mr. PM did not ask manager`s permission if the problem should be fixed or not.

Erklärung

Frage 45 von 150

1

You are the Project manager for process automation project of a fast food company with 20 restaurants. As part of the work, the project team is collecting requirements of different functionality. Which of the following will be you biggest concern?

Wähle eine der folgenden:

  • a. Schedule delay.

  • b. Scope creep.

  • c. Quality assurance.

  • d. Close Procurements.

Erklärung

Frage 46 von 150

1

The inflation in a country is an important aspect when sponsor and project manager are reviewing a Project Charter. It is consider:

Wähle eine der folgenden:

  • a. A requirement of the project success.

  • b. A measurable objective.

  • c. An Organizational Process Asset.

  • d. An Enterprise Environmental Factor.

Erklärung

Frage 47 von 150

1

The Cost Performance Baseline is a time phased budget and is used as a basis to measure, monitor and control overall cost performance of the project. It is usually displayed in the form of:?

Wähle eine der folgenden:

  • a. A Z curve

  • b. An inverted S curve

  • c. Pie-chart

  • d. An S-curve

Erklärung

Frage 48 von 150

1

A Project manager is managing three project simultaneously. These three projects, A, B, and C are related to each other, Project A is to customize a software application X, Project B is to deploy X to the whole organization and C is to train users according to their roles in X. How would you describe the situation??

Wähle eine der folgenden:

  • a. This is an operational work and should not be considered Project.

  • b. He is managing one Project, which has three phases.

  • c. Project B should start after Project A and Project C after Project B.

  • d. He is managing a program with three inter-related projects.

Erklärung

Frage 49 von 150

1

What does consultants, professionals and technical associations provide during project execution?

Wähle eine der folgenden:

  • a. Deliverable status

  • b. Work performance data

  • c. Expert judgment

  • d. Issue management procedures

Erklärung

Frage 50 von 150

1

What is the process of random selection and inspection of a work product?

Wähle eine der folgenden:

  • a. Control Charting

  • b. Flow Charting

  • c. Statistical Sampling

  • d. Inspection

Erklärung

Frage 51 von 150

1

A project manager issued a purchase order to a seller to provide catering service during a major event. The event is three day meeting to be held for requirements gathering. The project manager is in which of the following processes?

Wähle eine der folgenden:

  • a. Plan Procurement Management

  • b. Prepare Procurements

  • c. Conduct Procurements

  • d. Control Procurements.

Erklärung

Frage 52 von 150

1

Which of the following processes best facilitates lessons learned document?

Wähle eine der folgenden:

  • a. Plan Communications Management.

  • b. Identify Stakeholders.

  • c. Manage Quality

  • d. Plan Quality Management.

Erklärung

Frage 53 von 150

1

The team is in the process of completing the Work Breakdown Structure of the project. Once they have completed this, which of the following can they begin to work on?

Wähle eine der folgenden:

  • a. Estimate Cost

  • b. Develop Schedule

  • c. Estimate Activity Durations

  • d. All of the answers

Erklärung

Frage 54 von 150

1

What tool does Project Manager could use if he wants to reduce the sensivility of product performance to variations caused by environmental differences?

Wähle eine der folgenden:

  • a. Design of Experiments (DOE)

  • b. Benchmarking

  • c. Statistical Sampling

  • d. Pareto Diagram

Erklärung

Frage 55 von 150

1

A project's approved Budget is $250,000 and planned Budget to date is $150,000. What will be the Schedule Variance when Schedule Performance Index is 0.8?

Wähle eine der folgenden:

  • a. 50,000

  • b. 30,000

  • c. -50,000

  • d. -30,000

Erklärung

Frage 56 von 150

1

A team member is really confused about the priorities of their assigned job because he receives orders from Project Manager and from functional Manager, and doesn't know to whom listen. He is living the typical effect of:

Wähle eine der folgenden:

  • a. The Matrix structure in organization communication problems.

  • b. The organizational process assets of the project.

  • c. The inexperience.

  • d. The lack of requirements management process.

Erklärung

Frage 57 von 150

1

Which of the following is NOT a typical characteristic of a project management office (PMO)?

Wähle eine der folgenden:

  • a. Developing and managing project management methodology and standards.

  • b. Coaching and training project managers.

  • c. Managing projects resources and assigning project tasks.

  • d. Defining and maintaining vendor engagement processes.

Erklärung

Frage 58 von 150

1

Which is the main difference between project expediter and project coordinator??

Wähle eine der folgenden:

  • a. The expediter have more responsibility than the coordinator

  • b. A project expediter works as staff assistant and coordinator works in operational activities.

  • c. Project coordinators have power to make some decision, have some authority

  • d. Project coordinator have less work than project expediter.

Erklärung

Frage 59 von 150

1

What is the output of a decision tree analysis?

Wähle eine der folgenden:

  • a. List of decisions that can be made.

  • b. Expected monetary value of each option.

  • c. Recommended corrective actions.

  • d. Cost of managing the risk that was analyzed,

Erklärung

Frage 60 von 150

1

Your project has completed its 50% deliverables and is in the middle of execution. You created a stakeholder register during initiating process which was then used to create a stakeholder management strategy. You have been managing stakeholders according to this strategy. Now, you have recently become aware of a highly influential stakeholder that has not been identified in the stakeholder register. What is the BEST course of action?

Wähle eine der folgenden:

  • a. Ask the project sponsor if this person be included in the stakeholder register.

  • b. Send a request to senior management asking for direction.

  • c. Update stakeholder register and stakeholder management strategy with the new information.

  • d. Inform the stakeholder that it is too late for him to be involved in the project as the stakeholder register was completed during initiating process.

Erklärung

Frage 61 von 150

1

You are a Project manager working on new product development Project. You have a long-term contract with a reputed seller. Under the contract, the seller is charging you $50 per hour per resource engaged on your Project and $200 per week as overhead charges. You have a ­­­­­­­­­____________ contract with the seller.?

Wähle eine der folgenden:

  • a. Cost reimbursable.

  • b. Fixed Price.

  • c. Time and material.

  • d. Cost plus fixed fee.

Erklärung

Frage 62 von 150

1

Which of the following is an input to Control Stakeholder Engagement process??

Wähle eine der folgenden:

  • a. Work performance report

  • b. Work performance information

  • c. Work performance data

  • d. Work performance analysis.

Erklärung

Frage 63 von 150

1

A project manager is unsure of the difference between precision and accuracy and asks for your help in understanding the difference between the two terms. Which of these responses would be the best response to such a question?

Wähle eine der folgenden:

  • a. Precision is consistency that the value of a repeated set of measurements are clustered and have little scatter whereas accuracy is correctness that the measured value is very close to the true value

  • b. Accuracy is consistency that the value of a repeated set of measurements are clustered and have little scatter whereas precision is correctness that the measured value is very close to the true value

  • c. Accuracy and Precision are equivalent and normally specified in the SOW by the customer who issues the SOW

  • d. Accuracy is more important than precision. The project management team must decide the level of accuracy required

Erklärung

Frage 64 von 150

1

Which is one objective of Critical Path Method (CPM)?

Wähle eine der folgenden:

  • a. Define the possible activity paths in the project.

  • b. Determine the amount of scheduling flexibility .

  • c. Identify the resources needed in critical activities.

  • d. Identify the most important activities, for example, director meetings.

Erklärung

Frage 65 von 150

1

ABC company is a important manufacturing firm. They are looking for a experiment project manager for a critical project . They consult to you about that aspects the firm should consider in order to evaluate candidates for this important position. What recommendation would you do to them:

Wähle eine der folgenden:

  • a. To apply a really difficult knowledge exam to evaluate his knowledge in project management.

  • b. Prepare a real case and stress the candidate to evaluate his leadership in real situations. Personal skills are really important.

  • c. Evalate his conflict resolution habilities, because projects are conflictive situations, mainly during execution phase, when project plan could change.

  • d. To evaluate his knowledge in project management, their experience in applying this knowlege in real projects and his personal competences like leadership, communications, etc.

Erklärung

Frage 66 von 150

1

For effective risk management, project risk ______________.?

Wähle eine der folgenden:

  • a. Should be identified whether they are expected to have positive or negative outcome.

  • b. Acceptance is the best strategy.

  • c. Should be identified, deeply analyzed and responded at the beginning of the project.

  • d. Should continue to be tracked even after it has occurred.

Erklärung

Frage 67 von 150

1

Project manager and his team is talking about the stakeholders management and the must important objective of that. They conclude to assign more priority to:

Wähle eine der folgenden:

  • a. Visit all stakeholders identified to report project status

  • b. Send reports to key stakeholders.

  • c. Avoid conflicts among stakeholders.

  • d. Compromise them and manage their satisfaction.

Erklärung

Frage 68 von 150

1

Which of the following are part of the Organizational Process Asset of Direct and Manage Project Work:

Wähle eine der folgenden:

  • a. Organizational culture.

  • b. Infrastructure, existing facilities and capital equipment.

  • c. Stakeholder risk tolerances.

  • d. Communication requirements defining allowed communication media, record retention and security requirements.

Erklärung

Frage 69 von 150

1

When managing a medical research project, what should you focus on during the Executing processes?

Wähle eine der folgenden:

  • a. Measuring progress.

  • b. Performing the Project work.

  • c. Conflict resolution.

  • d. Coordinating human and other resources.

Erklärung

Frage 70 von 150

1

Organizational Process assets that are updated during the Close Project or Phase process are:?

Wähle eine der folgenden:

  • a. Business case.

  • b. Project management plan, expert judgment.

  • c. Project management plan, project calendars

  • d. Project charter

Erklärung

Frage 71 von 150

1

Which of the following will have the BIGGEST impact in making project a success?

Wähle eine der folgenden:

  • a. Expert level technical knowledge.

  • b. Clear roles and responsibilities.

  • c. Co-located project team

  • d. Highly experienced project manager

Erklärung

Frage 72 von 150

1

What is an output of the Close Procurements process that the buyer provides to the seller?

Wähle eine der folgenden:

  • a. A copy of the lessons learned document

  • b. Written notice of acceptance of all deliverables and completion of contract.

  • c. Project management plan updates

  • d. Letter of appreciation to the seller.

Erklärung

Frage 73 von 150

1

You and your team celebrate, as part of the management process, a weekly meeting to review their practices about work, communication and project team management. The main objective of it is:

Wähle eine der folgenden:

  • a. To gain confidence from the key stakeholders

  • b. To evaluate the team

  • c. To achieve the project objectives and contribute to organizational learning.

  • d. To collect work performance data.

Erklärung

Frage 74 von 150

1

A project manager is working on office space refresh project. While using earned value technique, he determines that the project will run over budget by $2,000 if current performance trend continues. The project manager has used ­­­­­­­­­­___________ characteristics to identify the issue.?

Wähle eine der folgenden:

  • a. Interpersonal

  • b. Knowledge

  • c. Problem solving

  • d. Earned Value.

Erklärung

Frage 75 von 150

1

When the project manager is looking for providers, one source selection criteria are all except:

Wähle eine der folgenden:

  • a. Management approach and experience

  • b. Past performance and references.

  • c. The format of SOW they use.

  • d. Product cost and life cycle cost

Erklärung

Frage 76 von 150

1

The technique of comparing actual or planned project practices to those of other projects to generate ideas for improvement and to provide a basis by which to measure performance is known as:?

Wähle eine der folgenden:

  • a. Workbench

  • b. Benchmarking

  • c. Quality Control

  • d. Best Practices

Erklärung

Frage 77 von 150

1

A project manager wants to determine how his Project is doing at the end of sixth month. The actual total expense of the Project is $720,000. The planned Budget for this length of time was $600,000. He finds that:

Wähle eine der folgenden:

  • a. The Project is over-budget.

  • b. There is not enough information to determine how the Project is doing.

  • c. The Project is a head of Schedule.

  • d. The Project is on track.

Erklärung

Frage 78 von 150

1

Status reports, memos and information notes are examples of:

Wähle eine der folgenden:

  • a. Work Performance Information.

  • b. Project management Plan Updates.

  • c. Work performance reports.

  • d. Project Management Information System (PMIS).

Erklärung

Frage 79 von 150

1

A project is estimated to cost $50,000 with a timeline of 50 days. After 25 days, the porject manager finds that 50% of the project is complete and Actual costs are $50,000. What is the Cost Performance Index (CPI)?

Wähle eine der folgenden:

  • a. CPI is 1

  • b. CPI is 1.5

  • c. CPI is 2

  • d. CPI is 0.5

Erklärung

Frage 80 von 150

1

Which of the following is NOT a valid tool for risk identification?

Wähle eine der folgenden:

  • a. Braingstorming

  • b. Assumptions analysis

  • c. Histogram chart

  • d. SWOT analysis

Erklärung

Frage 81 von 150

1

If a project’s actual total cost is $300,000 against a total budget of $400,000 and the project is 75% complete, then what is the earned value?

Wähle eine der folgenden:

  • a. Cannot be determined from the information given.

  • b. 0.75

  • c. 300,000

  • d. 100,000

Erklärung

Frage 82 von 150

1

A project manager has been assigned to a project that is in trouble. He is going to focus his attention on:

Wähle eine der folgenden:

  • a. Controlling procurement.

  • b. Schedule because on-time delivery is most important.

  • c. Communication because good communication ensure Project success.

  • d. Factors that have the biggest impact on meeting Project objectives.

Erklärung

Frage 83 von 150

1

Business value is defined as:

Wähle eine der folgenden:

  • a. The cost of their buildings, infrastructure and furniture.

  • b. The net quantifiable benefit derived from a business endeavor. The benefit may be tangible, intangible or both.

  • c. The knowledge base and the experience of the project team

  • d. The cash flow at the end of the project.

Erklärung

Frage 84 von 150

1

Which of the following is NOT an input to the Plan Procurement Management Process?

Wähle eine der folgenden:

  • a. Work performance data

  • b. Project scope statement

  • c. Work breakdown structure

  • d. Stakeholder register

Erklärung

Frage 85 von 150

1

Which of the following statements is TRUE concerning functionality that is over and above the documented scope?

Wähle eine der folgenden:

  • a. It should be channeled back through the change control board to ensure that it gets documented into the project scope

  • b. Additional functionality should be leveraged to exceed customer expectations.

  • c. The final product should include all the functionality and only the functionality documented in the scope baseline.

  • d. Additional functionality should be issued by the customer, reviewed by the project manager and approved for implementation.

Erklärung

Frage 86 von 150

1

One of the inputs you need to close a project is:
Direct and Manage project work activities include?

Wähle eine der folgenden:

  • a. Document analysis

  • b. Variance analysis

  • c. A final report

  • d. Configuration management knowledge base

Erklärung

Frage 87 von 150

1

All of the following are correct statements about the contract change control system EXCEPT:?

Wähle eine der folgenden:

  • a. Buyer and seller both can submit a change request to the contract change control system.

  • b. Contract change control system is mainly used during the Control Procurements process

  • c. Contract change control system should be defined separately from the terms of the contract.

  • d. Contract change control system is an Enterprise Environmental Factor, and is part of the Project’s integrated change control system.

Erklärung

Frage 88 von 150

1

The project manager and the project management team are in a meeting reviewing the scope baseline and the validated products to ensure competition of the project, and use for it a trend analysis method. Which process are the project manager doing?

Wähle eine der folgenden:

  • a. Validate Scope.

  • b. Define Scope.

  • c. Perform Integrated Change Control.

  • d. Close Project or Phase.

Erklärung

Frage 89 von 150

1

When an organization rejects a project because it is not aligned to its strategy, they:

Wähle eine der folgenden:

  • a. Improve their revenue.

  • b. Reject a non profit projects.

  • c. Improve business value using Portfolio Mangement techniques.

  • d. Adverse to risk.

Erklärung

Frage 90 von 150

1

All of the following are characteristics of the project management information system (PMIS) EXCEPT:

Wähle eine der folgenden:

  • a. Inculde a standardized set of automated tools available within the organization and integrated into a system.

  • b. It is used by the project management team to support generation of the project management plan, facilitate feedback as the document is developed, control changes to the project management plan, and release the approved document.

  • c. It is used by the project management team to monitor and control the execution of activities that are planned and scheduled in the project management plan. The PMIS is also used to create new forecasts as needed.

  • d. It is used by the project management team only to generate presentations to key stakeholders.

Erklärung

Frage 91 von 150

1

Funding requirements for a project are usually in incremental amounts that are not continuous , and these appear as a step function in the graph depicting Cash flow, Cost baseline and Funding. Any gap at the end of the project, between funds allocated and the cost baseline and cash flow amounts represents:

Wähle eine der folgenden:

  • a. The amount of management reserve that was not used

  • b. The amount of management reserve that was not allocated

  • c. The cost overrun

  • d. Innefective utilization of funds

Erklärung

Frage 92 von 150

1

You are the Project manager of a design build Project that has an approved Budget of $1,000,000. The Project started eight months ago and has a total actual cost of $650,000 till now. The $650,000 is the:

Wähle eine der folgenden:

  • a. Design cost.

  • b. Earned Value.

  • c. Expended cost.

  • d. Cost variance.

Erklärung

Frage 93 von 150

1

A finales del mes de marzo, con unos seis meses de ejecución del proyecto, el cliente nos solicita comparar el desarrollo del trabajo con la línea base. Esta línea base servirá para realizar la comparación en el/los proceso/s de:?

Wähle eine der folgenden:

  • a. Validar el Alcance

  • b. Controlar el Alcance

  • c. Validar el Alcance y Controlar el Alcance

  • d. Revisar el Alcance y análisis de stakeholders

Erklärung

Frage 94 von 150

1

Lucy is a project manager involved in the Estimate Costs process in the initiation phase of a project. Given the limited detail available to her, what would you expect the range of her estimate to be and what would you call such an estimate?

Wähle eine der folgenden:

  • a. -25% to +25%, Rough Order of Magnitude

  • b. -10 to +10% , Budgetary

  • c. -1% to +1%, Definitive

  • d. -25% to +75% , Order of Magnitude

Erklärung

Frage 95 von 150

1

A business case includes all of the follow, except:

Wähle eine der folgenden:

  • a. Business needs

  • b. Analysis of the situation

  • c. Organizational culture.

  • d. Options identification

Erklärung

Frage 96 von 150

1

You are a project manager working on a global project with project team members distributed in four continents. Which of the following can help you the MOST to be successful?

Wähle eine der folgenden:

  • a. Knowledge of local languages and customs

  • b. Instant messaging & email

  • c. Well developed virtual communications skills

  • d. Responsibility Assignment Matrix.

Erklärung

Frage 97 von 150

1

Mr. PM and the project management team are learning project management best practices. The team are performing really well. They celebrated only one stakeholders identification session before project kick off. Their mentor is not satisfied with stakeholder management practices mainly because:

Wähle eine der folgenden:

  • a. Project Management Team didn`t identify all stakeholders.

  • b. Mr. PM did not explain to stakeholders the integrated change control.

  • c. Mr. PM and the team celebrated stakeholder identification only one time and this proces must be a continuous process throughout the project.

  • d. Mr. PM didn´t asked manager`s permission to change stakeholder list.

Erklärung

Frage 98 von 150

1

If you have to choose one of the following as NOT being a project, which one will it be??

Wähle eine der folgenden:

  • a. Building a 10 ft. x 15 ft. shed in your backyard.

  • b. Creating a project management office in the IT department.

  • c. Increasing parking spaces from 300 to 400 in a parking lot.

  • d. Shipping 10 times larger than usual order received through internet.

Erklärung

Frage 99 von 150

1

Which of the following tools is used during Plan Quality?

Wähle eine der folgenden:

  • a. Control Charts

  • b. Scatter Diagram

  • c. Mind maping

  • d. Cause and Effect Diagram

Erklärung

Frage 100 von 150

1

Thinking about identification of stakeholders for a project, which of the following statements is incorrect?

Wähle eine der folgenden:

  • a. Project may get into trouble if negative stakeholders are ignored.

  • b. Stakeholders with a positive approach help project manager succeed.

  • c. Various stakeholders may have opposing views on a project.

  • d. Manage the expectations of positive stakeholders should have a higher priority than the negative stakeholders.

Erklärung

Frage 101 von 150

1

Which one of the following is NOT an input to Develop Project Charter process?

Wähle eine der folgenden:

  • a. Enterprise environmental factors

  • b. Expert judgment

  • c. Business case

  • d. Statement of work

Erklärung

Frage 102 von 150

1

Which project management process will you use if you find out that the task needed to accomplish a work package are not valid?

Wähle eine der folgenden:

  • a. Integrated change control

  • b. Corrective action

  • c. Preventive action

  • d. Monitor and control project work

Erklärung

Frage 103 von 150

1

The project team has decided that a preventive action must be taken to solve an possible deviation. What are they referring to?

Wähle eine der folgenden:

  • a. They are referring to an activity that can help eliminate performance of the desired state.

  • b. They are referring to an activity that can help lessen the chances of negative outcomes of actions.

  • c. They are referring to an activity that can help repair the chances of negative impacts.

  • d. They are referring to an activity that can help improve performance back to the desired state.

Erklärung

Frage 104 von 150

1

What is an output of Control Procurements process?

Wähle eine der folgenden:

  • a. Work performance report

  • b. Work performance information

  • c. Resource calendars

  • d. Source selection criteria

Erklärung

Frage 105 von 150

1

As Project manager for a new product development Project, you read a report on hot costumer trends for the next decade. You realize that your product lacks some of those aspects. After review and discussion with the business and the marketing department, changes were approved to the product specifications. Why did this charge occur?

Wähle eine der folgenden:

  • a. Because an external factor has impacted your Project.

  • b. Because scope was not well defined.

  • c. Because your Project Budget does not allow lavish spending

  • d. Because requirements were incorrect

Erklärung

Frage 106 von 150

1

What happens in the Monitor and Control Project Work process?

Wähle eine der folgenden:

  • a. Planned work as per Project management plan is completed.

  • b. Actual project performance is compared with the baselines.

  • c. Actual project performance is compared with schedule performance baseline.

  • d. Planned Project performance is compared with the Budget baseline.

Erklärung

Frage 107 von 150

1

Which of the following relates to Root Cause Analysis?

Wähle eine der folgenden:

  • a. Process Analysis

  • b. Performance Measurements

  • c. Quality Audits

  • d. Quality control measurements

Erklärung

Frage 108 von 150

1

Project manager is preparing the procurement issues. He is finding out what kind of construction permissions they must have to develop the project. He is considering:

Wähle eine der folgenden:

  • a. The organizational process assets of the project.

  • b. How to prepare the final budget of the project.

  • c. Enterprise Environmental Factors of the project.

  • d. He is preparing to select sellers.

Erklärung

Frage 109 von 150

1

Which of these are not inputs to the Determine Budgets process??

Wähle eine der folgenden:

  • a. Cost Baseline, Requirements traceability matrix

  • b. Project schedule, contracts

  • c. Basis of estimates, Activity cost estimates

  • d. Project schedule, Resource calendars

Erklärung

Frage 110 von 150

1

Right after you received final deliverable approval from the sponsor of your Project, you were assigned to a new Project and asked to skip the closing process for current Project. For which kind of Project can you skip the closing processes?

Wähle eine der folgenden:

  • a. Large Projects.

  • b. Administrative Projects.

  • c. Closing processes should not be skipped for any kind of Project.

  • d. Small projects.

Erklärung

Frage 111 von 150

1

A characteristic of the Project Life Cycle is:

Wähle eine der folgenden:

  • a. Always are identical, in all kind of industries

  • b. Risk and uncertainly are highest at the end of the project

  • c. Cost and staffing levels are low at the start, peak as the work is carried out, and drop rapidly as the project draws to a close.

  • d. The cost and staffing are the same regardless of the type of project

Erklärung

Frage 112 von 150

1

A Project manager working on highway extension Project finds out that noise barriers are required to be approved by the provincial highway authority before the work can proceed. The company does have a defined process and forms to go through the approval process. This defined process can be called as?

Wähle eine der folgenden:

  • a. Enterprise Environmental Factor.

  • b. A Project.

  • c. Government requirement.

  • d. A program.

Erklärung

Frage 113 von 150

1

Which of the following is not part of the Project Management Plan?

Wähle eine der folgenden:

  • a. Configuration management plan.

  • b. Basis of estimates.

  • c. Risk management plan.

  • d. WBS dictionary.

Erklärung

Frage 114 von 150

1

You are the project manager of a network replacement Project for a 40-floor office building. You plan to hire a contractor to pull the old cables out and then install the new cables. The work has to be done in such a way to have minimum to zero disruption to the tenant organization during business hours, hence you need to hire a well experienced reputed firm. You contract the procurement department to develop a list of firms that have the capability to do the work. What are you referring to?

Wähle eine der folgenden:

  • a. Develop evaluation criteria.

  • b. Negotiating a contract.

  • c. Solicitation package to be sent out to prospective sellers.

  • d. Qualified sellers list

Erklärung

Frage 115 von 150

1

What is the name of the technique that examines the problems experienced within the project, limitations faced, and the feeling of non-value-added work?

Wähle eine der folgenden:

  • a. Scatter diagram.

  • b. Quality audit.

  • c. Process analysis.

  • d. Quality assurance.

Erklärung

Frage 116 von 150

1

Acquiring, training, and managing team members that have been assigned to the project are part of which process??

Wähle eine der folgenden:

  • a. Direct and Manage Project Work.

  • b. Acquire Project Team.

  • c. Monitor and Control Project Work.

  • d. Manage Team.

Erklärung

Frage 117 von 150

1

As a project manager, you periodically do project performance reviews to compare cost performance over time, schedule activities or work packages over-running and under-running budget, milestones due, and milestones met. Which of the following is not a valid technique that you would use for performance-reporting?

Wähle eine der folgenden:

  • a. Trend Analysis

  • b. Earned Value Performance

  • c. Variance Analysis

  • d. Integration Analysis

Erklärung

Frage 118 von 150

1

A Sara le han pedido que se haga cargo del desarrollo e implementación de un sistema de planificación de recursos organizacionales para su empresa. Sara ha enviado una solicitud para reunirse con el patrocinador del proyecto y discutir sobre la planificación de la gestión de los interesados. El patrocinador piensa que tal planificación no es importante en proyectos internos como el que está llevando Sara; sin embargo él piensa que únicamente con planificar bien la gestión del alcance, el cronograma y los costos es suficiente para este tipo de proyectos. El patrocinador le ha pedido a Sara describir el objetivo de la reunión. ¿Cuál de las siguientes es la mejor respuesta para el patrocinador??

Wähle eine der folgenden:

  • a. El objetivo de la reunión es desarrollar el registro de los interesados del proyecto.

  • b. El objetivo de la reunión es la de desarrollar las estrategias para efectivamente gestionar las expectativas de los interesados en el proyecto y lograr su participación eficaz durante el proyecto.

  • c. El objetivo de la reunión es cumplir con los estándares dictados por el PMBOK.

  • d. El objetivo de la reunión es la de identificar y clasificar a las interesados del proyecto.

Erklärung

Frage 119 von 150

1

Which of the following is an input to Manage Stakeholder Engagement process??

Wähle eine der folgenden:

  • a. Issue log

  • b. Change log

  • c. Change request

  • d. Work performance data

Erklärung

Frage 120 von 150

1

Project Manager is calculating SPI and SV (Schedule Variance) in order to determine if the project is still within the tolerances defined by client. He will use this information to:

Wähle eine der folgenden:

  • a. Evaluate the project team.

  • b. Prepare a change request.

  • c. Define project forecast.

  • d. Prepare provider payments.

Erklärung

Frage 121 von 150

1

You find it very valuable to attend the regular monthly Project management training session. Most Project managers at your office share your view and make effort to attend these sessions. It was mentioned in the last session that improvement in Project management practice has been observed since the start of these training sessions a year ago. The PMO manager is quite pleased with these results because:?

Wähle eine der folgenden:

  • a. Training, coaching and mentoring is one of the functions of PMO.

  • b. Stage gate review can be scheduled to enable Project to proceed to next phases.

  • c. Resources can be managed by Project managers.

  • d. More strategic projects can be initiated.

Erklärung

Frage 122 von 150

1

You are working as a seller’s Project manager for a buyer on a cost reimbursable contract. The buyer wants to add scope to the current statement of work and also wants to change the contract to a Fixed Price one. You have all of the following options available EXCEPT:?

Wähle eine der folgenden:

  • a. Since the buyer wants a fixed prices contract, negotiate one that includes all the work that is still to be performed.

  • b. Negotiate a new Fixed Price contract for the additional scope but stay on cost reimbursable for the original statement of work

  • c. Negotiate with buyer to restart the whole Project with a fixed Price contract so that a dispute can be avoided.

  • d. Refuse to do the additional work but complete the original work under the cost reimbursable contract.

Erklärung

Frage 123 von 150

1

Which of the following is an input to Manage Project Team?

Wähle eine der folgenden:

  • a. Work performance reports

  • b. Work performance information

  • c. Work performance data

  • d. Work performance standards

Erklärung

Frage 124 von 150

1

A variance threshold for costs or other indicators to indicate the agreed amount of variation allowed is called:

Wähle eine der folgenden:

  • a. Variance limits

  • b. Control threshold

  • c. Cost limit

  • d. Acceptable Threshold

Erklärung

Frage 125 von 150

1

The information of the project management plan used to control scope is all of follow, except:

Wähle eine der folgenden:

  • a. Change management plan

  • b. Expert judgement.

  • c. Configuration management plan.

  • d. Requirements management plan.

Erklärung

Frage 126 von 150

1

Your project is mid-way through a delivery schedule. As project manager, you want to understand how much work is left. Which is the most accurate way to determine the remaining work to be done by the project team?

Wähle eine der folgenden:

  • a. Rolling wave method

  • b. Earned Value Analysis

  • c. A manual forecast

  • d. Future analysis

Erklärung

Frage 127 von 150

1

An automotive designer uses a certain technique to determine which combination of suspension and tires will produce the most desirable ride characteristics at a reasonable cost. In order to do this, she works with a statistical framework and systematically changes all of the important parameters instead of changing the factors one at a time. This is known as:

Wähle eine der folgenden:

  • a. Design for X

  • b. Root cause analysis

  • c. Design of Quality

  • d. Design of Automobiles

Erklärung

Frage 128 von 150

1

You are the project manager of a building construction project. One of the routine meetings you have is a weekly meeting with project team where each team member provides you with how much work they have completed on assigned task and what are the measurements from quality tests. What are these examples of?

Wähle eine der folgenden:

  • a. Time and cost estimating.

  • b. Earned value analysis.

  • c. Perform quality audits.

  • d. Work performance data.

Erklärung

Frage 129 von 150

1

What does consultants and professionals and technical associations provide during project execution??

Wähle eine der folgenden:

  • a. Deliverable status

  • b. Work performance data

  • c. Expert judgment

  • d. Issue management procedures

Erklärung

Frage 130 von 150

1

As a project manager on a software development project for a customer, you have received an advice from customer that they want deliverable-based invoices. This means you will have to track the costs by each piece of work done. The system within your organization is setup to capture costs by resources, which means the total cost of the project at a certain instance is derived from cost booked against the project of the resources. What should you do?

Wähle eine der folgenden:

  • a. Only track cost as requested by customer.

  • b. Follow internal procedures and refuse customer.

  • c. Track costs both ways to fulfill internal and external requirements.

  • d. Evaluate to find out cost of complying with customer's demand.

Erklärung

Frage 131 von 150

1

Contingency Reserves are estimated costs to be used at the discretion of the project manager to deal with:?

Wähle eine der folgenden:

  • a. Inadequacies in the original estimate

  • b. Anticipated but not certain events

  • c. Unanticipated events

  • d. Anticipated and certain events

Erklärung

Frage 132 von 150

1

You are in charge of a new important project with a lot of uncertainty scenarios in front. Which practice do you choose an why?

Wähle eine der folgenden:

  • a. Predictive approach.

  • b. Iterative scheduling with a backlog to define scope gradually

  • c. Leveling resources to avoid uncertainty assuring enough resources.

  • d. Standard deviation to tells your boss the state of the project.

Erklärung

Frage 133 von 150

1

You were invited to a meeting by a manager. When you entered the room you saw sitting there the key user working on your Project. The manager tells you that she has discussed with the key user a change to the functionality being developed by your Project: they both agree that it should be changed from manual entry to system generated entry. He then asks you to fill out the required form and get it signed. What is going on?

Wähle eine der folgenden:

  • a. You are working as Project expediter.

  • b. The management is actively involved in the Project.

  • c. This is a good example of integrated change control.

  • d. Manager is concerned with satisfying key stakeholders.

Erklärung

Frage 134 von 150

1

You have received a statement of work (SOW) from the customer. You will be using this SOW as an input when you are creating the project charter. Which of the following is NOT a reason why you received the SOW from the customer?

Wähle eine der folgenden:

  • a. It was part of the proposal.

  • b. You requested information from the customer

  • c. It was part of the contract

  • d. It was part of the scope statement

Erklärung

Frage 135 von 150

1

Which information flows from Direct and Manage Project Work process to Develop Project Management Plan process??

Wähle eine der folgenden:

  • a. Work performance information

  • b. Deliverables

  • c. Project management plan updates

  • d. No such information flow occurs.

Erklärung

Frage 136 von 150

1

What is the purpose of reviewing a defect repair Which of the following BEST describes defect repair review?

Wähle eine der folgenden:

  • a. To ensure the defect was repaired properly and as required.

  • b. To ensure stakeholders are satisfied with the repair.

  • c. To create a Pareto chart to see the major reason for defect

  • d. To verify the extent of the repair as per scope defined in the Project Charter.

Erklärung

Frage 137 von 150

1

What is the impact of noise on communication??

Wähle eine der folgenden:

  • a. Noise changes the message while being delivered.

  • b. Noise interferes with the understandings of the message by the receiver.

  • c. Noise impacts only if it is persistent.

  • d. Noise makes it hard to hear the communication since it is too loud.

Erklärung

Frage 138 von 150

1

In order to calculate the Estimate To Complete (ETC), the following is typically needed:?

Wähle eine der folgenden:

  • a. Cost Performance Index (CPI) and the Actual Cost (AC).

  • b. Actual Cost (AC) and Estimate At Complete (EAC)

  • c. Earned Value (EV) and the Actual Cost (AC).

  • d. Cost Performance Index (CPI), actual cost (AC), and the Earned Value (EV).

Erklärung

Frage 139 von 150

1

Which of the following is INCORRECT about conflicts??

Wähle eine der folgenden:

  • a. Conflicts should be resolved publicly to avoid any misunderstanding.

  • b. Conflicts happen all the time.

  • c. Most conflicts can be resolved using a collaborated approach

  • d. Conflicts should be attended when the project is beginning

Erklärung

Frage 140 von 150

1

Which of the following is the BEST example of the use of coercive power by the Project manager?

Wähle eine der folgenden:

  • a. Project manager ask a resource Ò Come on. You know you owe me. Get me the report tomorrowÓ.

  • b. Project manager talking to a resource ñI want you to complete this report by end of tomorrowî

  • c. Project manager say to a resource ÒIf I do not get de document from you within two days, I will speak with your managerÓ.

  • d. Project manager asks a resource ÒShould I meet in person or just send her an email. Which is the right approach?Ó

Erklärung

Frage 141 von 150

1

Which of the following in the project manager always responsible for??

Wähle eine der folgenden:

  • a. Meeting the project’s profit margin.

  • b. Prioritizing projects based on business need.

  • c. Writing performance reports for Project resources.

  • d. Selecting appropriate processes for the project.

Erklärung

Frage 142 von 150

1

The agreement could be:

Wähle eine der folgenden:

  • a. A bill of materials

  • b. A contract, an SLA or a purchase order

  • c. A purchase policy

  • d. The most competitive cost estimate

Erklärung

Frage 143 von 150

1

A project manager does not have much time to spend planning before the mandatory start date arrives. He therefore wants to move through planning as effectively as possible. Which of the following would you recommend?

Wähle eine der folgenden:

  • a. Make sure you have a signed project charter and then start scheduling and budgeting

  • b. Create a WBS and activity list then a network diagram and Gantt chart

  • c. Document all the known risks before you document the high level assumptions

  • d. Finalize the quality management plan before you determine quality metrics

Erklärung

Frage 144 von 150

1

The project team has decided to perform an intentional activity that realigns the performance of the project work with the plan. The team is doing:

Wähle eine der folgenden:

  • a. A requirement of the project success.

  • b. A corrective action.

  • c. A preventive action

  • d. They are referring to an activity that can help improve performance back to the desired state.

Erklärung

Frage 145 von 150

1

You are managing a gas pipeline river crossing project. The project involves drilling piles in the river bed to build a bridge to cross the gas pipeline over the river. The biggest risk you have identified and planned a response for was the delay in shipping and import of steel piles from abroad. There were two shipments planned a few months apart. First shipment was received at the docks on time. Three large trailers took off from the docks to the site, carrying enough piles for three weeks of work. It will take them one week to reach the site from the docs. All the teams and installation equipment was ready on south bank of the river on the day the shipment was to arrive. The shipment reached the site on time but on the north side of the river. It would take a whole week to bring it to south side as the bridge, which can accommodate the large trailers, was very far from the site. No one in the project time had imagined this as a risk. What do you think will be the BEST way to handle this situation?

Wähle eine der folgenden:

  • a. Add this to risk register, analyze and develop risk response, then communicate to make sure no more trailers get sent to he north side.

  • b. This should be handled as an issue and not as a risk.

  • c. Evaluate impact on this issue on project performance baselines.

  • d. Analyze this risk and use contingency reserve, which is for unplanned risks.

Erklärung

Frage 146 von 150

1

An organization is highly reputed for deliverables quality. What would be an appropriate statement that BEST represent this situation?

Wähle eine der folgenden:

  • a. The organization has a low cost of quality.

  • b. Organization uses a standard quality management plan for all projects.

  • c. Organization’s Project schedules are highly robust.

  • d. The organization has a high cost of quality.

Erklärung

Frage 147 von 150

1

A Project life cycle in which phases intentionally repeat one or more project activities to develop the product through a series of repeated cycles, adding functionality to product.

Wähle eine der folgenden:

  • a. Predictive life cycle.

  • b. Risk life cycle.

  • c. Iterative and incremental life cycle.

  • d. Adaptive life cycle.

Erklärung

Frage 148 von 150

1

You are iniciating a new project and you and your team are in the middle of a meeting trying to identify the key stakeholders. Which documents are the better sources for do that:

Wähle eine der folgenden:

  • a. Business case and Benefit Management Plan

  • b. Project Charter

  • c. Issue log

  • d. Resource Breakdown Structure

Erklärung

Frage 149 von 150

1

A project was terminated in the middle of execution when half of the deliverables have already been completed. If you are the project manager of this project, what will you do??

Wähle eine der folgenden:

  • a. Discuss with the sponsor of what can be done to keep the project running.

  • b. Perform scope validation of the completed deliverables.

  • c. Stop the work immediately and release project resources.

  • d. Send a detailed project status report to the sponsor on how well the project was doing.

Erklärung

Frage 150 von 150

1

You have a seller working on a Time and Material contract. As per contract, two resources will work for 12 months on the project for a total cost of $180,000. However, the project took longer than expected and by the time it was completed, the two resources have been on the project for 18 months with a total cost of $250,000. What went wrong??

Wähle eine der folgenden:

  • a. Just like an initiative for finishing earlier, a penalty should have been proposed for delay

  • b. A maximum amount and time limit should have been established under the contract.

  • c. Fixed price contract, which is good for these kind of situations, should have been used.

  • d. Nothing went wrong since this was Time and Material contract under which resources charged for the time they worked on the project.

Erklärung