Frage 1
Frage
Q1: You are participating in developing the project charter for a new project assigned to you. Which of the following is input in Develop Project Charter?
Antworten
-
A. Project management plan
-
B. Communication management plan
-
C. A Contract
-
D. Stakeholder management plan
Frage 2
Frage
You are a project manager working on a project when the customer wants another feature added to the product. However, there is no additional budget for the new feature. As a project manager what should you do next?
Antworten
-
A. Ask your manager for guidance
-
B. Follow the contract change control process
-
C. Remove some other feature and add the new feature
-
D. Negotiate with the customer to provide additional funding for the new feature
Frage 3
Frage
You are a project manager running a public transportation system project. A strike by local workers occurs due to the lateness workers' payments. That leads to delays in a major component delivery. What could have been done differently to prevent this type of situation?
Frage 4
Frage
The sponsor of your project is particularly interested in reviewing the roles of different stakeholders on the project. As a project manager, you should direct the sponsor of the project one of the following document?
Antworten
-
A. Stakeholder’s engagement assessment matrix
-
B. Stakeholder Register
-
C. Stakeholder management plan
-
D. Project Team Directory
Frage 5
Frage
Q5: During project managers meeting in your organization, they were discussing a project management methodologies subjects such as agile and waterfall, they were discussing one of the followings:
Frage 6
Frage
you are a project manager in the implementation phase, if the project sponsor has told the functional manager that the project will delay by two weeks, and the Functional Manager has told you to document that, which type of organizational structure you are working in?
Antworten
-
A. Functional
-
B. Projectized
-
C. Matrix
-
D. Tight Matrix
Frage 7
Frage
You are the Project Manager and are currently in the monitoring process group. You and your team are trying to identify the relationship between an independent variable and the dependent variable by plotting their values on a diagram. One of your team members asks you what is this diagram known as?
Frage 8
Frage
You are a project manager in a construction project. One of the key stakeholders expressed surprise to you because being informed of a previously published a change request to a project deliverable. All other stakeholders received notification about a change request. What could have been done to prevent this type of situation?
Antworten
-
A. Review the communication management plan
-
B. Inform the stakeholder of the date when the change was approved
-
C. Ignore the key stakeholder
-
D. Address the situation in the next steering committee meeting
Frage 9
Frage
One of the tasks that are completed at the start of a project is to conduct the first project meeting, known as the project kick-off meeting. What’s the purpose of the project kick-off meeting?
Antworten
-
A. It introduces the project goals/objectives
-
B. The project manager gain the commitment from the key stakeholders
-
C. Approved project charter
-
D. Discuss the project Schedule
Frage 10
Frage
You are a project manager in a construction project. 85% of the project works completed. And the project has spent the budget due to the change in a cost of the materials. If a cost of the materials was US $7.0 and your estimating were US $10.0. If a cost of the materials reached to US $16.0.
What were your estimated should be?
Antworten
-
A. US $11.0
-
B. US $10.33
-
C. US $10.50
-
D. US $16.0
Frage 11
Frage
Chris is a project manager for a large construction company. Risk management is a large part of what you manage. Your management instructs you to focus on the business risks and informs you they will focus on the pure risks. How is your organization most likely to deal with pure risks?
Frage 12
Frage
The preferred method to settle claims and disputes in the project is:
Antworten
-
A. Arbitration
-
B. Mediation
-
C. Negotiation
-
D. Litigation
Frage 13
Frage
Based on the diagram below, the project is currently:
Antworten
-
A. Ahead of schedule and under budget
-
B. Ahead of schedule and over budget
-
C. Behind schedule and over budget
-
D. Behind schedule and under budget
Frage 14
Frage
You are developing the project charter for a new project assigned to you. Which of the following is input in Develop Project Charter?
Antworten
-
A. Historical information and lessons learned knowledge base
-
B. Project Management Plan
-
C. Work performance reports
-
D. Change Requests
Frage 15
Frage
While managing a project, you decide to create a prototype of your product first to ensure that it is acceptable to stakeholders before creating your product. This is an example of:
Frage 16
Frage
the project manager has just received a change from the customer. The project manager realize that if approved this change will increase the project cost by $30,000.
What is the project manager should do next?
Antworten
-
A. reject the change
-
B. make the change as soon as possible
-
C. get the change approved internally first
-
D. see how the change effects the other project constraints
Frage 17
Frage
One of the stakeholder on the project, led a change request a month back. He reached out to the project manager stating that he has not received any response yet. How can this situation be resolved?
Antworten
-
A. By reviewing the issue log
-
B. By reviewing the stakeholder register
-
C. By reviewing the perform integrated change control process
-
D. Reach out to your team lead to understand why it was miss
Frage 18
Frage
as a project manager in construction project, if the Project Sponsor tells you that the project will be terminated because of Stumbled in the credit limit of the bank. What could have done by the project manager to prevent this type of situation?
Frage 19
Frage
You are a project manager of a large construction project for the government. The customer is asking for multiple scope changes. You are considering these requested changes and trying to determine their true magnitudes. You are most likely to review what document?
Antworten
-
A. The WBS
-
B. Cost management plan
-
C. The project charter
-
D. Scope management plan
Frage 20
Frage
Rework is an example of a (an):
Antworten
-
A. External failure cost
-
B. Internal failure cost
-
C. Appraisal cost
-
D. Prevention cost
Frage 21
Frage
you are the project manager of a large, complex, multi-year project. In the past, you have planned out all the details of the activities early in the project. For your current project you are more likely to do progressive elaboration through:
Antworten
-
A. Rolling wave planning
-
B. Templates
-
C. WBS
-
D. Scope management
Frage 22
Frage
Training is an example of a (an):
Antworten
-
Internal failure cost
-
External failure cost
-
Prevention cost
-
Appraisal cost
Frage 23
Frage
Scrap is consider as:
Antworten
-
A. prevention cost
-
B. appraisal cost
-
C. internal failure cost
-
D. external failure cost
Frage 24
Frage
A statistical method used to determine optimal conditions for producing the product is called:
Antworten
-
A. Design of experiments
-
B. Benchmarking
-
C. Cost-benefit analysis
-
D. Portotype
Frage 25
Frage
Mark is managing a project .with limited resources on the project. Several quality defects have been discovered, causing the customer concern. He wish to begin by attacking the causes that have the largest number of defects, which tool shows defects by volume from greatest to least?
Antworten
-
A. Ishikawa Diagram
-
B. Scatter Diagram
-
C. Pareto Chart
-
D. Control Chart
Frage 26
Frage
an activity has an optimistic estimate of 10 days, pessimistic estimate of 16 days, and most likely estimate of 13 days. If the project manager is being used a non-linear method to estimates the duration of these task. What is the duration estimate for the activity?
Frage 27
Frage
Senior management needs to be informed regarding the progress of your project. You will be making progress reports based on the scope, schedule, and cost details provided in the:
Frage 28
Frage
If your project is under budget, your cost variance (CV) is:
Antworten
-
A. 1
-
B. -1
-
C. Negative
-
D. Positive
Frage 29
Frage
Adel is a project manager who manages equipment installations in an automobile manufacturing project. Early in the planning process, He is asked to generate ideas for improvement and to provide a basis by which to measure performance. Adel is most likely to use:
Antworten
-
A. Control charts
-
B. Pareto charts
-
C. Scatter diagrams
-
D. Benchmarking
Frage 30
Frage
Based on your success on previous projects, you have been asked to manage a project for a different department in your organization. This department has documented processes for most of their work. You realize that you will need to tailor many of their standard processes so that they will make sense for your new project. Which organizational process asset will probably help you the most?
Antworten
-
A. Infrastructure
-
B. Project management information system (PMIS)
-
C. Project plan templates
-
D. Change management plan
Frage 31
Frage
Enterprise Environmental Factors includes some elements such as:
Antworten
-
A. Organizational Structure, Culture, infrastructure
-
B. Project closure guidelines or requirements
-
C. Project files from previous projects (e.g., scope, cost, schedule and performance measurement baselines
-
D. Project plan templates
Frage 32
Frage
Which conflict resolution technique is most likely to result in a permanent resolution?
Frage 33
Frage
the Output of Develop project team is:
Frage 34
Frage
You have been assigned to a project which has major cost overruns, as well as a long list of uncontrolled changes. Uncontrolled changes are also known as:
Antworten
-
A. Scope Creep
-
B. Scope change
-
C. WBS change
-
D. Schedule creep
Frage 35
Frage
If earned value is larger than planned value:
Antworten
-
A. The project is under budget
-
B. The project is over budget
-
C. The project is ahead of schedule
-
D. The project is behind schedule
Frage 36
Frage
The CPI= 0.7 and the SPI=1.2. How is your project doing?
Antworten
-
A. Behind schedule, over budget
-
B. Ahead of schedule, under budget
-
C. Ahead of schedule, over budget
-
D. Behind schedule, under budget
Frage 37
Frage
The CV= -1.1 and the SV=1.2. How is your project doing?
Antworten
-
A. Ahead of schedule, under budget
-
B. Ahead of schedule, over budget
-
C. Behind schedule, under budget
-
D. Behind schedule, over budget
Frage 38
Frage
You project is running with a CPI of 1.1. The EAC is $100,000. What is the BAC?
Antworten
-
A. $90.000
-
B. $110.000
-
C. $125.000
-
D. $115.000
Frage 39
Frage
You have just been moved onto a project that is well into the project implementation phase. You then realize that no stakeholder register exists for the project. Since you are new to the organization, you want to ensure that you use its templates for documents. Therefore you search for a template for a stakeholder register in the:
Antworten
-
A. Organizational process assets
-
B. Enterprise environmental factors
-
C. Stakeholder management plan
-
D. Project management plan
Frage 40
Frage
The project manager has been brought in long before initiating the project is complete. Often the first task the project manager performed while initiating a project is:
Antworten
-
A. Identify key deliverables based on business requirements
-
B. Participate in the development of the project charter
-
C. Conduct benefits analysis to validate project alignment
-
D. Perform a project assessment in order to evaluate the feasibility of the project.
Frage 41
Frage
A project manager is using a method that not consider risk to perform schedule network analysis ,which type of duration estimates is being the project manager used?
Frage 42
Frage
Change requests on projects may be either rejected or approved. Approved changes are processed through which process for implementation?
Antworten
-
A. Develop project management plan
-
B. Develop project Charter
-
C. Direct and manage project work
-
D. Perform integrated change control
Frage 43
Frage
Your manufacture component business is growing at an exponential rate. With respect to product testing, you are moving to testing samples instead of entire populations. In general, the main reasons to test samples instead of populations include all of the following except:
Antworten
-
A. The testing takes a long time
-
B. The testing may be destructive
-
C. The testing is variable related not attribute related
-
D. The testing is expensive
Frage 44
Frage
On what contract type does the highest risk for the seller?
Frage 45
Frage
tool and technique for quality assurance is:
Antworten
-
A. Quality audit
-
B. Expert judgment
-
C. Pareto diagrams
-
D. Control chart
Frage 46
Frage
: The document that describes how the project scope will be defined, documented, validated, managed, and controlled is called?
Frage 47
Frage
a tool and technique of creating WBS:
Antworten
-
A. Meeting
-
B. Product Analysis
-
C. Facilitated Workshops
-
D. Decomposition
Frage 48
Frage
collect requirements is The process of determining, documenting, and managing stakeholder needs and requirements to meet project objectives, after collect requirements what will you do next?
Antworten
-
A. Control Scope
-
B. Define Scope
-
C. Create WBS
-
D. Validate Scope
Frage 49
Frage
Who is responsible for create WBS?
Frage 50
Frage
: the process of tracking, reviewing, and reporting the progress to meet the performance objectives defined in the project management plan is?
Antworten
-
A. Develop project management plan
-
B. Direct and manage project work
-
C. Monitor and control the project work
-
D. Manage stakeholders
Frage 51
Frage
: A project manager has invited key stakeholders and team members for the first project meeting. The agenda of the meeting is to announce the start of the project, outline the project goals and objectives, and to communicate the project success criteria. The project manager also plans to discuss individual roles and responsibilities along with the desired commitment levels of the stakeholders. What is this activity called?
Antworten
-
A. Project kick-off meeting
-
B. Project launch meeting
-
C. Project closure meeting
-
D. Project sign-off meeting
Frage 52
Frage
As a project manager of a construction project, you understand the importance of contract documents and correspondence for future references. Which of the following can be used to manage and store contract documents and records?
Frage 53
Frage
: Of the following, which conflict resolution technique is believed to generate the least positive results?
Antworten
-
A. Compromising
-
B. Withdrawal
-
C. Forcing
-
D. Collaborating
Frage 54
Frage
Mark is a project manager working on a compliance project in a banking firm. The project is scheduled to be completed six weeks from now. Your sponsor tells you that if the project is finished sooner, the company can receive some monetary incentives offered by the government. What would be the effect if Mark decide to fast track the project?
Antworten
-
A. Cannot be determined
-
B. Increased risk in the project
-
C. Not affect the project risk
-
D. Decrease risk in the project
Frage 55
Frage
A project manager shares project performance through status reports via email to all of the stakeholders of the project. Which of the following techniques is he using?
Frage 56
Frage
After a major milestone release, one of the key stakeholders are not happy and complain their requirements are not being met. In which of the following processes should the project manager have involved them to ensure their approval for the release?
Frage 57
Frage
One of the key stakeholder expresses his concern over lack of project visibility and progress. He says that he has been sent project status reports, but most times, they lack information relevant to his department. How should the project manager respond?
Antworten
-
A. Relook at distributed information to identify the gaps
-
B. Change management plan
-
C. Review the stakeholder management plan
-
D. Review the communication management plan
Frage 58
Frage
You are a project manager and member of the Project Management Office, if your senior management want you to present a snapshot of the status of various projects going on in the organization. Which of the following charts would be most suitable for the purpose?
Antworten
-
A. Control chart
-
B. Critical path method
-
C. Gantt chart
-
D. Milestone chart
Frage 59
Frage
which of the following is output from identify stakeholders process?
Frage 60
Frage
: which of the following is tool and technique for identify stakeholders process?
Antworten
-
A. Stakeholder analysis
-
B. Stakeholder register
-
C. Analytical Techniques
-
D. Management Skills
Frage 61
Frage
Sandra is a project manager in the process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create an approved project schedule. What should Sandra do next?
Antworten
-
A. Use the critical path method and what-if scenario to calculate optimum duration of the project
-
B. Use this approved schedule duration as a baseline and start tracking the project
-
C. Create a network diagram of the project
-
D. Determine resource requirement for each activity in the project
Frage 62
Frage
A project manager is in the process of documenting and defining stakeholders’ needs to meet the project objectives. What is the output of this process?
Frage 63
Frage
: you are a project manager and you in closing phase you want to report the final status of the closed contract to the stakeholders. Which form of communication is appropriate?
Antworten
-
A. Formal, verbal
-
B. Formal, written
-
C. Informal, verbal
-
D. Informal, written
Frage 64
Frage
A pharmaceutical company recently terminated a research project because it no longer seemed commercially viable for the company. What is the first thing the project manager should do?
Antworten
-
A. Conduct scope validation
-
B. Document the lessons learned
-
C. Discuss with the senior manager the reason for termination
-
D. Control Scope process
Frage 65
Frage
: All of the following are inputs to the develop project charter process except:
Frage 66
Frage
As a project manager, what would you do if you received a change request that does not impact the project schedule?
Antworten
-
A. Go ahead and do the change
-
B. Evaluate the impact on the other project constraints
-
C. Get in touch with the change control board
-
D. Ask your boss’s permission
Frage 67
Frage
Which of the following is a tool to assess the current and desired state of engagement of a stakeholder on the project?
Frage 68
Frage
: A project manager is encountering numerous problems on his project. He wants to identify the root causes of the problems, so he can focus his attention on those causes. Which of the following tools should he use?
Antworten
-
A. Ishikawa diagram
-
B. Control chart
-
C. Pareto diagram
-
D. Histogram
Frage 69
Frage
Which conflict resolution technique is best for a long-lasting solution?
Antworten
-
A. Smoothing
-
B. Forcing
-
C. Withdrawal
-
D. Problem Solving
Frage 70
Frage
A project manager has recently been assigned to a long running project and wants to know who the key influences are on the project and what their level of involvement is. The best document to gather this kind of information is:
Antworten
-
A. Stakeholder management plan
-
B. Project management plan
-
C. Human resource management plan
-
D. Stakeholder register
Frage 71
Frage
Which process group has accepted deliverables as the output?
Frage 72
Frage
You have contracted some work to sub-contractor, and would like to identify successes and failures of other procurement contracts within the performing organization. This can be performed through:
Frage 73
Frage
As part of your staffing management plan, you are creating a chart to illustrate the number of hours that a person, department, or entire project team will need each week or month over the course of the project. This chart is also known as:
Frage 74
Frage
You are a project manager and you want to perform some analysis of defects and problems that have been discovered in the project. Which chart can reveal factors that might be linked to potential problems within your project?
Frage 75
Frage
which of the following is output from Conduct procurements?
Frage 76
Frage
which of the following are Tools and Techniques of Control Stakeholder Engagement?
Antworten
-
A. Stakeholder analysis, Expert Judgment
-
B. Communication method, interpersonal skills
-
C. Meetings, Expert judgment, information management system
-
D. Management skills, issue log, expert judgment
Frage 77
Frage
Whose job is it to determine the priorities among projects in a company?
Antworten
-
A. Senior Management
-
B. Functional manager
-
C. Project sponsor
-
D. Project Team
Frage 78
Frage
Which of the following is NOT an input of the close project or phase process?
Antworten
-
A. Organizational process assets
-
B. Project management plan
-
C. Project management methodology
-
D. Accepted deliverables
Frage 79
Frage
You are a project manager managing a project with 24 months duration. During the middle of the project, it is found that the quality of the project is not as planned or expected. Who is responsible for this situation?
Antworten
-
A. The project manager
-
B. Functional manager
-
C. The customer
-
D. The customer
Frage 80
Frage
: The staffing management plan, which is part of the human resource plan, describes when and how human resources requirements will be met, which of the following inputs in the staffing management plan?
Antworten
-
A. Networking-Organizational Theory-project management plan
-
B. Project documents-Resource calendar-staffing management plan
-
C. Project management plan-activity resources requirements-enterprise environmental factors-Organizational process assets
-
D. Project staff assignments-Resource calendar-Human resource management
Frage 81
Frage
WBS for your project has been prepared and distributed to the project team members. When execution begins, which document will be providing the detailed descriptions of the WBS elements?
Frage 82
Frage
Henry is a project manager in a large project he has been informed by the project sponsor that the customer intends to terminate the project in the middle of the execution process group. Which of the following will henry do FIRST as a Project Manager?
Antworten
-
A. Meet the sponsor to discuss the course of actions
-
B. Evaluate the impact of project closure
-
C. Initiate the Close Project or phase process
-
D. Share this information with all stakeholders by email
Frage 83
Frage
As a project manager for your organization and you’re working with your team to define the difference between projects and operations. You explain that projects are unique while operations are the core business. Projects are typically initiated for all of the following reasons except for which one?
Frage 84
Frage
As a project manager for a new construction project in Chicago. You and the project team are creating the scope statement and are evaluating the function, purpose, and activities that will take place within the warehouse to help the project customer gather all of the requirements for the scope. This process is an example of which one of the following?
Frage 85
Frage
You are the project manager of village housing construction project. You are interviewing the village owners to determine their requirements and needs for the home construction. You are discussing, room by room, what they’d like in their home. This long process is called what?
Antworten
-
A. Stakeholder analysis
-
B. Scope creation
-
C. Quality matrices
-
D. Risk analysis
Frage 86
Frage
Which of the following is an example of quality assurance?
Antworten
-
A. Process analysis
-
B. Control chart
-
C. Design of experiments
-
D. pareto chart
Frage 87
Frage
You are working on warehouse project when you realize that you may miss the due date of the project. What would you do in such a scenario?
Antworten
-
A. Ask your senior manager for guidance in such case
-
B. Change the due date and discuss the new date with all relevant stakeholders
-
C. Evaluate options to meet the due date
-
D. Nothing to do
Frage 88
Frage
: One of your team members comes to you and proposes a change in the project that can reduce the project schedule by 3 weeks. As a Project Manager.
What should you do next?
Antworten
-
A. Advise the team member to just focus on his work
-
B. Analyze the impact of the change on the other triple constraints
-
C. Go ahead with the change
-
D. Nothing to do
Frage 89
Frage
: You are the Project Manager doing earned value analysis when you find out that SPI = 1.12 and CPI is 0.75. What can be said about the project status?
Antworten
-
A. The Project is behind the schedule and under budget
-
B. The Project is behind the schedule and over budget
-
C. The Project is ahead of the schedule and over its budget
-
D. The Project is ahead of the schedule and under its budget
Frage 90
Frage
Feeding buffers and the project buffer are part of which of the following Develop Schedule tools and techniques?
Frage 91
Frage
You are a project manager working on gathering requirements and establishing estimates for the project. Which process group are you in?
Frage 92
Frage
which of the following diagrams rank-order factors for corrective action by frequency of occurrence. They are also a type of histogram
Antworten
-
A. Scatter diagrams
-
B. Flowcharts
-
C. Pareto diagrams
-
D. Scatter diagrams
Frage 93
Frage
The business need, product scope description, and strategic plan together describe elements of the following?
Antworten
-
A. The project charter
-
B. The project statement of work
-
C. Tools and techniques of the Initiating processes
-
D. Organizational process assets
Frage 94
Frage
the purpose of the project charter is:
Antworten
-
A. To recognize and acknowledge the project sponsor
-
B. To recognize the existence of the project, and commit organizational resources to the project.
-
C. To describe the selection method used to choose the project
-
D. To acknowledge the existence of the project team, project manager, and project sponsor.
Frage 95
Frage
Your project sponsor has requested a cost estimate for the project on which you're working. This project is similar in scope to a project you worked on last year. She would like to get the cost estimates as soon as possible. Accuracy is not her primary concern, which tool and technique will use for the estimate?
Frage 96
Frage
Your sponsor has requested you to come up with a cost estimate for all the activities which are defined in the project schedule. He has specially mentioned it to you to make sure that you are taking Risk into consideration. Which technique will be best in such kind of scenarios?
Antworten
-
A. Bottom-up
-
B. Beta distribution
-
C. Parametric
-
D. Analogous
Frage 97
Frage
You are a buyer side project manager and have given a contract to a small startup company. In the middle of the project, supplier reported to you that he won't be able to deliver all the deliverable which are required to be completed as a part of this project. What could have been done differently to prevent this type of situation?
Antworten
-
A. Giving the contract to more experienced vendor
-
B. Reviewing the agreement regularly.
-
C. Performing procurement reviews regularly
-
D. More Stringent/Strict Selection Criteria
Frage 98
Frage
The customer is really interested in reviewing the key performance indicators of the project. Where will you find this information for the project?
Antworten
-
A. KPI is included in the project charter as success criteria
-
B. KPI can be part of organizational process assets
-
C. KPI is included in the project charter in the business case section
-
D. KPI is part of change control tool
Frage 99
Frage
The total budget of a 12 month project is $100,000. You have completed three months' worth of work and are in your 4th month of your project. The total amount spent till now is $35,000. What is the project status?
Antworten
-
A. Under Budget, Behind Schedule
-
B. Under Budget, Ahead of Schedule
-
C. Over Budget, Behind Schedule
-
D. Over Budget, Ahead of Schedule
Frage 100
Frage
A stakeholder formatted and arranged all the information which he was able to gather at the end of initiation stage. He collaborated everything into one document and presented it to other stakeholders for approval. Which document is the stakeholder referring to?
Antworten
-
A. Stakeholder Register
-
B. Agreement
-
C. Project Charter
-
D. Business Case
Frage 101
Frage
You are a project manager working on a big critical project. In one of the meetings, project sponsor shouted you why did you send the critical reports to the payroll manager. What could have been done the project manager to prevent this situation?
Antworten
-
A. Review communication management plan
-
B. Review stakeholder management plan
-
C. Review project communications
-
D. Review organizational process assets
Frage 102
Frage
Quality audits are an important part of quality management because:
Antworten
-
A. They check to see if the quality process is being followed
-
B. They randomly audit product results to see if they are meeting quality standards.
-
C. They are conducted without prior notice
-
D. They allow for quantification of the risk
Frage 103
Frage
You are evaluating proposals from prospective sellers. What process are you involved in?
Frage 104
Frage
You are a project manager and you are ready to close out a procurement. Where is the best place to look for guidance in how to perform this activity?
Frage 105
Frage
What are the dimensions measured on a stakeholder grid?
Frage 106
Frage
if the project manager is unsure who has the authority to approve changes in project scope, he should consult:
Frage 107
Frage
Your project team has just received the sponsor's approval of the scope statement. What is the NEXT?
Antworten
-
A. Develop the product description
-
B. Create the scope baseline
-
C. Hold the kickoff meeting
-
D. Create the network diagram
Frage 108
Frage
In which of the following documents could the sponsor find work package descriptions?
Frage 109
Frage
The process in which project deliverables are reviewed and accepted is called:
Antworten
-
A. Plan scope
-
B. Closing
-
C. Control scope change
-
D. Validate scope
Frage 110
Frage
Your Company’s top management has requested a meeting with you and two other project managers for a status update on your various projects. What is the BEST document you can bring with you to this meeting?
Antworten
-
A. The network diagram for this project
-
B. Copies of the most recent status reports from the team members
-
C. The milestone chart for this project
-
D. The project charter
Frage 111
Frage
You are a project coordinator from the buyer side. The supplier side project manager reached out to you to recommend a change in the proposal which will greatly benefit the end product. You believe the same but your PM think otherwise. As per him it's a waste of time and told you to continue with the existing project plan. What conflict resolution technique did the project manager use?
Antworten
-
A. Compromising
-
B. Smoothing
-
C. Direct/force
-
D. Avoid
Frage 112
Frage
You are a project manager and you are reviewing the deliverables developed by the seller organization. If you would like to review the quality specifications of the deliverable, which document can help you in this scenario?
Antworten
-
A. Procurement Documents
-
B. SOW
-
C. Agreements/contracts
-
D. Procurement Plan
Frage 113
Frage
You are a project manager in the execution stage of the project where your team members are conducting a meeting to reassess their risk informations and to identify new risks that might affect the project. What is project team doing?
Antworten
-
A. Risk Assessment
-
B. Plan Risk Responses
-
C. Risk Reassessment
-
D. Risk Identification
Frage 114
Frage
A probability and impact matrix is useful for:
Frage 115
Antworten
-
A. A response to an unplanned risk event
-
B. A technique for conflict management
-
C. An adjustment to the project budget
-
D. Change Request
Frage 116
Frage
The process of identify, documenting, and assigning roles, responsibilities, and reporting relationships for a project is called
Antworten
-
A. Staff Management Planning
-
B. Schedule management plan
-
C. Human Resource Planning
-
D. Organizational Breakdown
Frage 117
Frage
: Project stakeholders requested for scope related changes to the project. These changes will result into change in scope and time. After discussing with the team, the project manager discussed the potential impacts of these changes with the stakeholders. If these impacts result into some issue, what is the best method a project manager can take to resolve
Frage 118
Frage
you are a project manager in construction project during the closing of the purchase contract with one of the subcontractors which of the following is tool and technique, you will use for this purpose?
Antworten
-
A. Records Management System
-
B. Contract Change Control System
-
C. Procurement Performance Reviews
-
D. Inspections and Audits
Frage 119
Frage
A project manager you are mentoring comes to you for help because he is about to face his first procurement audit .you might explain that he should not worry about such an audit because it:
Antworten
-
A. Identifies successes and failures that warrant transfer to other procurements
-
B. Makes sure that the contract is being followed
-
C. Makes sure the schedule of the project is line with the schedule baseline
-
D. Makes sure the deliverables are accepted
Frage 120
Frage
A customer has requested a change that requires you to obtain new equipment. If the cost of buying the equipment is $210,000, and the daily rent cost is $2,000 and includes maintenance cost is $10,000 .after how many days the buying becomes better than renting the equipment?
Antworten
-
A. 99 days
-
B. 101 days
-
C. 100 days
-
D. 110 days
Frage 121
Frage
In which process group creates the project charter?
Antworten
-
A. Initiating
-
B. Planning
-
C. Executing
-
D. Mentoring and control
Frage 122
Frage
You are performing administrative closure activities during the Close Project or Phase Process. All are administrative closure activities of a Project EXCEPT:
Antworten
-
A. Lesson Learned Documentation
-
B. Project Document Archiving
-
C. Transfer the Project’s products to operations
-
D. Performance Measurement Documentation
Frage 123
Frage
Where would you find a detailed list and description of specific project assumptions and constrains associated with the project?
Antworten
-
A. Project charter
-
B. Project scope statement
-
C. Project configuration document
-
D. Change management plan
Frage 124
Frage
Which of the following is a reason of collecting lessons learned?
Antworten
-
A. Documenting both the success stories and the failed attempts
-
B. Documenting only the success stories
-
C. Focusing purely on the negatives and analyzing failures
-
D. Lessons learned just documents do not have any interest
Frage 125
Frage
who is the person is responsible to make changes in the Project Charter?
Frage 126
Frage
Sandra is currently assessing her project stakeholders' engagement levels. During this exercise she finds out the she also need to document an escalation process which will come in handy in future. Where does she need to document the project's escalation process?
Antworten
-
A. Stakeholder management plan
-
B. Either the stakeholder management plan or the communications management plan
-
C. Both the stakeholder management plan and the communications management plan
-
D. Communications management plan
Frage 127
Frage
: Which of the following is not a tool or technique of the Acquire Project Team process?
Antworten
-
A. Negotiation
-
B. Interpersonal skills
-
C. Pre-assignment
-
D. Conflict management
Frage 128
Frage
When writing the roles and responsibilities for team members, you should document the role, authority, responsibility and competency for each team member. Where this information must be documented?
Frage 129
Frage
Which of the following processes produces a Risk Register?
Frage 130
Frage
Based on the following table, as a project manager which risk are you going to tell the project stakeholders is the greatest and is therefore the biggest concern of the team right now
Frage 131
Frage
You are the project manager in a company. You have finished preparing a detailed description of the project and product. What will you do next?
Frage 132
Frage
As a project manager in multi mega project, while identifying stakeholders, you plan to group project stakeholders based on their level of authority and their active involvement in the project. You can do this by using:
Antworten
-
A. Power/Influence grid
-
B. Power/Interest grid
-
C. Power/Impact grid
-
D. Flow charts
Frage 133
Frage
The framework that provides the project manager and the team with the structure, processes, decision-making models, and tools for managing the project is called:
Antworten
-
A. The change management plan
-
B. The project management plan
-
C. Project governance
-
D. Communication management plan
Frage 134
Frage
Your project has 15% probability of having to profit $10,000 .and a 20% probability of loss $15,000. What is the expected monetary value of this situation?
Antworten
-
A. $1,500 loss
-
B. $1,500 profit
-
C. $1,200 loss
-
D. $1,200 profit
Frage 135
Frage
you are a project manager, and you are working on a major new product when a risk occurs that does not have a risk response plan. What should you do next?
Antworten
-
A. A workaround
-
B. Use the reserves to accommodate the risk
-
C. Inform the management about the new risk
-
D. Use the contingency management plan
Frage 136
Frage
the project customer requests a change to the project that would increase the project risk. As a project manager what should you do next?
Antworten
-
A. Change the risk management plan
-
B. A workaround
-
C. Talk to the customer about the impact of the change
-
D. Analyze the impact of the change with the team
Frage 137
Frage
The contract type that often spans multiple years and allows for final adjustments to the total price due to changed conditions is:
Antworten
-
A. Fixed price with economic price adjustments (FP-EA)
-
B. Time and materials
-
C. Cost plus fixed fee (CP-FF)
-
D. Cost plus incentive fee (CP-IF)
Frage 138
Frage
: If the buyer is likely to make their final selection on a vendor based on technical capability and not just low price they are most likely to send out a (n):
Antworten
-
A. Request for quote
-
B. Invitation for bid
-
C. Tender notice
-
D. Request for proposal
Frage 139
Frage
Which of the following statements is FALSE?
Antworten
-
A. Project closure documents and project files are outputs of the Close Project Process.
-
B. The project files consists of documentation resulting from project activities, such as the project management plan, scope, cost, risk registers, quality baselines
-
C. The formal acceptance documentation formally indicates that the customer or sponsor has officially accepted the project deliverables.
-
D. After the Close Project or Phase process is complete, the Project Manager should identify and document the lessons learnt.
Frage 140
Frage
you are a Project Manager working with your team to explore alternatives to decrease project cost without compromising on performance or scope of the project. You are most probably using which of the following techniques?
Frage 141
Frage
Whose job is it to determine the priorities among projects in a company?
Antworten
-
A. The project manager
-
B. Senior Management
-
C. The project team
-
D. The sponsor
Frage 142
Frage
Which of the following is NOT an input of the close project or phase process?
Frage 143
Frage
You are a project manager one of your Project team is working on how better or faster it can carry out the work and what optimization it can make within the project. Which of the following techniques/knowledge/skills are being used?
Antworten
-
A. Performance measurement techniques like KPI, key success factors
-
B. Project quality best practices
-
C. Fast track principles
-
D. Process analysis techniques
Frage 144
Frage
Sandra is working on an international project, which involves 200 team members and the project budget is $2,400,000. The weekly status meeting is conducted worldwide and is scheduled for Wednesday at 7:00 PM and the duration of the meeting is three hours. All of the team members globally communicate using the video conferencing unit at their location. What kind of communication method is this?
Frage 145
Frage
Your most recent project status report contains the following information: EV = 3.000, AC = 4.000, and PV = 5.000. The schedule variance is:
Antworten
-
A. -2.000
-
B. -1.000
-
C. 2.0000
-
D. 1.000
Frage 146
Frage
Which processes are in the Initiating process group?
Antworten
-
A. Develop Project Charter and Identify Stakeholders
-
B. Develop Project Charter and Develop Project Management Plan
-
C. Develop Project Management Plan and Identify Stakeholders
-
D. Identify Stakeholders and develop the communication management plan
Frage 147
Frage
you are a Project Manager, you are ensuring that quality standards are followed on your project. In which process are the quality standards that need to be followed identified?
Frage 148
Frage
What is the MOST important thing that a Project Manager should ensure during the 'Validate scope' process?
Antworten
-
A. Quality
-
B. Acceptance
-
C. Completeness
-
D. Cost
Frage 149
Frage
: Senior management needs to be informed regarding the progress of your project. You will be making progress reports based on the scope, schedule, and cost details provided in the:
Antworten
-
A. Stakeholder Management Plan
-
B. Project Management Plan
-
C. Change management plan
-
D. Schedule baseline
Frage 150
Frage
You are a Project Manager, you want your team use (WBS) in cost estimation developed for your project. Which techniques are you most likely to use?
Antworten
-
A. Analogous estimating
-
B. Expert Judgment
-
C. Bottom up estimating
-
D. Numerical estimating
Frage 151
Frage
Which is the best way of selecting a project, other things being constant?
Antworten
-
A. Project with highest IRR
-
B. Project with lowest Payback period
-
C. Project with lowest NPV
-
D. Project with lowest BCR
Frage 152
Frage
Which of the following is an output from the 'identify stakeholder' process?
Antworten
-
A. Stakeholder Register
-
B. Stakeholder management plan
-
C. Stakeholder Management Strategy
-
D. Stakeholder identification document
Frage 153
Frage
: Adel is the Project Manager of a new product development project. His team is getting the project deliverables accepted as per the specified project acceptance criteria. Why does the team need acceptance criteria for the project's final deliverables?
Antworten
-
A. To complete project records
-
B. To ensure customer satisfaction
-
C. To know what to create
-
D. To abide by the Project Manager's rule
Frage 154
Frage
you are A Project Manager hired by a construction company, the sponsor is developing a document which authorizes the project manager. Which is this document?
Antworten
-
A. Project charter
-
B. Project file
-
C. Project plan
-
D. Project baseline
Frage 155
Frage
Which of the following is a tool and technique used in 'Control Communications' process?
Frage 156
Frage
You are a project Manager for construction project and are looking for all possible information before the phase of project initiation. Which is the best source of information for your project?
Frage 157
Frage
The staffing management plan, which is part of the human resource plan, describes when and how human resources requirements will be met. Information on the staffing management plan may vary according to the application area and project size. Key areas may be the following except?
Antworten
-
A. Rewards
-
B. Training needs
-
C. Staff release plan
-
D. Work Items
Frage 158
Frage
your top management wants to be sure that only the work that is defined in the project scope is what gets done. Which project documentation should he ask the Project Manager for?
Frage 159
Frage
Which of the following is an output from close project or phase process?
Antworten
-
A. Final Product, Service, or Result Transition
-
B. Project management plan updates
-
C. Approved change requests
-
D. Accepted deliverables
Frage 160
Frage
Which of the following is an output from close project or phase process?
Frage 161
Frage
The organizational process assets that can influence the Close Project or Phase process include:
Antworten
-
A. Change Requests
-
B. Project management information system (pmis)
-
C. A configuration management system
-
D. Historical information and lessons learned knowledge base
Frage 162
Frage
Which of the following are Tools and Techniques for close project or phase?
Antworten
-
A. Expert Judgment, Analytical Techniques, Meetings
-
B. Expert Judgment, Analytical Techniques
-
C. Analytical Techniques, Meetings,
-
D. Expert Judgment, Meetings
Frage 163
Frage
Which of the following is a tool and technique use in Determine Budget?
Frage 164
Frage
A high level description of the scope issued by the buyer specifying the work expected to be completed by the seller is called (a/an):
Frage 165
Frage
A project manager you are shares project performance through status reports via email to all of the stakeholders of the project. Which of the following techniques is he using?
Frage 166
Frage
The estimating technique that uses a statistical relationship between the historical data and other variables to calculate an estimate for an activity is called:
Frage 167
Frage
as a project manager how would you save your project from cost overruns?
Frage 168
Frage
as a project manager how you will manage changes in you project?
Antworten
-
A. Cost management plan
-
B. Change management plan
-
C. Project management plan
-
D. Schedule management plan
Frage 169
Frage
which of the following is the primary output of the develop project team process?
Frage 170
Frage
A resource histogram includes which two data points?
Frage 171
Frage
Your project sponsor needs to know each team member in your project and their responsibilities. The best document to gather this kind of information is?
Antworten
-
A. Organizational chart
-
B. Resource calendar
-
C. WBS work package
-
D. Activity resource
Frage 172
Frage
Organizations performing projects will usually divide each project into several project phases to improve management control. This also provides links to the ongoing operations of the performing organization. Collectively, project phases are also called:
Frage 173
Frage
As a project manager working In Plan Risk Responses process, you are developing options to reduce threats to your project`s objectives. When you show the results to your project sponsor, she is not comfortable with the risks in the project and suggests that the project scope should be decreased. This is an example of:
Antworten
-
A. Risk acceptance
-
B. Risk avoidance
-
C. Risk mitigation
-
D. Risk a ppetite
Frage 174
Frage
In your project, one of your project team leave the site early at 2:00 pm you would like to establish clear expectations regarding the acceptable behavior of the team member to avoid such situations you should establish:
Frage 175
Frage
AS a project manager in your project, you want to ensure that all prospective sellers have a clear and common understanding of the procurement. In which of the following processes would you use bidder conferences as a tool?
Antworten
-
A. Control procurement
-
B. Close Procurement
-
C. Plan procurement
-
D. Conduct Procurement
Frage 176
Frage
Q176: As a project manager, If the customer need to validate the scope of the deliverables. This will help to
Frage 177
Frage
you are a project manager, you would like to conduct a lessons learned session to identify project successes and failures, as well as make recommendations to improve future project performance. This is done during
Frage 178
Frage
In your project, you will use a code of accounts to:
Antworten
-
A. Identify each component of the WBS
-
B. Update project files
-
C. Update change management plan
-
D. Project management plan updates
Frage 179
Frage
As a project manager, you are responsible for managing changes to the project scope. If, at the end of the project, a customer wants a major change in the scope of work, you should:
Antworten
-
A. Reject the change
-
B. Submit the change request to the (CCB) change control board
-
C. Escalate the matter to senior management
-
D. Let the customer know about the impact of the change
Frage 180
Frage
In your project, you would like to document team member roles and responsibilities. You have documented project roles as responsible, accountable, consult and inform. A good way to depict the information is through:
Antworten
-
A. RAM (responsibility assignment matrix)
-
B. RBS (resource breakdown structure)
-
C. WBS Dictionary (work breakdown structure dictionary)
-
D. Control charts
Frage 181
Frage
The customer accepted your project`s product two weeks ago, but recently complained that some of the product features are not as desired and that the product is not functioning properly. What should you do FIRST?
Antworten
-
A. Ignore the customer, since he already accepted the product
-
B. Review the quality management plan
-
C. Fix the errors as reported by the customer
-
D. Review the Validate Scope process
Frage 182
Frage
As a project manager if a problem occurs between two stakeholders in your project, what is the name of the document that lists any problems that stakeholders may have and records what is being done about them?
Frage 183
Frage
As a project manager if you would like to contact one of the stakeholders in the project. Which of the following documents will contain a description of stakeholder contact details and their requirements for the project?
Frage 184
Frage
You are the seller of a potential good or service, and are responding to an RFP document where there is a poorly defined scope of work. What type of contract would you prefer to enter into?
Frage 185
Frage
Your project has a budget = $2,000. After two-thirds of the project duration has been spent, $1,500, your project could be best described as:
Antworten
-
A. Under budget
-
B. Over budget
-
C. Within the budget
-
D. A head of budget
Frage 186
Frage
Which of the following is an organizational process asset that would be updated as a result of completing project closure?
Antworten
-
A. Project charter
-
B. Change requests update
-
C. Enterprise environmental factors
-
D. Historical information
Frage 187
Frage
The final product, service, or result is an output of the Close Project or Phase process. Where does it go after this process?
Frage 188
Frage
Which of the following is input in close project or phase process?
Frage 189
Frage
Which of the following is a tool and technique used in Perform Quantitative Risk Analysis?
Frage 190
Frage
Mark is a new project manager and this is the first project he will manage, he tries to set up a meeting with senior project managers those who have good experience of managing projects in the organization. However, all the senior project managers are busy with their current projects and have no availability. What should he do next?
Antworten
-
A. He should review lessons learned for the past similar projects
-
B. He review the project charter
-
C. Project management plan
-
D. Change management plan
Frage 191
Frage
You are managing a project when an unplanned risk event occurs. You meet with experts and determine a workaround to keep the project on track. In which process are you engaged?
Antworten
-
A. Qualitative Risk Analysis
-
B. Risk Monitoring and Control
-
C. Risk Response Planning
-
D. Quantitative Risk Analysis
Frage 192
Frage
A company in the middle of a new product development merges with another company in the middle of the project. The project is terminated because the new company already offers a similar product. What is the FIRST thing the project manager should do?
Antworten
-
A. Make sure your lessons learned are communicated to the manager of the existing product
-
B. Obtain a written project termination
-
C. Perform a comparative product analysis
-
D. Perform the Close Project process
Frage 193
Frage
Release criteria for team members is defined as part of
Antworten
-
A. 'The organizational management plan.
-
B. The human resources management plan
-
C. The staffing management plan
-
D. 'The work authorization system.
Frage 194
Frage
Communicating via email is considered:
Antworten
-
A. Formal written communication
-
B. Informal written communication
-
C. Formal electronic communication
-
D. Informal non-verbal communication
Frage 195
Frage
Refer to the table at right what is float (slack) of critical path?
Frage 196
Frage
In your project, you would like to generate ideas about a problem. Which one of the following techniques would you use?
Frage 197
Frage
Risk audits look at:
Antworten
-
A. Identification of new risks
-
B. Reassessment of current risks
-
C. Closing of outdated risks
-
D. Effectiveness of the risk management processes
Frage 198
Frage
the most detailed level of the WBS is called:
Antworten
-
A. WBS element
-
B. Work package
-
C. Project
-
D. Deliverables
Frage 199
Frage
Who is the Key Person in the kick-off meeting?
Antworten
-
A. The Project manager
-
B. The project sponsor
-
C. The project team
-
D. The customer
Frage 200
Frage
: In which phase the Kick-off Meeting established?