The following are deliverables produced by the Architect:

Select one of the following:

  • Conceptual Mass Model

  • Preliminary Design Coordination Report between
    Architecture model & Structural model

  • Clash detection & resolution report between Architecture, Structure & MEP models

  • RFI Resolutions

  • All of the above

Explanation

Question 2 of 7

1

Current BIM implementation is still based on a Hybrid method

Select one of the following:

  • True
  • False

Explanation

Question 3 of 7

1

To generate the topography model, the Architect will use topography drawings of the existing site, provided by the Registered Surveyor / Civil Engineers

Select one of the following:

  • True
  • False

Explanation

Question 4 of 7

1

During Schematic design phase, the Architect do not produce

Select one of the following:

  • Layout plans 1:200 scale

  • Outline structural and mechanical design

  • Fabrication details

  • Generic wall / window / door 
components

Explanation

Question 5 of 7

1

During Detail Design phase, the Architect would produce:

Select one or more of the following:

  • Layout plans showing layer construction 1:100 – 1:50 scale

  • 
Produce 1:20 – 1:5 detail drawings 


  • Construction sequencing

Explanation

Question 6 of 7

1

During Details Design phase, Model Exchange is done continuously as the design and project progresses. Early clash detections are performed to lessen conflict of elements before construction.

Select one of the following:

  • True
  • False

Explanation

Question 7 of 7

1

When continue and develop Architecture model to Contractor’s model, basic elements required from the Architecture model are:

Select one or more of the following:

  • X, Y, Z Coordinates 


  • Topography (Existing Site Model) 


  • Topography (Proposed Site Model) 


  • Grid and Level 


  • Building components: Wall, Architectural Column, Door, Window, Slab/ Floor, Ceiling, Fixtures, Furniture (optional), Facade, Railing, etc.