damimgd2u
Quiz by , created more than 1 year ago

Project Mngt Chapter 9 Test Questions

10064
0
0
damimgd2u
Created by damimgd2u about 8 years ago
Close

Project Mngt Chapter 9

Question 1 of 60

1

Preceding activities are those that must occur before others can be done.

Select one of the following:

  • T/F

  • Answer: TRUE

Explanation

Question 2 of 60

1

A backward pass is performed when it is necessary to undo some work that has been performed in order to complete it properly.

Select one of the following:

  • T/F

  • Answer: FALSE

Explanation

Question 3 of 60

1

A merge activity has two or more immediate predecessors.

Select one of the following:

  • T/F

  • Answer: TRUE

Explanation

Question 4 of 60

1

Float is always measured in exactly the same way as slack.

Select one of the following:

  • T/F

  • Answer: TRUE

Explanation

Question 5 of 60

1

The PERT technique assumes that durations are more deterministic

Select one of the following:

  • T/F

  • Answer: FALSE

Explanation

Question 6 of 60

1

Burst activities are those with two or more successor activities.

Select one of the following:

  • T/F

  • Answer: FALSE

Explanation

Question 7 of 60

1

You must know the mean of an activity in order to determine its standard deviation.

Select one of the following:

  • T/F

  • Answer: FALSE

Explanation

Question 8 of 60

1

In assigning a value for the most pessimistic (b) duration, the project manager should estimate the duration of the activity to have a 99% likelihood that it will take b or less amount of time.

Select one of the following:

  • T/F

  • Answer: TRUE

Explanation

Question 9 of 60

1

The late start time should be calculated using a forward pass through the network.

Select one of the following:

  • T/F

  • Answer: FALSE

Explanation

Question 10 of 60

1

Negative float exists when a project's critical path has been completed more quickly than anticipated.

Select one of the following:

  • T/F

  • Answer: TRUE

Explanation

Question 11 of 60

1

The term ordered activity means:
A) tasks must either precede or follow other tasks in project planning and management.
B) tasks cannot be performed unless the project manager issues a specific command to perform the work.
C) prior project planning removes the need for any rush so that tasks can be performed in a methodical fashion.
D) tasks are not performed unless the customer issues a specific request to perform the work.

Select one of the following:

  • M/C

  • Answer: A

Explanation

Question 12 of 60

1

A sequence of activities defined by the project network logic is a(n):
A) event.
B) path.
C) node.
D) route.

Select one of the following:

  • M/C

  • Answer: B

Explanation

Question 13 of 60

1

One of the defining points of a network, a junction point joined to some or all of the others by dependency lines, is called a(n):
A) event.
B) path.
C) node.
D) burst.

Select one of the following:

  • M/C

  • Answer: C

Explanation

Question 14 of 60

1

These can be located by doing a backward pass through a network.
A) critical paths
B) merge activities
C) successors
D) burst activities

Select one of the following:

  • M/C

  • Answer: D

Explanation

Question 15 of 60

1

An activity with two or more immediate predecessors is a(n):
A) merge activity.
B) burst activity.
C) float activity.
D) event.

Select one of the following:

  • M/C

  • Answer: A

Explanation

Question 16 of 60

1

The amount of time an activity may be delayed from its early start without delaying the finish of the project is the:
A) delay.
B) float.
C) late start.
D) late finish.

Select one of the following:

  • M/C

  • Answer: B

Explanation

Question 17 of 60

1

The least amount of float is found:
A) in a resource-limited schedule.
B) after a burst activity.
C) on the critical path.
D) after a merge activity.

Select one of the following:

  • M/C

  • Answer: C

Explanation

Question 18 of 60

1

Prior to creating a network, it is important to:
A) identify all loops through activities.
B) identify the party responsible for each activity.
C) calculate the float for each activity.
D) understand the activity precedence.

Select one of the following:

  • M/C

  • Answer: D

Explanation

Question 19 of 60

1

Serial activities are those that:
A) flow from one to the next in sequence.
B) have sequential numbers.
C) have the same numbers.
D) should be performed simultaneously.

Select one of the following:

  • M/C

  • Answer: A

Explanation

Question 20 of 60

1

Concurrent activities are:
A) activities that must be done one after the other.
B) activities that can be performed at the same time.
C) activities that use labor from the same group of workers.
D) activities that use resources from the same resource pool.

Select one of the following:

  • M/C

  • Answer: B

Explanation

Question 21 of 60

1

Which of these statements about this network is best?


A) Activities A and B are serial activities.
B) Activities B and C are serial activities.
C) Activities A and C are serial activities.
D) Activity D is a merge activity.

Select one of the following:

  • M/C

  • Answer: D

Explanation

Question 22 of 60

1

Network logic suggests that:


A) Activity D can start any time.
B) Activity A must be complete before Activity B can be done.
C) Activities A, B and C must be complete before Activity D can be done.
D) Activity C must begin before Activity B begins.

Select one of the following:

  • M/C

  • Answer: C

Explanation

Question 23 of 60

1

What is the earliest that Activity D can begin if Activity A takes 3 days, Activity B takes 5 days, and Activity C takes 7 days?


A) day 15
B) day 7
C) day 5
D) day 3

Select one of the following:

  • M/C

  • Answer: B

Explanation

Question 24 of 60

1

Based on the activity network pictured, what is the best statement?


A) Before starting Activity C, Activity A and Activity B must be completed.
B) Before starting Activity D, Activity A and Activity B need to be completed.
C) Before starting Activity E, Activity A and Activity B need to be completed.
D) Before starting Activity C, Activity A and Activity D must be completed.

Select one of the following:

  • M/C

  • Answer: A

Explanation

Question 25 of 60

1

Based on the activity network pictured, what is the best statement?


A) Activity C is a burst activity.
B) Activity E has one predecessor, Activity B.
C) Activity A and Activity C are merge activities.
D) There are no serial activities in this network.

Select one of the following:

  • M/C

  • Answer: B

Explanation

Question 26 of 60

1

The length of time expected to complete an activity assuming that its development proceeds normally is called the:
A) optimistic duration.
B) pessimistic duration.
C) most likely duration.
D) normal duration.

Select one of the following:

  • M/C

  • Answer: C

Explanation

Question 27 of 60

1

Ray's shipment of materials hit every red light and traffic jam on the way to the site. Upon arrival, half of the material was judged defective, necessitating a trip back to the supplier, and then the same arduous journey back to the site once the new materials were loaded. Traffic was a little better on the second round but the flat tire and subsequent repair caused as much if not more delay than the first trip. In the final analysis:
A) the project activity of Material Delivery was pretty close to the optimistic estimate.
B) the project activity of Material Delivery was pretty close to the most likely estimate.
C) the project activity of Material Delivery had a much higher variance than anticipated.
D) the project activity of Material Delivery was pretty close to the pessimistic estimate.

Select one of the following:

  • M/C

  • Answer: D

Explanation

Question 28 of 60

1

The variance of an activity is given by:
A) [1/6(b-a)]2.
B) 1/6[b-a].
C) [1/36(b-a)]2.
D) 1/36[b-a].

Select one of the following:

  • M/C

  • Answer: A

Explanation

Question 29 of 60

1

An activity has an optimistic time estimate of 15 days, a most likely estimate of 24 days, and a pessimistic estimate of 40 days. What is the expected duration of the activity?
A) less than 27 days but greater than or equal to 26 days
B) less than 26 days but greater than or equal to 25 days
C) less than 25 days but greater than or equal to 24 days
D) less than 24 days

Select one of the following:

  • M/C

  • Answer: B

Explanation

Question 30 of 60

1

An activity has an optimistic time estimate of 15 days, a most likely estimate of 24 days, and a pessimistic estimate of 40 days. What is the variance of the activity?
A) 4.17
B) 25.17
C) 17.36
D) 10.33

Select one of the following:

  • M/C

  • Answer: C

Explanation

Question 31 of 60

1

An activity has an optimistic time estimate of 7 days, a most likely estimate of 12 days, and a pessimistic estimate of 20 days. What is the expected duration of the activity?
A) 13 days
B) 13.5 days
C) 12 days
D) 12.5 days

Select one of the following:

  • M/C

  • Answer: D

Explanation

Question 32 of 60

1

An activity has an optimistic time estimate of 7 days, a most likely estimate of 12 days, and a pessimistic estimate of 20 days. What is the expected standard deviation of the activity?
A) between 2 and 3 days
B) between 3 and 4 days
C) between 4 and 5 days
D) between 5 and 6 days

Select one of the following:

  • M/C

  • Answer: D

Explanation

Question 33 of 60

1

An activity has a pessimistic time that is three times as long as its most likely time and five times as long as its optimistic time. If the activity variance is 10, what is the expected time?
A) about 10 days
B) about 14 days
C) about 19 days
D) about 23 days

Select one of the following:

  • M/C

  • Answer: A

Explanation

Question 34 of 60

1

Activity Z has estimates a = 5, b = 10, m = 7; activity X has estimates a = 4, b = 11, m = 6; and activity Y has estimates a = 3, b = 12, m = 8. Which of the following statements is best?
A) Activity X is longer than Activity Y.
B) Activity X has a higher standard deviation than Activity Z.
C) Activity Z is shorter than Activity Y.
D) Activity Y has a smaller variance than Activity Z.

Select one of the following:

  • M/C

  • Answer: B

Explanation

Question 35 of 60

1

What is the early start time for Activity D given the activity times and precedence requirements shown in the table?

Activity Time Predecessor
A 5 --
B 8 A
C 4 A
D 5 B, C

A) 5
B) 9
C) 13
D) 18

Select one of the following:

  • M/C

  • Answer: C

Explanation

Question 36 of 60

1

What is the late start time for Activity B given the activity times and precedence requirements shown in the table?

Activity Time Predecessor
A 5 --
B 8 A
C 4 A
D 5 B, C

A) 18
B) 9
C) 13
D) 5

Select one of the following:

  • M/C

  • Answer: D

Explanation

Question 37 of 60

1

What is the late start time for Activity E given the activity times and precedence requirements shown in the table?

Activity Time Predecessor
A 4 --
B 7 --
C 8 A
D 2 A
E 4 B
F 5 C, D
G 9 E, F
H 7 G

A) 12
B) 13
C) 14
D) 15

Select one of the following:

  • M/C

  • Answer: B

Explanation

Question 38 of 60

1

What is the late finish time for Activity D given the activity times and precedence requirements shown in the table?

Activity Time Predecessor
A 4 --
B 7 --
C 8 A
D 2 A
E 4 B
F 5 C, D
G 9 E, F
H 7 G

A) 14
B) 13
C) 12
D) 11

Select one of the following:

  • M/C

  • Answer: C

Explanation

Question 39 of 60

1

What is the early start time for Activity G given the activity times and precedence requirements shown in the table?

Activity Time Predecessor
A 4 --
B 7 --
C 8 A
D 2 A
E 4 B
F 5 C, D
G 9 E, F
H 7 G

A) 14
B) 15
C) 16
D) 17

Select one of the following:

  • M/C

  • Answer: D

Explanation

Question 40 of 60

1

What is the early finish time for Activity F given the activity times and precedence requirements shown in the table?

Activity Time Predecessor
A 4 --
B 7 --
C 8 A
D 2 A
E 4 B
F 5 C, D
G 9 E, F
H 7 G

A) 17
B) 12
C) 13
D) 26

Select one of the following:

  • M/C

  • Answer: A

Explanation

Question 41 of 60

1

What is the slack time for Activity B given the activity times and precedence requirements shown in the table?

Activity Time Predecessor
A 4 --
B 7 --
C 8 A
D 2 A
E 4 B
F 5 C, D
G 9 E, F
H 7 G

A) 7
B) 6
C) 5
D) 4

Select one of the following:

  • M/C

  • Answer: B

Explanation

Question 42 of 60

1

What is the slack time for Activity C given the activity times and precedence requirements shown in the table?

Activity Time Predecessor
A 4 --
B 7 --
C 8 A
D 2 A
E 4 B
F 5 C, D
G 9 E, F
H 7 G

A) 2
B) 1
C) 0
D) 3

Select one of the following:

  • M/C

  • Answer: C

Explanation

Question 43 of 60

1

What is the float start time for Activity C given the activity times and precedence requirements shown in the table?

Activity Time Predecessor
A 5 --
B 8 A
C 4 A
D 5 B, C

A) 1
B) 2
C) 3
D) 4

Select one of the following:

  • M/C

  • Answer: D

Explanation

Question 44 of 60

1

Use the information in the table to determine the late start time for Activity E.

Task Predecessor Duration Early Start Early Finish Late Start Late Finish
A -- 8
B A 14
C A 23 8
D C, B 6 23 26
E C 32
F D, E 32 38

A) day 23
B) day 26
C) day 32
D) day 17

Select one of the following:

  • M/C

  • Answer: A

Explanation

Question 45 of 60

1

Use the information in the table to determine the early start time for Activity B.

Task Predecessor Duration Early Start Early Finish Late Start Late Finish
A -- 8
B A 14
C A 23 8
D C, B 6 23 26
E C 32
F D, E 32 38

A) day 10
B) day 8
C) day 9
D) day 11

Select one of the following:

  • M/C

  • Answer: B

Explanation

Question 46 of 60

1

Use the information in the table to determine the early finish time for Activity D.

Task Predecessor Duration Early Start Early Finish Late Start Late Finish
A -- 8
B A 14
C A 23 8
D C, B 6 23 26
E C 32
F D, E 32 38

A) day 23
B) day 26
C) day 29
D) day 32

Select one of the following:

  • M/C

  • Answer: C

Explanation

Question 47 of 60

1

Use the information in the table to determine the late finish time for Activity B.

Task Predecessor Duration Early Start Early Finish Late Start Late Finish
A -- 8
B A 14
C A 23 8
D C, B 6 23 26
E C 32
F D, E 32 38

A) day 17
B) day 26
C) day 20
D) day 23

Select one of the following:

  • M/C

  • Answer: D

Explanation

Question 48 of 60

1

Use the information in the table to determine the slack time for Activity B.

Task Predecessor Duration Early Start Early Finish Late Start Late Finish
A -- 8
B A 14
C A 23 8
D C, B 6 23 26
E C 32
F D, E 32 38

A) 6 days
B) 4 days
C) 2 days
D) 0 days

Select one of the following:

  • M/C

  • Answer: A

Explanation

Question 49 of 60

1

What is the slack time for activity E?

Task Predecessor Duration Early Start Early Finish Late Start Late Finish
A -- 8
B A 14
C A 23 8
D C, B 6 23 26
E C 32
F D, E 32 38

A) 1 day
B) 0 days
C) 2 days
D) 4 days

Select one of the following:

  • M/C

  • Answer: B

Explanation

Question 50 of 60

1

Use the network diagram and activity lengths in the nodes to determine the early start time for activity D.


A) 8
B) 13
C) 14
D) 21

Select one of the following:

  • M/C

  • Answer: C

Explanation

Question 51 of 60

1

Use the network diagram and activity lengths in the nodes to determine the late start time for activity F.


A) 21
B) 24
C) 26
D) 23

Select one of the following:

  • M/C

  • Answer: D

Explanation

Question 52 of 60

1

Use the network diagram and activity lengths in the nodes to determine the early finish time for activity G.

A) 26
B) 25
C) 24
D) 23

Select one of the following:

  • M/C

  • Answer: A

Explanation

Question 53 of 60

1

Use the network diagram and activity lengths in the nodes to determine the late finish time for activity C.


A) 12
B) 13
C) 14
D) 15

Select one of the following:

  • M/C

  • Answer: C

Explanation

Question 54 of 60

1

Use the network diagram and activity lengths in the nodes to determine the slack time for activity D.


A) 3
B) 2
C) 1
D) 0

Select one of the following:

  • M/C

  • Answer: D

Explanation

Question 55 of 60

1

Use the network diagram and activity lengths in the nodes to determine the early start time for activity D.


A) 8
B) 13
C) 14
D) 21

Select one of the following:

  • M/C

  • Answer: C

Explanation

Question 56 of 60

1

There's an old saying, "The job is not finished until the paperwork is done." From an activity network standpoint, this does not necessarily mean that the paperwork can't begin until the last non-paperwork activity is completed. It might be possible to work on some paperwork as early activities are completed. In order to depict this in an activity network:
A) hammock activities could be drawn.
B) subroutines could be added.
C) shortcuts can be added to the network.
D) laddering could be used to redraw the network.

Select one of the following:

  • M/C

  • Answer: D

Explanation

Question 57 of 60

1

Project Test Bank is composed of activities we will refer to as A, B, C, and D for convenience (and lack of creativity). Durations and precedence requirements are shown in the table. Each of these activities can be conveniently laddered into two sub-activities of equal duration. The first half of each activity serves as the predecessor to its second half and the first half of the original following activity. What is the expected completion time of the laddered project?

Activity Length Predecessor
A 10 --
B 18 A
C 14 A
D 20 B, C

A) 34
B) 38
C) 42
D) 48

Select one of the following:

  • M/C

  • Answer: A

Explanation

Question 58 of 60

1

Project Test Bank is composed of activities we will refer to as A, B, C, and D for convenience (and lack of creativity). Durations and precedence requirements are shown in the table. Each of these activities can be conveniently laddered into two sub-activities of equal duration. The first half of each activity serves as the predecessor to its second half and the first half of the original following activity. What is the expected completion time of the laddered project?

Activity Length Predecessor
A 10 --
B 18 A
C 14 A
D 20 B, C

A) 34
B) 38
C) 42
D) 48

Select one of the following:

  • M/C

  • Answer: B

Explanation

Question 59 of 60

1

Project Test Bank is composed of activities we will refer to as A, B, C, and D for convenience (and lack of creativity). Durations and precedence requirements are shown in the table. Each of these activities can be conveniently laddered into two sub-activities of equal duration, so activity C in the original project becomes two activities, C1 and C2, each of which lasts 7 days. The first half of each activity serves as the predecessor to its second half and the first half of the original following activity. What is the difference in the late start time for activity C in the original project and activity C1 in the laddered project?

Activity Length Predecessor
A 10 --
B 18 A
C 14 A
D 20 B, C

A) 3
B) 5
C) 7
D) 9

Select one of the following:

  • M/C

  • Answer: C

Explanation

Question 60 of 60

1

A gentleman farmer maniacally works on academic projects to raise funds for his true passion, farming. He has identified seven tasks and developed three time estimates (all in days) of the next big project on the farm, replacing the fence at the comedy pasture. Tasks, precedence requirements, and time estimates are shown in the table. What is the expected completion time of the project?

Activity Optimistic time Most Likely time Pessimistic time Predecessor
Corner Posts 4 5 6 --
String Line 7 8 9 --
Dig Holes 10 12 14 Corner Posts
Plant Posts 11 14 17 String Line
Weld Top Bar 8 11 14 String Line
Paint 9 11 13 Dig Holes, Plant Posts
Tack Wire 9 12 16 Weld Top Bar

A) 32 days
B) 33 days
C) 34 days
D) 35 days

Select one of the following:

  • M/C

  • Answer: B

Explanation