The RIBA Plan of Work 2013 Unit 5 M1 Preparation

Question 1 of 20

1

How may stages are in the RIBA Plan of work 2013

Select one of the following:

  • 7

  • 5

  • 10

  • 8

  • 12

Explanation

Question 2 of 20

1

Which part of the stage of the RIBA Plan of Work 2013 is particularly relevant in the context of sustainability.

Select one of the following:

  • Stage 4

  • Stage 1

  • Stage 0

  • Stage 7

  • Stage 5

Explanation

Question 3 of 20

1

Stage 6 is primarily concerned with?

Select one of the following:

  • Post occupancy

  • Concept design

  • Preparation and brief

  • Hand over and close out

  • Developed design maps

Explanation

Question 4 of 20

1

What does BIM stand for

Select one of the following:

  • Building Information Modelling

  • Business Information Modelling

  • Built Individual Model

  • Building In Materials

Explanation

Question 5 of 20

1

Which stage is a new stage in which a project is strategically appraised and defined before a detailed brief is created?

Select one of the following:

  • Stage 4 Technical Design

  • Stage 5 Construction

  • Stage 0 Strategic Definition

  • Stage 3 Developed Design

Explanation

Question 6 of 20

1

Which stage of the RIBA plan of Work focuses on making sure the that the initial business case matches the desired outcomes.

Select one of the following:

  • Stage 7 In use

  • Stage 0 Strategic definition

  • Stage 6 Handover and close out

  • Stage 3 Developed design

  • Stage 5 Construction

Explanation

Question 7 of 20

1

What is meant by the term procurement?

Select one of the following:

  • The design and execution of the infrastructure .

  • The construction of an object or a system.

  • The acquisition of goods, services or works from an outside external source.

  • Preparing for and forming building systems.

Explanation

Question 8 of 20

1

Is The RIBA Plan of Work 2013 itself a contractual document?

Select one of the following:

  • Yes

  • No

Explanation

Question 9 of 20

1

Within the RIBA Plan of work which task bars are fixed and always present?

Select one of the following:

  • Task Bar 1 Core Objectives, Task Bar 3 Programme & Task Bar 8 Government Gateways.

  • Task Bar 8 Government Gateways, Task Bar 6 Sustainability Checkpoints & Task Bar 3 Programme

  • Task Bar 1 Core Objectives,Task Bar 5 Key Support Tasks, & Task Bar 7 Information Exchanges

  • Task Bar 6 Sustainability Checkpoints,Task Bar 4 (Town) Planning &Task Bar 2 Procurement

Explanation

Question 10 of 20

1

Which two task-bars can be switched on or off in The RIBA Plan of Work 2013?

Select one of the following:

  • Task Bar 6 Sustainability Checkpoints & Task Bar 8 Government Gateways.

  • Task Bar 3 Programme & Task Bar 1 Core Objectives.

  • Task Bar 2 Procurement & Task Bar 5 Key Support Tasks,

  • Task Bar 8 UK Government Information Exchanges & Task Bar 6 Sustainability Checkpoints.

Explanation

Question 11 of 20

1

Which three task-bars are variable in The RIBA Plan of Work 2013?

Select one of the following:

  • Task Bar 4 (Town) Planning, Task Bar 5 Key Support Tasks & Task Bar 1 Core Objectives.

  • Task Bar 2 Procurement ,Task Bar 3 Programme & Task Bar 8 Government Gateways.

  • Task Bar 3 Programme ,Task Bar 2 Procurement & Task Bar 4 (Town) Planning

  • Task Bar 6 Sustainability Checkpoints, Task Bar 1 Core Objectives & Task Bar 5 Key Support Tasks.

Explanation

Question 12 of 20

1

Why has the UK Government Information Exchanges task bar has been introduced?

Select one of the following:

  • To encourage consideration of the stages that the UK Government requires information to be exchanged.

  • To provide guidance on the information that would typically be delivered at the Information Exchanges at the end of each stage.

  • To allow for a number of forms of procurement.

  • To underline the need on every project for a Project Programme that sets out the duration of each stage and any supporting activities.

Explanation

Question 13 of 20

1

What has been a core requirement of collaborative contracts for some time as it ensures that each party is involved in the process of agreeing timescales and is fully aware of the risks that the programme generates in relation to their specific Schedule of Services?

Select one of the following:

  • Construction Programme

  • Design Programme

  • Building Contract

  • Project Programme.

Explanation

Question 14 of 20

1

On certain projects, where it is uncertain that consent will be granted, can the client appoint all of the designers or may appoint them on a restricted Stage 2 Schedule of Services?

Select one of the following:

  • Yes

  • No

Explanation

Question 15 of 20

1

The Sustainability Checkpoints task bar is selectable and can be switched off?

Select one of the following:

  • True
  • False

Explanation

Question 16 of 20

1

Where detailed circumstances specific to a given project require an alternative approach, what should used to deal with this?

Select one of the following:

  • Building Contract

  • Health and Safety Strategy

  • Project Programme.

  • Design Responsibility Matrix

Explanation

Question 17 of 20

1

What does the UK Government recognise that a client does not need to be involved in?

Select one of the following:

  • Every Information Exchange

  • Data-rich information that can be used post- occupancy to manage its entire estate and to allow stringent benchmarking activities to occur.

Explanation

Question 18 of 20

1

Which task-bar sets out key tasks in relation to statutory requirements, such as those relating to Building Regulations submissions and project and design management protocols, roles and responsibilities?

Select one of the following:

  • Task Bar 7 Information Exchanges

  • Task Bar 5 Key Support Tasks

  • Task Bar 1 Core Objectives

  • Task Bar 8 Government Gateways

Explanation

Question 19 of 20

1

It is also acknowledged that on certain projects (conservation projects, for example) other planning matters may have to be concluded during which other stage?

Select one of the following:

  • Task Bar 5 Key Support Tasks

  • Task Bar 4 (Town) Planning

  • Task Bar 3 Programme

  • Task Bar 2 Procurement

Explanation

Question 20 of 20

1

The RIBA Plan of Work 2013 does all of the following Acts across the full range of sectors and project sizes: Provides straight-forward mapping for all forms of procurement.
Integrates sustainable design processes. Maps Building Information Modelling (BIM) processes and provides flexible around (town) planning procedures.

Select one of the following:

  • True
  • False

Explanation