PO - Test 2

Question 1 of 10

1

1. Definition of “Done” is

Select one of the following:

  • a) Initially defined per product by Scrum Team, but may change throughout the product development duration

  • b) Initially defined per Scrum Team, and doesn’t change

  • c) Defined after first Sprint based on the new insights obtained from first Sprint Review

Explanation

Question 2 of 10

1

2. Which of the following statements are true? Select all that apply

Select one or more of the following:

  • a) After Sprint Planning, a sprint cannot proceed without complete requirement specification

  • b) After Sprint Planning, a sprint cannot proceed without a Sprint Goal

  • c) After Sprint Planning, a sprint can proceed without complete Sprint Backlog

  • d) After Sprint Planning, a sprint cannot proceed without complete architecture

Explanation

Question 3 of 10

1

3. A Development Team is self-organized and empowered. It is also the authority on deciding what business needs are required to be developed

Select one of the following:

  • a) True

  • b) False

Explanation

Question 4 of 10

1

4. Who decides the duration of the Sprint?

Select one of the following:

  • a) Product manager

  • b) Scrum Master

  • c) Development Team

  • d) Scrum Team

Explanation

Question 5 of 10

1

5. A Product Owner is not available for Scrum events and not supportive enough for Development Team. The next immediate accountability is with

Select one of the following:

  • a) Development Team that needs to cancel the Sprint

  • b) Stakeholders that need to get a written commitment from Product Owner

  • c) Product Owner’s manager who needs to engage the Development Team and understand their problems

  • d) Scrum Master, who needs to educate Product Owner on his role

Explanation

Question 6 of 10

1

6. When a Product Backlog is retired?

Select one of the following:

  • a) When the Product Owner retires

  • b) When all the Sprints are over

  • c) When the Product retires

  • d) When the Customer provides the sign-off on completion of the project

Explanation

Question 7 of 10

1

7. A Product Owner cannot send a representative (delegate) to the Sprint Review.

Select one of the following:

  • a) True

  • b) False

Explanation

Question 8 of 10

1

8. A Product Owner is also knowledgeable on technology. In addition to product requirements, they also impose some technical conditions that the product should meet. These conditions must be added to

Select one of the following:

  • a) Product Backlog

  • b) Sprint Backlog

  • c) Definition of “Done”

Explanation

Question 9 of 10

1

9. An increment is

Select one of the following:

  • a) The sum of the value of all increments from previous iterations integrated with the Product Backlog Items “done” in latest Sprint

  • b) The sum of Product Backlog Items selected into Sprit Backlog

  • c) The sum of Product Backlog Items “done” in latest Sprint

Explanation

Question 10 of 10

1

10. What are the true statements?

Select one or more of the following:

  • a) Scrum Team is responsible for formulating a Sprint Goal

  • b) When existing Product Backlog Items in the Sprint Backlog are modified, the Sprint Goal is bound to become invalid

  • c) The coherence between Product Backlog items is made transparent by Sprint Goal. Lack of coherence will lead to them working individually

Explanation