PO - Test3

Question 1 of 10

1

1. The role of Scrum Master in Sprint Retrospective is

Select one of the following:

  • a) Auditor

  • b) Silent Observer

  • c) Peer Team Member

  • d) None of the above

Explanation

Question 2 of 10

1

2. To deliver a single product, three different Development Teams are formed. How many Product Owners are needed?

Select one of the following:

  • a) As many as recommended by Scrum Master

  • b) Three

  • c) One

Explanation

Question 3 of 10

1

3. Scrum framework is founded on

Select one of the following:

  • a) Empiricism

  • b) Empiricism and Technical Practices

  • c) Empiricism and Emotional Intelligence

Explanation

Question 4 of 10

1

4. After Sprint Review, Production release in Scrum requires

Select one of the following:

  • a) Hardening Sprints

  • b) Non-Functional Testing

  • c) Architectural Validations

  • d) Usability/End User testing

  • e) All of the above

  • f) None of the above

Explanation

Question 5 of 10

1

5. A Scrum Team crafts the following Sprint Goal: “All the Sprint code should have passed 100% automated unit tests”.

Select one of the following:

  • a) Not an appropriate goal, since Sprint goal should be about expected business value

  • b) It is incorrect, since Product Owner formulates the goal and not the Scrum Team

  • c) It is well formed Sprint Goal

Explanation

Question 6 of 10

1

6. One of the Scrum Teams chose to have a Development Team member also playing the role of Scrum Master. A Development Team member cannot also play Scrum Master’s role.

Select one of the following:

  • a) True

  • b) False

Explanation

Question 7 of 10

1

7. Duration (length) of the Sprint is decided by

Select one of the following:

  • a) Product Owner

  • b) Scrum Master

  • c) Scrum Team

Explanation

Question 8 of 10

1

8. During Daily Scrum, this plan is used as a reference to understand the changes in progress.

Select one of the following:

  • a) Sprint Backlog

  • b) Product Backlog

  • c) Sprint Burn-down

Explanation

Question 9 of 10

1

9. An important executive wants the Development Team to take in a highly critical feature in the current Sprint. The Development Team

Select one of the following:

  • a) Will work on that since organization priority is more important

  • b) Will ask the executive to work with Product Owner

  • c) As empowered team, will seek the executive to select an alternative work to be removed instead

Explanation

Question 10 of 10

1

10. A Scrum Team is in the process of defining Product Backlog items. The Scrum Master notices that the team is not using User Story format to capture the backlog items. Scrum Master should

Select one of the following:

  • a) correct the team’s behavior by coaching them about user stories

  • b) let the team decide the format of Product Backlog items

  • c) add a business analyst with knowledge of writing user stories to the team, with specific responsibility of documenting backlog in terms of user stories

Explanation