starshyne
Quiz by , created more than 1 year ago

Taking the PMP exam? Try these practice questions to make sure you are fully ready.

11
0
0
Andrea Leyden
Created by Andrea Leyden over 8 years ago
starshyne
Copied by starshyne over 8 years ago
Close

PMP Prep quiz

Question 1 of 10

1

Most common cause of conflicts in a project is:

Select one of the following:

  • Schedules

  • Technical Opinions

  • Personal Issues

  • Project Priorities

Explanation

Question 2 of 10

1

You are the Project Manager of the XYZ project. You want to find the planned expenses for next month. Which document do you need to refer to?

Select one of the following:

  • Cost Management Plan

  • Cost Baseline

  • Cost Control Plan

  • Cost Variance report

Explanation

Question 3 of 10

1

You are working on the project of painting of your house. You identify a dependency that the painting of roof should begin only after two days of completion of painting of walls. This is an example of :

Select one of the following:

  • Lag

  • Lead

  • Slack

  • Float

Explanation

Question 4 of 10

1

Control Procurements is a process in the Project Procurement Management Knowledge area.

Select one of the following:

  • True
  • False

Explanation

Question 5 of 10

1

Which of the following theory was suggested by Deming?

Select one of the following:

  • Apply continuous small improvements to reduce costs and ensure consistency.

  • Marginal Analysis

  • Expectancy theory - people expect to be rewarded for their efforts.

  • Plan-do-check-act to improve quality.

Explanation

Question 6 of 10

1

You are required to estimate the time to paint a large wall. You know it takes two hours to paint one square foot of wall. The wall has an area of 30 square foot. So you estimate that it will take 60 hours to paint the wall. Which estimation model are you using?

Select one of the following:

  • Bottom-up

  • Parametric modeling

  • Analogous

  • Expert judgment

Explanation

Question 7 of 10

1

In which process of Project Risk Management knowledge area are numeric values assigned to probabilities and impact of risks?

Select one of the following:

  • Perform Qualitative Risk Analysis

  • Perform Quantitative Risk Analysis

  • Perform Numeric Risk Analysis

  • Plan Risk Response

Explanation

Question 8 of 10

1

Which of the following is an output of the Identify Risks process.

Select one of the following:

  • Lessons Learned

  • Checklists

  • Risk Register

  • SWOT Analysis

Explanation

Question 9 of 10

1

The process of Conduct Procurements is part of the planning phase.

Select one of the following:

  • True
  • False

Explanation

Question 10 of 10

1

Which process identifies the project manager?

Select one of the following:

  • Develop Project Management Plan

  • Develop Project Charter

  • Define Scope

  • Select Project Process

Explanation