Niamh Ryan
Quiz by , created more than 1 year ago

Quiz on project management

74
0
0
Niamh Ryan
Created by Niamh Ryan almost 7 years ago
Close

Project Management Tools Quiz

Question 1 of 10

1

A critical activity has...

Select one of the following:

  • Negative slack time

  • Zero slack time

  • Positive slack time

Explanation

Question 2 of 10

1

Select from the dropdown lists to complete the text.

Critical path: The path of activities which represent the ( longest, shortest ) total time required to complete the project. A delay in an activity on the critical path causes a delay in the ( entire project, preceding activity, parallel activities ).

Explanation

Question 3 of 10

1

Select from the dropdown lists to complete the text.

Finish to start lag: The minimum amount of time that must pass between the ( finish, start ) of one activity and the ( finish, start ) of its successor(s)

Explanation

Question 4 of 10

1

Select from the dropdown list to complete the text.

The variance in the project completion time can be calculated by ( subtracting, summing, multiplying ) the variances in the completion times of the activities in the critical path

Explanation

Question 5 of 10

1

Fill the blank space to complete the text.

The normal distribution assumption holds if the number of activities in the path is large enough for the to be applied.

Explanation

Question 6 of 10

1

Fill the blank space to complete the text.

The following times for completion an activity have been estimated.
Optimistic time: 4 days
Most likely time: 7 days
Pessimistic time: 10 days.
The variance in the expected time is days.

Explanation

Question 7 of 10

1

Fill the blank spaces to complete the text.

When preparing a Work Breakdown Structure, continue to subdivide components until the lowest level component requires between and hours of work.

Explanation

Question 8 of 10

1

Fill the blank space to complete the text.

When components of a WBS are defined in sufficient detail for management and planning purposes, they are known as .

Explanation

Question 9 of 10

1

Fill the blank space to complete the text.

High level elements in the WBS should match, word for word, nouns used to describe outcomes in the .

Explanation

Question 10 of 10

1

Fill the blank space to complete the text.

The current activity has an Early Start of March 1st and a duration of 3 days.
The succeeding activity has an Early Start of March 7th. Assuming everyday is a work day, then the free float is days.

Explanation