SAB4#98 Pre Assignment VS Acquisition
  1. Pre-assignment
    1. Is when you can actually build the assignments into your staffing management plan. Sometimes you have resources who are guaranteed to you when you start the project, so you don't need to negotiate for them.
    2. Acquisition
      1. Means going outside of your company to contractors and consultants to staff your team.
      2. When the resource is available, the cost of pre-assignement is less than acquisition. PMI orientation is: use FIRST the internal available resource BEFORE outsourcing resource.