Network Diagrams
AOA Vs. AON Activities on arc vr. Activities on node
Node Labels
Duration Estimation Methods • Past experience • Expert opinion • Mathematical derivation – Beta distribution – Most likely (m) – Most pessimistic (b) – Most optimistic (a)
Constructing the Critical Path • Forward pass – an additive move through the network from start to finish • Backward pass – a subtractive move through the network from finish to start • Critical path – the longest path from end to end which determines the shortest project length
Rules for Forward pass Forward Pass Rules (ES & EF) – ES + Duration = EF – EF of predecessor = ES of successor – Largest preceding EF at a merge point becomes EF for successor
Rules for Backward Pass Backward Pass Rules (LS & LF) – LF – Duration = LS – LS of successor = LF of predecessor – Smallest succeeding LS at a burst point becomes LF for predecessor
Reducing the Critical Path • Eliminate tasks on the CP • Convert serial paths to parallel when possible • Overlap sequential tasks • Shorten the duration on critical path tasks • Shorten – early tasks – longest tasks – easiest tasks – tasks that cost the least to speed up
Show full summary Hide full summary

Similar

Projectmanagement Skript 4 Übung 4
Lukas Berger
Projectmanagement Skript 5 Übung 5
Lukas Berger
Projectmanagement Skript 2 Übung 2
Lukas Berger
Projectmanagement Sript 6 Übung 6
Lukas Berger
Projectmanagement Skript 7 Übung 7
Lukas Berger
Projectmanagement Skript 3 Übung 3
Lukas Berger
Business Studies Unit 2
tara.springate
GCSE Maths Quiz
Andrea Leyden
A Level: English language and literature techniques = Structure
Jessica 'JessieB
Geography Coasts Questions
becky_e
An Inspector calls - Gerald Croft
Rattan Bhorjee