SAB9# 63 Analysis Diagram Red

Description

pm Curso PM Mind Map on SAB9# 63 Analysis Diagram Red, created by Juan Garcia on 25/02/2016.
Juan Garcia
Mind Map by Juan Garcia, updated more than 1 year ago
Juan Garcia
Created by Juan Garcia about 8 years ago
28
0

Resource summary

SAB9# 63 Analysis Diagram Red
  1. Definition
    1. A diagramming technique to visualize the dependencies of the activities and calculate the total duration of the project.
    2. Dependence
      1. • (FS) Finish to Start: The start of the activity thus successor to the completion of the predecessor activity
        1. • (FF) Final Final: The completion of the successor activity depends upon the completion of the predecessor activity.
          1. • (SS) Star to Start The initiation of the successor activity depends upon the initiation of the predecessor activity.
            1. • (SF) Start to Finish: The completion of the successor activity depends upon the initiation of the predecessor activity.
            2. Characteristics:
              1. Each activity is represented by a box and only one
                1. Each frame has a number of unique activities
                  1. The activities are arranged in the order of the presidency to know when you start first
                    1. You can start an activity to finish the preceding
                      1. There may be concurrent activities
                      2. Concepts
                        1. • Predecessor Activity: Activity that precedes the successor activity
                          1. • successor Activity: Activity happens predecessor activities
                            1. • Critical Path: Path or going from start to finish and also takes longer compared to other routes
                              1. • Full Clearance: The additional time available to complete an activity, if all the above activities as early as possible and start the following latest
                                1. • free float; Is the additional time that may extend an activity without affecting the next start of any subsequent activity
                                  1. the critical chain is the sequence of precedences and dependent on resources that prevent a project, which is given limited resources, can be completed in less time terminal elements . If the resources of a project were always available in unlimited quantities , then the critical chain of a project would be equal to its critical path.
                                  2. Steps
                                    1. Define the project and prepare the work breakdown structure
                                      1. Development of relations between activities
                                        1. Draw the network connecting all activities
                                          1. Calculate the time of the longest path
                                            1. Using the network to help plan your schedule, you supervise and control the project
                                    2. Activities list
                                      Show full summary Hide full summary

                                      Similar

                                      Unit 3.1: Marketing
                                      nk_
                                      The Gettysburg Address
                                      PrincessLaura
                                      G481 Mechanics Definitions
                                      nikeishabk
                                      BIOLOGY B1 1
                                      x_clairey_x
                                      Analysing Text
                                      amberbob27
                                      MAPA MENTAL
                                      blanca beatriz m
                                      Chemistry revision
                                      Jordyn Niu
                                      Flame tests
                                      Joshua Rees
                                      CCNA Security 210-260 IINS - Exam 2
                                      Mike M
                                      CSA IITU Part 1 (235)
                                      Hello World