SAB4#55_Estimate_Activities_Duration

Annotations:

  • * Estimate Activity Durations is the process of estimating the numbers of work periods needed to complete individual activities with estimated resources. * Estimate how much time each Activity will take.
  1. Process: Estimate Activity Durations
    1. Process Group: Planning
      1. Knowledge Area: Time Management
        1. 1. Schedule Management Plan
          1. 2. Activity list
            1. 3. Activity attributes
              1. 4. Activity resources requirements
                1. Estimate Activities Resources
                2. 5. Resource Calendars
                  1. 6. Project Scope Statement
                    1. 7. Risk Register
                      1. 8. Resource breakdown structure RBS
                        1. Estimate Activities Resources
                        2. 9. EEF
                          1. 10. OPAs
                            1. 1. Expert Judgment

                              Annotations:

                              • Will come from your project team members who are familiar with the work that has to be done.
                              1. 2. Analogous Estimation (Top Down)

                                Annotations:

                                • Is when you look at activities from previous projects that were similar to this one and look at how long it took to do similar work before.
                                1. 3. Parametric Estimating

                                  Annotations:

                                  • Parametric estimating looks at the relationships between variables on an activity to calculate time or cost estimates.  The data can come  from historical records from previous projects, industry requirements, standard metrics, or other sources.
                                  1. Regression Analysis (scatter diagrams)
                                    1. Learning Curve
                                    2. 4. Three-Point estimating

                                      Annotations:

                                      • Statistically, there is a very small probability of completing a project on exactly any one date. As we know, things do not always go according to plan. With the three-point technique, estimators give an optimistic (0),  pessimistic (P), and most likely (M)  estimate for each activity.
                                      1. 5. Group decision-making techniques

                                        Annotations:

                                        • Involving team members in estimating can be beneficial on many levels. Those doing the work are most likely to have a good understanding of the time required to complete the effort.
                                        1. 6. Reserve Analysis

                                          Annotations:

                                          • Means adding extra time to the schedule (called a contingency reserve  or a buffer ) to account for extra risk.
                                          1. 1.- Activity duration estimates
                                            1. 2. Project Document Updates
                                              Show full summary Hide full summary

                                              Similar

                                              Biology- Genes, Chromosomes and DNA
                                              Laura Perry
                                              Enzymes and Respiration
                                              I Turner
                                              PSBD TEST # 3
                                              yog thapa
                                              General questions on photosynthesis
                                              Fatima K
                                              NSI / PSCOD/ ASSD
                                              Yuvraj Sunar
                                              REGLAMENTO DE USO LEGAL, ADECUADO Y PROPORCIONAL DE LA FUERZA PARA LA POLICÍA NACIONAL DEL ECUADOR
                                              edwin patrico
                                              3.1 Keywords - Marketing
                                              EMI D
                                              Estructura de un Sistema Operativo
                                              Oliver Axel Martinez Becerra
                                              Vocabulário Inglês Básico
                                              Aline Nicomédio
                                              Los orígenes del conductismo
                                              michel neri hernandez
                                              TRANSCRIPCIÓN
                                              Carlos Arroyo