SAB4#63_Network Diagram Analysis

Description

Mind Map on SAB4#63_Network Diagram Analysis, created by pmpcertificacion on 21/02/2015.
pmpcertificacion
Mind Map by pmpcertificacion, updated more than 1 year ago
pmpcertificacion
Created by pmpcertificacion about 9 years ago
17
0

Resource summary

SAB4#63_Network Diagram Analysis
  1. Critical path metod

    Annotations:

    • Involves determining the longest path through the network diagram, the earliest and latest activity can star, and the earliest and latest it can be completed.
    1. Critical path

      Annotations:

      • Is the longest duration path through a network diagram an determines the shortest time it could take to complete the project.
      • The aesiest way to find the critical path is to identify all paths through the network and add the activity durations along each path.  The path with the longest duration is the critical path.
      1. Near critical path

        Annotations:

        • This path is close in duration to the critical path.  Something could happen that shortnes the critical path or lengthens the near-critial path to the point where the near-critical path becomes critical.
        • The closer in length the near-critical an critical paths are, the more risk the project has.
      2. Float (slack)
        1. Total float

          Annotations:

          • Is the amount of time an activity can be delayed without delaying the project end date or an intermediary milestone.
          1. Free float

            Annotations:

            • This is the amount of time an activity can be delayed without delating the early start date of its succesor 
            1. Project float

              Annotations:

              • Is the amount of time a project can be delayed without delaying the externally imposed project completion date required by the customer or management.
              1. Start formula

                Annotations:

                • Float=LS-ES
                1. Finish formula

                  Annotations:

                  • LF-EF
              2. Schedule compresion

                Annotations:

                • During project planning, schedule compresion can help a project manager determine if the desired completion date can be met and, if not, what can de changed to meet the requested date.
                1. Fast tracking

                  Annotations:

                  • Involves taking critical path activities that were originally planned in a series and doing them instead in parallel for some or all of their duration.
                  1. Crashing

                    Annotations:

                    • Involves adding or adjunting resources in order to compress the schedule while mantaining the original project scope.
                    • Crashing, by definition, always results in increased costs and may increase risk.
                  2. Modeling

                    Annotations:

                    • In creating a finalized, realistic schedule, it is helpful to ask "what if a particular factor changed on the project?  Would thah produce a shorter schedule?
                    • The assumptions for each activity can change and, therefore, the activity durations can also change.
                    1. Monte Carlo Analysis

                      Annotations:

                      • This technique uses computer software to simulate the outcome of a project, based on the three-point estimates (optimistic, pessimistic, and most likely) for each activity and the network diagram.
                      • The simulation can tell you: 1.- The probability of completing the project on any specific day. 2.- The probabilty of completing the project for any specific cost. 3.- The probability of any activity actually being on the critical path. 4.- The overall project riks.
                    2. Resource optimiaztion

                      Annotations:

                      • Refers to finding ways to adjust the use of resources.
                      1. Resource leveling

                        Annotations:

                        • Is used to produce a resource-limited schedule.
                        1. Resource Smoothing

                          Annotations:

                          • Is a modified form of resource leveling, where resources are leveled only within the limits of the float of ther activities.
                        2. Critical chain method

                          Annotations:

                          • Uses a network diagram and critical path to develop a schedule by assigning each activity to occur as late as posible to still meet the end date.
                          • You add resource dependencies to the schedule and then calculate the critical chain. Starting at the end date, you buid buffers for ersource limitations and risks into the chain at critical milestones (risk response planning).
                          • These reserves, spread throughout the project, provide cushions for delays in the scheduled activities.  You manage these buffers so thah you meet each individual milestone date and thus the project milestone completion date as well.
                          Show full summary Hide full summary

                          Similar

                          English Vocabulary
                          Niat Habtemariam
                          Pigeon English - apostrophe practice
                          Bob Read
                          To Kill A Mockingbird Complete Notes
                          jessica.moscrip
                          One child policy, China- Population Control Case Study
                          a a
                          B5 - Growth and Deveolopment
                          blairzy123
                          Biology
                          Holly Bamford
                          GCSE CHEMISTRY UNIT 2 STRUCTURE AND BONDING
                          mustafizk
                          GCSE AQA Biology 1 Nerves & Hormones
                          Lilac Potato
                          GCSE AQA Biology 3 Kidneys & Homeostasis
                          Lilac Potato
                          CCNA Security 210-260 IINS - Exam 1
                          Mike M
                          2PR101 1.test - 1. část
                          Nikola Truong