SAB9#58_59_Types_Relation_Activities_&_Types_Estimations
  1. PDM (Precedence Diagramming Method)

    Annotations:

    • or Activity-on-Node (AON)
    1. Finish to Start (FS)

      Annotations:

      • The most common
      1. one thing needs to end before the next can begin
      2. Start to Start (SS)
        1. activities begin at the same time
        2. Finish to Finish (FF)
          1. These two finish at the same time
          2. Start to Finish (SF)

            Annotations:

            • This dependency is rarely used
            1. An activity must star before the successor can finish
          3. Types of Dependencies
            1. External dependencies
              1. Sometimes your project will depend on things outside the work you are doing
              2. Discretionary dependencies (Preferred, Preferential, SOFT Logic)

                Annotations:

                • you should set discretionary dependencies based on your knowledge of the best practices for getting the job done
                1. it’s just a matter of preference.
                2. Mandatory dependencies (HARD Logic)
                  1. Mandatory predecessors are the kind that have to exist just because of the nature of the work
                  2. Internal dependencies
                    1. Some dependencies are completely within the team’s control
                  3. One-Point Estimating

                    Annotations:

                    • Is often not the best method to use
                    1. Expert judgment
                      1. Historical information
                      2. Analogous Estimating (Top-down)

                        Annotations:

                        • Advantages---------  -allows for quick calculation -less expensive Disadvantages-------  -This technique can be problematic -It can force people into padding their estimates
                        1. Expert judgment
                          1. Historical information

                            Annotations:

                            • previous projects
                          2. Parametric Estimating

                            Annotations:

                            • -more accurate than analog -The results of parametric estimating can become heuristics 
                            1. Historical information
                              1. Relationships between variables
                                1. Regression analysis (scatter diagram)
                                  1. 2 variables to see if they are related and creates a mathematical formula
                                  2. Learning curve
                                  3. Heuristics
                                    1. a generally accepted rule, or best practice
                                  4. Three-Point Estimating
                                    1. Triangular Distribution (Simple Average)
                                      1. equal weight
                                      2. Beta Distribution (Weighted Average)
                                        1. gives stronger consideration to the most likely
                                          1. Standar Deviation
                                            1. the possible range for estimate
                                        2. Group Decision Making

                                          Annotations:

                                          • team members
                                          1. brainstorming
                                            1. the nominal group technique
                                              1. Delphi technique
                                                1. anonymous
                                                  1. external experts
                                                2. Reserve Analysis
                                                  1. contingency reserves

                                                    Annotations:

                                                    • are included in the project schedule baseline
                                                    1. identified schedule risks
                                                    2. management reserves

                                                      Annotations:

                                                      • additional funds
                                                      1. unforeseen risks
                                                    Show full summary Hide full summary

                                                    Similar

                                                    Social Psychology, Milgram (1963)
                                                    Robyn Chamberlain
                                                    IB Bio - Mitosis Quiz
                                                    j. stu
                                                    Macbeth Notes
                                                    Bella Ffion Martin
                                                    EEO Terms
                                                    Sandra Reed
                                                    ENG LIT TECHNIQUES
                                                    Heloise Tudor
                                                    Edexcel Additional Science Chemistry Topics 1+2
                                                    El Smith
                                                    Physics 2
                                                    Peter Hoskins
                                                    Top learning tips for students
                                                    Micheal Heffernan
                                                    Macbeth Essay Notes
                                                    Mel M
                                                    Using GoConqr to study History
                                                    Sarah Egan
                                                    Salesforce Admin 201 Exam Chunk 6 (156-179)
                                                    Brianne Wright