CDT Exam - Fall 2015

Question 1 of 200

Medal-premium 1

When interpreting contract documents, Architect/Engineer should:

Select one of the following:

  • Show no partiality to Owner or Contractor

  • Protect the client's best interests

  • Protect Architect/Engineer from possible liabilities

  • Achieve the original design intent of Architect/Engineer

Question 2 of 200

Medal-premium 1

Product equivalency, effect on the other aspects of the project, and warranty are the major factors to be considered for:

Select one of the following:

  • Alternates

  • Shop drawing submittals

  • Substitution requests

  • Change order request

Question 3 of 200

Medal-premium 1

Which of the following is not a management expertise that contractors bring to the project
delivery process?

Select one of the following:

  • Knowledge of factors that influence cost, time, and quality

  • Identifying codes and regulations applicable to the design

  • Ability to manage multiple subcontractors and suppliers

  • Experience with managing a construction budget in a risk-based setting

Question 4 of 200

Medal-premium 1

Which of the following is a stage of the Facility Life Cycle?

Select one of the following:

  • Preliminary Project Description

  • Facility maintenance

  • Project permitting

  • Project conception

Question 5 of 200

Medal-premium 1

The written formats can each be employed for a variety of applications; the chief advantage of
using standard formats is:

Select one of the following:

  • a standardized numbering system.

  • a standardized location within the Drawings for subject matter

  • a standardized means of organizing, storing, retrieving, and communicating an enormous
    body of data.

  • a standardized set of contracts between the owner and contractor

Question 6 of 200

Medal-premium 1

The design stage of a project includes all of the following except which one?

Select one of the following:

  • Preliminary project description

  • Engineering design criteria

  • Feasibility studies

  • Outline specifications

Question 7 of 200

Medal-premium 1

Green buildings are designed to reduce the overall impact of the built environment on human
health and the natural environment by:

Select one of the following:

  • Efficiently using manpower resources during construction

  • Protecting occupant health and improving employee productivity

  • Reducing waste, pollution and environmental degradation during construction

  • Increasing volatile organic compounds in construction materials

Question 8 of 200

Medal-premium 1

The NCS is comprised of which of the following standards?

Select one of the following:

  • OmniClassTM

  • CSI CAD Layer Guidelines

  • MasterFormat®

  • CSI Uniform Drawing System

Question 9 of 200

Medal-premium 1

Which of the following is a procurement stage activity?

Select one of the following:

  • Bid securities are provided by the owner

  • The owner enters into negotiation with the contractor

  • Purchase orders are given to the consultants

  • The architect certifies the application for payment

Question 10 of 200

Medal-premium 1

Which of the following entities are responsible for design compliance with the authorities
having jurisdiction?

Select one of the following:

  • Owner

  • Architect

  • Contractor

  • Plan reviewer

Question 11 of 200

Medal-premium 1

Which of the following will the courts use to interpret specifications in the same manner as
they interpret contracts?

Select one of the following:

  • Autonomy to contract

  • General takes precedence over specific

  • Professional negligence

  • Construction for the drafter

Question 12 of 200

Medal-premium 1

It is not uncommon for a public owner to dictate the design and construction process for the
different delivery methods, which of the following are examples of this?

Select one of the following:

  • Which financial institutions will provide bonding for the contractor financing

  • AHJ Submittal requirements

  • How the architect’s construction administration and the contractor’s project management
    will be conducted

  • How safety will be controlled on the project site

Question 13 of 200

Medal-premium 1

All of the following are examples of project soft costs except which one?

Select one of the following:

  • Relocation

  • Commissioning

  • Due diligence studies

  • Topographical surveys

Question 14 of 200

Medal-premium 1

Which of the following is not a construction schedule milestones?

Select one of the following:

  • Submittal approval

  • Project delivery and team selection processes

  • Procurement (bidding/negotiating/purchasing) activities

  • Contract completion

Question 15 of 200

Medal-premium 1

All of the following activities are associated with the project conception stage except which
one?

Select one of the following:

  • Predesign

  • Planning

  • Commissioning

  • Programming

Question 16 of 200

Medal-premium 1

Which of the following is not an example of zoning regulations?

Select one of the following:

  • Construction type

  • Facility function

  • Parking requirement

  • Height limitations

Question 17 of 200

Medal-premium 1

If the construction budget of a 50,000 square foot project is $5,000,000 based on $100 per
square foot, it is an example of which method of preparing the budget?

Select one of the following:

  • Unit price

  • Cost per measured unit

  • Systems

  • Component cost

Question 18 of 200

Medal-premium 1

Typical components of a project financial study do not include:

Select one of the following:

  • Owner’s financial condition

  • Life cycle costs

  • Contractor financial status

  • Available funding

Question 19 of 200

Medal-premium 1

Which of the following is not included in typical site studies?

Select one of the following:

  • Environmental issues

  • Hazardous materials

  • Similar facilities

  • Archeological Surveys

Question 20 of 200

Medal-premium 1

The nationally recognized California AIA "Integrated Project Delivery Guide" redefines the
stages of a project to include which of the following:

Select one of the following:

  • Conceptualization

  • Schematic Design

  • Design Development

  • Agency documents

Question 21 of 200

Medal-premium 1

Limitations of the design-bid-build project delivery method include which of the following:

Select one of the following:

  • Linear sequence shortens the project schedule

  • Bids may exceed budget

  • Partnering is a natural result

  • Low bids may encourage owner changes

Question 22 of 200

Medal-premium 1

Which of the following is a principal type (business arrangements) of the design-build project
delivery method?

Select one of the following:

  • An architect and an engineer may form a joint venture and contract with an owner to
    provide D-B services.

  • An A/E and a contractor may form a joint venture and contract with subcontractors to
    provide D-B services.

  • An owner may contract with the contractor and then subcontract with an A/E for
    architectural and engineering services

  • A construction manager may contract with an A/E for D-B services, and the A/E then
    subcontracts with a contractor for construction services

Question 23 of 200

Medal-premium 1

A result of the design-build project delivery method is which of the following:

Select one of the following:

  • The A/E will provide the same level of professional service as a conventionally delivered
    project.

  • Construction documents will be more detailed than a conventionally delivered project.

  • The material selections will be by the Owner

  • Dispute resolution will require less of the owner’s time

Question 24 of 200

Medal-premium 1

Which of the following is a primary characteristic of Integrated Project Delivery?

Select one of the following:

  • Schematic Design is performed by the General Contractor

  • Recognition that intensified planning results in efficiency and savings during execution

  • Can only be used with the Design Build delivery method

  • Reduces efficiency of Project Commissioning

Question 25 of 200

Medal-premium 1

Outline specifications aid in the design process for all of the following except which one?

Select one of the following:

  • Revising cost estimates and schedules

  • Value engineering studies

  • Checklist for selecting products

  • Serving as the basis for subcontracts in fast track construction

Question 26 of 200

Medal-premium 1

An alternate becomes part of the contract documents:

Select one of the following:

  • When the bids are opened

  • When owner makes a decision to accept

  • On A/E's recommendation

  • When stipulated in the owner/contractor agreement

Question 27 of 200

Medal-premium 1

Prior to BIM the following drawings required specialized skill to produce and were used rarely
in construction drawings:

Select one of the following:

  • Nonscaled views and plans

  • Plans and reflected ceiling plans

  • Perspectives and isometrics

  • Sections and perspectives

Question 28 of 200

Medal-premium 1

Thorough product selection requires which of the following?

Select one of the following:

  • Obtain product information, identify the product’s salient characteristics, establish
    performance criteria

  • Matches existing material, establish performance criteria, product representatives contact
    information

  • Establish performance criteria, product representatives contact information, obtain product
    information

  • Obtain product information, identify the products salient characteristics, contractor
    approval

Question 29 of 200

Medal-premium 1

Products can be categorized into the following types:

Select one of the following:

  • Standard products, custom products, natural products, manufactured products

  • Materials, commodities, products, assemblies, equipment

  • Materials, standard products, custom products, assemblies, equipment

  • Standard products, custom products, commodities, equipment

Question 30 of 200

Medal-premium 1

What functional considerations must the A/E use to design the project elements and their
relationships in a manner that ensures proper function of the project in accordance with the
owner’s program and related AHJ requirements?

Select one of the following:

  • Adjacency of project elements, contextual compatibility of materials, aesthetic effects of
    project elements

  • Contractor’s ability to procure the materials, owners programmatic requirements,

  • Quantities and arrangements of elements, juxtaposition of light and shadow

  • The size of project elements, performance capacity of project elements, arrangement of
    project elements

Question 31 of 200

Medal-premium 1

Life cycle costs require several considerations, including:

Select one of the following:

  • Initial construction cost as well renovation, remodeling, and improvements

  • Initial cost of construction including the cost of materials and permits

  • Alteration, renovation, and demolition

  • Maintenance and code changes cost over the life of the product

Question 32 of 200

Medal-premium 1

There are occasions when it will be necessary for the A/E to consider special procedures for
certain variables in a project, including:

Select one of the following:

  • Indeterminate items, unknowns, and contingencies

  • Postponement of decisions until the design is complete

  • Identification and control of design costs

  • Flexibility and adjustment for AHJs requirements

Question 33 of 200

Medal-premium 1

The special procedures used to ensure cost compliance include which of the following?

Select one of the following:

  • Cash allowances, material allowances, quantity allowances

  • Alternates, unit prices, stipulated sums

  • Alternates, unit prices, allowances

  • Guaranteed maximum price, unit prices, design allowances

Question 34 of 200

Medal-premium 1

What written forms are used to document project decisions during schematic design and design
development?

Select one of the following:

  • MasterFormat®, PageFormat™

  • UniFormat™, PageFormat™

  • Preliminary project description, outline specifications

  • SectionFormat™, PageFormat™

Question 35 of 200

Medal-premium 1

What technology is rapidly shifting the emphasis from 2-dimension CAD drawings to 3-
dimensional thinking?

Select one of the following:

  • NCS (National CAD Standard)

  • BIM (Building Information Modeling)

  • UDS (Uniform Drawing System)

  • LEED (Leadership in Energy and Environmental Design)

Question 36 of 200

Medal-premium 1

BIM (Building Information Modeling) is the basis of how design and construction documents
should be prepared and used when utilizing what project delivery method?

Select one of the following:

  • Design-bid-build

  • Design-negotiate-build

  • Owner-build

  • Integrated Project Delivery

Question 37 of 200

Medal-premium 1

Instructions for procurement:

Select one of the following:

  • Are used only on private projects

  • Frequently are standard industry forms

  • May include the geotechnical report as an attachment

  • Are binding upon the contractor

Question 38 of 200

Medal-premium 1

The document named "Available Information" is part of the:

Select one of the following:

  • Instructions to Bidders

  • Contract Documents

  • Specifications

  • Procurement Requirements

  • All of the above

Question 39 of 200

Medal-premium 1

Contractual clauses in the Conditions of the Contract:

Select one of the following:

  • Have priority over Division 01

  • Are superseded by Division 01

  • Are expanded upon by the provisions of Division 01

  • Are independent and Division 01 provisions have no effect

Question 40 of 200

Medal-premium 1

An affirmation of fact or promise made by the seller to the buyer that relates to the goods
and becomes a part of the basis of the bargain creates _______________________

Select one of the following:

  • An implied warranty

  • A full warranty

  • An express warranty

  • A guarantee

Question 41 of 200

Medal-premium 1

As a result of the widely held misconception that a contractor's responsibility for defective
work lasts only for the one-year guaranty period:

Select one of the following:

  • The supplementary conditions should state that the period last a specific additional length
    of time

  • EJCDC and AIA documents state correction period instead of guaranty period

  • The owner accepts any repairs after that date

  • The courts relieve the contractor of his responsibility

Question 42 of 200

Medal-premium 1

Under the AIA A201 and EJCDC C-700, who provides property insurance covering the
Work?

Select one of the following:

  • Contractor's surety

  • Owner

  • Contractor

  • Financing agency

  • None of the above

Question 43 of 200

Medal-premium 1

Marked-up or corrected contract drawings that indicate changes incorporated in the Work are
known as:

Select one of the following:

  • Contract forms

  • Closeout submittals

  • Record drawings

  • As-builts

Question 44 of 200

Medal-premium 1

Which bond protects the owner from losing the benefit of an accepted bid?

Select one of the following:

  • Maintenance bond

  • Payment bond

  • Bid bond

  • Performance bond

Question 45 of 200

Medal-premium 1

Which of the following are best designated on the drawings?
1. Specific requirements
2. Location
3. Quality of materials
4. Dimension and size
5. Shape and form

Select one of the following:

  • 1, 2, 3, 4, and 5

  • 2, 4, and 5

  • 2, 3, 4, and 5

  • 1 and 3

  • 3, 4, and 5

Question 46 of 200

Medal-premium 1

All of the following could be Articles in PART 1 - GENERAL of a specification except which
one?

Select one of the following:

  • References

  • Action Submittals

  • Source Quality Control

  • Measurement and Payment

Question 47 of 200

Medal-premium 1

Submittal requirements for Facility Services Divisions 21 through 28 are specified in:

Select one of the following:

  • The first section in each respective division

  • Supplementary Conditions

  • Division 01 Section Submittal Procedures

  • Section 01 12 00 Summary of Multiple Contracts

Question 48 of 200

Medal-premium 1

When outside consultants are responsible for the production of major portions of the project
specifications:

Select one of the following:

  • One design team member should be responsible for overall specification coordination

  • Different document formats should be used to identify the work of the separate consultants

  • The lead design professional should avoid the liability inherent in reviewing consultants'
    work

  • Information should be collected and the project A/E assume responsibility for preparing
    each section

Question 49 of 200

Medal-premium 1

In the specifications, the stated requirements address:

Select one of the following:

  • The owner's responsibilities

  • The contractor's responsibilities

  • The subcontractor's responsibilities

  • The architect's responsibilities

Question 50 of 200

Medal-premium 1

Which of the following should be avoided in a specification?

Select one of the following:

  • Articles (the, an, a)

  • Symbols (#, $, &, ")

  • Abbreviations (conc., ptwd, aess)

  • All of the above

Question 51 of 200

Medal-premium 1

To be effective in communicating, specifications should be:

Select one of the following:

  • Complete, concise, and clear

  • Concise, clear, and correct

  • Clear, concise, correct, and complete

  • Concise, correct, coordinated, and complete

Question 52 of 200

Medal-premium 1

The dollar amounts of cash allowances are:

Select one of the following:

  • In the instructions to bidders

  • In the supplementary conditions

  • In Division 01

  • In the specification sections of Division 02 through 49 that specify the product installation

Question 53 of 200

Medal-premium 1

The two sentence structure moods that are recommended for specifications are:

Select one of the following:

  • The imperative mood

  • The indicative mood

  • The symbolic mood

  • The conflicting mood

Question 54 of 200

Medal-premium 1

All of the following are Articles in PART 3 - EXECUTION except which one?

Select one of the following:

  • Examination

  • Application

  • Fabrication

  • System startup

Question 55 of 200

Medal-premium 1

These graphic documents show the quantitative extent and relationship of elements to one
another?

Select one of the following:

  • Drawings

  • Specifications

  • Elevations

  • Details

Question 56 of 200

Medal-premium 1

Drawings produced during this design stage include, sketches, renderings, and conceptual
diagrams?

Select one of the following:

  • Design Development

  • Construction Document

  • Schematic Design

  • Conceptual Design

Question 57 of 200

Medal-premium 1

Substitution requirements and procedures during bidding _____________________.

Select one of the following:

  • Are not allowed under most public bidding statutes

  • Are modified by the supplementary conditions

  • Are governed by the instructions to bidders

  • Provide for requests by telephone

Question 58 of 200

Medal-premium 1

The following are all advantages gained by using standard agreement forms except which one?

Select one of the following:

  • Parties' familiarity with the forms

  • Uniformity of terminology

  • Legal precedents interpreting the documents

  • Accommodate choice from a wide variety of standard contract conditions

Question 59 of 200

Medal-premium 1

Which of the following is the recommended sequence for an addendum?

Select one of the following:

  • Changes to procurement requirements, changes to previous addenda, changes to conditions
    of the contract, changes to the agreement

  • Changes to previous addenda, changes to procurement requirements, changes to
    agreements and other contract forms, changes to specifications and drawings

  • Changes to specifications, changes to drawings, changes to previous addenda

  • Contract documents, changes to specifications

Question 60 of 200

Medal-premium 1

The negotiating process is between the?

Select one of the following:

  • Owner and Contractor

  • Request for Proposal (RFP)

  • Drawings and Specifications

  • Offer Forms and Supplements

Question 61 of 200

Medal-premium 1

Which of the following is not a document for Negotiating?

Select one of the following:

  • Invitation to bid

  • Request for Proposal (RFP)

  • Drawings and Specifications

  • Offer Forms and Supplements

Question 62 of 200

Medal-premium 1

The negotiating process includes which of the steps below:
A. Offer
B. Exchange
C. Compromise
D Restitution

Select one of the following:

  • A only

  • A and C

  • B and C

  • A and D

Question 63 of 200

Medal-premium 1

Value analysis, is also called:
A. Value Enhanced Design
B. Project Valuing
C. Enhanced Engineering
D. Value Engineering

Select one of the following:

  • A and C

  • C Only

  • A and D

  • C and D

Question 64 of 200

Medal-premium 1

The direct acquisition of materials and equipment by an Owner is:

Select one of the following:

  • Procurement

  • Bidding

  • Purchasing

  • Solicitation

Question 65 of 200

Medal-premium 1

The Design Negotiate Build Process is more conducive to:

Select one of the following:

  • Value analysis and repricing

  • Complex negotiations

  • Protracted counteroffers

  • Multiple prime contracts

Question 66 of 200

Medal-premium 1

Owner purchased items that are then added to the job by the contractor are referred to as

Select one of the following:

  • Owner Purchased and Contractor Installed

  • Owner Furnished and Contractor Installed

  • Owner Purchased and Contractor Provided

  • Owner Furnished and Contractor Provided

Question 67 of 200

Medal-premium 1

Subcontractors are not:

Select one of the following:

  • The principal providers of labor

  • Original Source of most materials

  • Providers of services

  • Providers of technical Information

Question 68 of 200

Medal-premium 1

Bid shopping is the practice of:

Select one of the following:

  • Negotiating with two of more subcontractors for the lowest price

  • Revealing the subbid of one subcontractor to another to obtain a lower price

  • Encouraging cost-cutting between subcontractors in Value Analysis

  • Achieving the lowest subbid for the Owners Benefit

Question 69 of 200

Medal-premium 1

The date of substantial completion is established by the:

Select one of the following:

  • Owner

  • A/E

  • Contractor

  • Authorities having jurisdiction

Question 70 of 200

Medal-premium 1

Preconstruction activities begin when the contractor has received:

Select one of the following:

  • a letter of intent to award

  • the contracting forms

  • the project specifications

  • a signed copy of the addenda

Question 71 of 200

Medal-premium 1

Which of the following is not a Mobilization and start up cost?

Select one of the following:

  • Transportation

  • Installation of temporary facilities

  • Protection between stages of work

  • Royalties, licenses, and fees

Question 72 of 200

Medal-premium 1

It is important to establish the site conditions prior to:

Select one of the following:

  • Notice to Proceed

  • Mobilization

  • Negotiating Procurement

  • Signing the contract

Question 73 of 200

Medal-premium 1

Mobilization typically occurs after:

Select one of the following:

  • Receipt of a notice to proceed and following a preconstruction meeting

  • After a site mobilization meeting and before receipt of a notice to proceed

  • Receipt of a notice to proceed and before establishing Environmental Protection
    Requirements

  • After site safety meeting and before receipt of a notice to proceed

Question 74 of 200

Medal-premium 1

Which two types of bonds might be required during construction?

Select one of the following:

  • Construction bond

  • Bid bond

  • Performance bond

  • Adhesive bond

Question 75 of 200

Medal-premium 1

Which party will typically provide builder’s risk insurance?

Select one of the following:

  • Owner

  • Architect

  • Contractor

  • Each subcontractor

Question 76 of 200

Medal-premium 1

The contractor should begin preparation and delivery of the preconstruction submittals after
which event?

Select one of the following:

  • Bid opening

  • Notice to proceed

  • Execution of agreement

  • Preconstruction meeting

Question 77 of 200

Medal-premium 1

Payment and performance bonds are which type of document?

Select one of the following:

  • Information available to bidders

  • Construction document

  • Preconstruction submittal

  • Closeout submittal

Question 78 of 200

Medal-premium 1

Types of control plans that the contractor may be requested to submit during preconstruction
include which three of the following?
A. Erosion control plan
B. Pollution control plan
C. Site control plan
D. Traffic control plan

Select one of the following:

  • A, B, D

  • A, C, D

  • B, C, D

  • none of the above

Question 79 of 200

Medal-premium 1

Which two parties are responsible for submittal of a set of construction documents to the AHJ
for permit review?

Select one of the following:

  • Owner & Architect

  • Architect & Owner

  • Contractor & Subcontractor

  • Subcontractor & Engineer

Question 80 of 200

Medal-premium 1

What is typically the contractor’s first activity on the project site?

Select one of the following:

  • Survey and lay out the new construction

  • Meet with AHJ

  • Install temporary power

  • Mobilization

Question 81 of 200

Medal-premium 1

The following are all advantages gained by using standard agreement forms except which one?

Select one of the following:

  • Parties' familiarity with the forms

  • Uniformity of terminology

  • Legal precedents interpreting the documents

  • Accommodate choice from a wide variety of standard contract conditions

  • Recognized customs resulting from longtime use

Question 82 of 200

Medal-premium 1

The responsibility of inspecting work already performed for proper condition to receive
subsequent work lies with the:

Select one of the following:

  • Owner

  • A/E

  • Contractor

  • Subcontractor

Question 83 of 200

Medal-premium 1

The Contractor’s superintendent:

Select one of the following:

  • Cannot be changed without Owner’s consent

  • Communication is as binding as if given by the Contractor

  • All of the above

  • None of the above

Question 84 of 200

Medal-premium 1

True or False: By executing the contract, the Contractor confirms that the contract time is
reasonable.

Select one of the following:

  • True
  • False

Question 85 of 200

Medal-premium 1

The date of substantial completion is established by the:

Select one of the following:

  • Owner

  • A/E

  • Contractor

  • Authorities having jurisdiction

Question 86 of 200

Medal-premium 1

Under AIA A201, who has the responsibility to pay sales, consumer, use and similar taxes for
the work provided?

Select one of the following:

  • A/E

  • Owner

  • Contractor

  • Installing subcontractor

  • None of the above

Question 87 of 200

Medal-premium 1

If the contractor is delayed in the progress of the work by the Owner, the Contractor should:

Select one of the following:

  • Write the A/E protesting the changes

  • Notify the bonding company

  • Write the A/E requesting a change order granting an extension of time

  • Stop the work until Owner makes a decision

Question 88 of 200

Medal-premium 1

Product equivalency, effect on the other aspects of the project, and warranty are the major
factors to be considered for:

Select one of the following:

  • Alternates

  • Shop drawing submittals

  • Substitution requests

  • Change order request

Question 89 of 200

Medal-premium 1

All of the following may be accomplished through issuing of a change order except which one?

Select one of the following:

  • Change in bid date

  • Decrease in contract sum

  • Extension of contract time

  • Reduction in scope of work

Question 90 of 200

Medal-premium 1

All of the following are defined as a contract modification except which one?

Select one of the following:

  • Change order

  • Construction change directive/ work change directive

  • Architect's supplemental instruction/field order

  • Addendum

Question 91 of 200

Medal-premium 1

Under AIA A201, who has the authority to stop the work, if nonconforming work fails to be
corrected?

Select one of the following:

  • A/E

  • Owner

  • Contractor

  • Varies - As stated in Division 01 General Requirements

  • None of the above

Question 92 of 200

Medal-premium 1

Drawings prepared by the contractor, subcontractor, or material supplier that show how a
particular aspect of the work is to be fabricated and installed, are called:

Select one of the following:

  • Record drawings

  • Construction documents

  • Shop drawings

  • Details

Question 93 of 200

Medal-premium 1

The contract clauses that establish payment responsibilities are found in:

Select one of the following:

  • General conditions

  • Division 01 General Requirements

  • Payment bond

  • Addenda

Question 94 of 200

Medal-premium 1

True or False: The A/E may withhold certification for payment in whole or in part if in the
A/E’s opinion representations to Owner cannot be made concerning the progress of the work.

Select one of the following:

  • True
  • False

Question 95 of 200

Medal-premium 1

When interpreting contract documents, the A/E should:

Select one of the following:

  • Show no partiality to Owner or Contractor

  • Protect the client's best interests

  • Protect the A/E from possible liabilities

  • Achieve the original design intent of the A/E

Question 96 of 200

Medal-premium 1

True or False: Acceptance of final payment constitutes a waiver of claims by the contractor,
subcontractor, and material supplier.

Select one of the following:

  • True
  • False

Question 97 of 200

Medal-premium 1

True or False: If a portion of the work is covered contrary to requirements specifically
expressed in the Contract Documents, it must if requested by the A/E, be uncovered for
examination and at the Contractors expense without change in the contract time.

Select one of the following:

  • True
  • False

Question 98 of 200

Medal-premium 1

True or False: The facility manager should not be involved in project closeout because the
facility manager is not a party to the construction contract.

Select one of the following:

  • True
  • False

Question 99 of 200

Medal-premium 1

It is important for the long-term success of the facility’s operations and maintenance that
project closeout activities include all of the following except which one?

Select one of the following:

  • Start-up and load testing

  • Receipt of final punch list

  • Demonstration for new operators

  • Operational training if necessary

  • Commissioning

Question 100 of 200

Medal-premium 1

Equipment and system review and training should occur:

Select one of the following:

  • Immediately after substantial completion.

  • Prior to substantial completion

  • After system commissioning

  • During the submittal review period

Question 101 of 200

Medal-premium 1

A punch list is generated by which of the following?

Select one of the following:

  • A/E just prior to substantial completion.

  • The subcontractors after substantial completion.

  • The owner prior to substantial completion

  • The contractor prior to substantial completion

Question 102 of 200

Medal-premium 1

Special warranties/guarantees can:

Select one of the following:

  • Be provided by manufacturer, contractor, or installer

  • Be longer or shorter than the correction period

  • Exclude abuse, misuse, and failure to maintain

  • All of the above

Question 103 of 200

Medal-premium 1

Facility managers should perform a post occupancy evaluation how long after initial
occupancy?

Select one of the following:

  • Three months

  • Three to six months

  • Six to nine months

  • Just before the one-year correction period completion

Question 104 of 200

Medal-premium 1

Objectives of a good maintenance program include all of the following except which one?

Select one of the following:

  • Minimize interruptions that affect the facility’s function and use

  • Minimize failures of equipment and facility structures that affect productivity

  • Select the best repair and replacement methods and materials

  • Implement effective energy conservation practices

Question 105 of 200

Medal-premium 1

Project Record Document consist of the following except?

Select one of the following:

  • Drawings

  • Project manual

  • Submittals

  • Spare parts and extra stock materials

Question 106 of 200

Medal-premium 1

Resource materials should be:

Select one of the following:

  • Should be permanently retained and accessible

  • Should be filed for safe keeping until the end of the correction period

  • Should be given to the contractor with the release of retainage

Question 107 of 200

Medal-premium 1

Which of these documents, might we find in the
Project Manual but they are not contract documents?

Select one of the following:

  • The Agreement

  • Procurement Documents

  • Addendum

  • Supplemental Conditions

Question 108 of 200

Medal-premium 1

Before a model building code can become the
building code for a jurisdiction, it has to be adopted
by?

Select one of the following:

  • Authority Having Jurisdiction

  • State Government

  • Building Inspector

  • International Organization for
    Standardization

Question 109 of 200

Medal-premium 1

The Construction Manager is hired by this entity?

Select one of the following:

  • The General contractor

  • Owner

  • A/E

  • Contract Administrator

Question 110 of 200

Medal-premium 1

The parties to the Construction Agreement are?

Select one of the following:

  • General Contractor, Sub Contractor, and
    Construction Manager

  • A/E, General Contractor, and Contract
    Administrator

  • Building Official, and General contractor

  • Owner, Contractor, and A/E

Question 111 of 200

Medal-premium 1

The organization responsible for the General
Conditions known as 201 are?

Select one of the following:

  • DBIA

  • AGC

  • AIA

  • CSI

Question 112 of 200

Medal-premium 1

When there is a dispute between the specifications
and the drawings, what is the proper way to settle
the dispute?

Select one of the following:

  • The drawings have priority

  • The A/E should interpret

  • The specifications

  • Arbitration

Question 113 of 200

Medal-premium 1

A subcontractor is obligated to the prime contractor
in the same manner as the prime contractor is
obligated to the:

Select one of the following:

  • Architect

  • Owner

  • Material Supplier

  • Principal in Charge

Question 114 of 200

Medal-premium 1

The requirements of the general conditions can be
modified or expanded to accommodate specific project
conditions, owner’s requirements, or unusual aspects
relating to the roles, rights, duties, and responsibilities of
the parties to the contract for construction, in this
document:

Select one of the following:

  • Contract Modifications

  • Supplemental Conditions

  • Addendum

  • Consensus Documents

Question 115 of 200

Medal-premium 1

Which of the following are not legal binding
construction documents?

Select one of the following:

  • General Conditions

  • Specifications

  • Preliminary Project Description

  • Addendum

Question 116 of 200

Medal-premium 1

This document states that the contractor shall review,
approve, and submit to the architect, shop drawings,
product data, samples, and similar submittals required by
the contract documents. It also states that the architect
will review and approve or take other appropriate action
upon the contractor’s submittals:

Select one of the following:

  • Construction Agreement

  • Field Order

  • General Requirements

  • AIA 201

Question 117 of 200

Medal-premium 1

Division 01 sections apply broadly to the execution of
the work of all the other sections of the
specifications. In addition, they expand on certain
administrative and procedural provisions of the:

Select one of the following:

  • Drawings

  • Construction Agreement

  • Conditions of the Contract

  • Procurement Documents

Question 118 of 200

Medal-premium 1

Defined as the written and graphic documents
prepared for communicating the project design for
construction and administering the construction
contract:

Select one of the following:

  • Construction Documents

  • Plans

  • Procurement Documents

  • Conditions of the Contract

Question 119 of 200

Medal-premium 1

Typically, procurement requirements should not
include which of the following documents?

Select one of the following:

  • Instructions for procurement

  • Available information, including resource
    drawings

  • Procurement forms and supplements

  • Performance bonds

Question 120 of 200

Medal-premium 1

The invitation to bid is designed to attract qualified
bidders.

Select one of the following:

  • True
  • False

Question 121 of 200

Medal-premium 1

The volume containing the specifications, conditions
of the contract, information to bidders, instructions to
bidders, and the bid form is called:

Select one of the following:

  • Spec book

  • Preliminary Project Descriptions

  • Project manual

  • Submittals

  • None of the above.

  • All of the above.

Question 122 of 200

Medal-premium 1

The documents developed to attract and assist
qualified bidders in properly submitting bids are
called?

Select one of the following:

  • Contract Documents

  • Procurement Requirements

  • Conditions of the Contract

  • Bidders Agreement

Question 123 of 200

Medal-premium 1

Signed by each party the Agreement can be best
explained as:

Select one of the following:

  • Defines the relationship of the owner, A/E, and
    contractor

  • Is the one instrument of the contract
    documents that binds the signing parties to the
    work

  • Constitutes the legal portion of the
    specifications

  • Binds the Architect to the General Contractor

Question 124 of 200

Medal-premium 1

An alternate:

Select one of the following:

  • Is the same as an option in the
    specifications.

  • Is used for the same purpose as unit prices.

  • Should be described in Division 01 and
    specified in the appropriate specification
    sections.

  • Should be described in detail on the bid
    form.

Question 125 of 200

Medal-premium 1

Contract Documents consist of:

Select one of the following:

  • Agreement between owner and contractor, conditions of
    the contract, drawings, and specifications, addenda and
    modifications, other documents listed in the agreement.

  • Agreement between owner and contractor, conditions of
    the contract, drawings and specifications, project manual,
    shop drawings.

  • Agreement between owner and contractor, conditions of
    the contract, drawings and specifications, instructions to
    bidders, bid form, addenda, modifications, other documents
    listed in the agreement.

Question 126 of 200

Medal-premium 1

Contract documents include:

Select one of the following:

  • Written portions of the contract only.

  • Graphic portions of the contract only.

  • Both written and graphic portions of the
    contract.

  • Invitation to bid.

Question 127 of 200

Medal-premium 1

Addenda are used to:

Select one of the following:

  • Modify the procurement documents before
    award of the contract.

  • Modify the contract documents after award
    of the contract.

  • Modify drawings and specifications only.

  • Formalize verbal instructions given during
    bidding.

Question 128 of 200

Medal-premium 1

The agreement is part of the:

Select one of the following:

  • Bidding requirements

  • General conditions

  • Specifications

  • Contract forms

Question 129 of 200

Medal-premium 1

Division 01 should be used to:

Select one of the following:

  • Provide a location for general and
    supplementary conditions

  • Provide a means to modify standard sections
    of the specifications

  • Provide a logical arrangement for specifying
    administrative, procedural, and temporary
    facilities

  • Provide a location for specifying special
    construction and materials the bidders might
    overlook

Question 130 of 200

Medal-premium 1

Division 01 sections relate to:

Select one of the following:

  • Procurement requirements, the agreement, general
    and supplementary conditions, and specifications

  • Procurement requirements, the agreement, general
    and supplementary conditions, the specifications, and
    the drawings

  • The agreement, general and supplementary
    conditions, and specification only

  • The agreement, general conditions, specifications,
    and drawings

Question 131 of 200

Medal-premium 1

Division 01 sections should coordinate with the
procurement requirements, the agreement, general
and supplementary conditions, specifications, and
drawings.

Select one of the following:

  • True
  • False

Question 132 of 200

Medal-premium 1

Administrative and procedural requirements are
specified in:

Select one of the following:

  • General Conditions

  • Supplementary Conditions

  • Division 01 General Requirements

  • Bidding requirements

  • Instructions to Bidders

Question 133 of 200

Medal-premium 1

The agreement form, before modification, should be
reviewed carefully by the:

Select one of the following:

  • Owner's legal counsel

  • Owner

  • Architect and Owner

  • Contractor

Question 134 of 200

Medal-premium 1

If a contractor recognizes or has knowledge of
errors, inconsistencies, or omissions in the contract
documents, the contractor is responsible for
reporting those errors, omissions, or inconsistencies
to:

Select one of the following:

  • The Owner

  • The Authority Having Jurisdiction (AHJ)

  • The A/E

  • His/her Surety Company

Question 135 of 200

Medal-premium 1

Shop drawings, product data, and samples are:

Select one of the following:

  • Considered part of the contract documents

  • Not contract documents

  • Prepared by the Architect

  • Prepared during construction document
    stage

Question 136 of 200

Medal-premium 1

During the construction stage of a project, several
types of supplemental drawings are prepared, such
as shop drawings. Shop drawings may be prepared
by:

Select one of the following:

  • The contractor

  • The subcontractor

  • The material/equipment supplier

  • All of the above

Question 137 of 200

Medal-premium 1

Preconstruction activities begin when the contractor
has received:

Select one of the following:

  • All his subcontracts

  • An executed agreement

  • A copy of the contract documents

  • A purchase order

Question 138 of 200

Medal-premium 1

Which of the following is not normally found in an
agreement:

Select one of the following:

  • Contract time

  • Contract sum

  • Reference to contract documents

  • Construction Submittal requirements

Question 139 of 200

Medal-premium 1

Procurement Documents include:

Select one of the following:

  • Procurement requirements, which include
    solicitation, instructions for procurement, available
    information, procurement forms and supplements

  • Contracting requirements, which include the
    agreement, performance bond, payment bond, and
    certificates

  • Conditions of the contract, which include the
    general and supplementary conditions

  • Specifications

  • All of the above

Question 140 of 200

Medal-premium 1

In a design-bid-build project delivery method, the
general construction contract is between:

Select one of the following:

  • The Subcontractors and Contractor

  • The Contractor and the Owner

  • The Architect and the Contractor

  • The Subcontractors and the suppliers

  • The Owner and the Architect

Question 141 of 200

Medal-premium 1

What is the relationship between the A/E and contractor
in the design-bid-build project delivery method?

Select one of the following:

  • There is no contractual relationship between
    the A/E and contractor

  • The contractor has separate agreements with
    the A/E for design services

  • The A/E has an agreement with the contractor
    for construction services

  • The A/E and contractor are contracted to hire
    the Construction Manager

Question 142 of 200

Medal-premium 1

Which of the following summarizes the design-build
project delivery method?

Select one of the following:

  • The CM, who is the owner’s agent as a contractor
    guarantees the cost of the project to the owner

  • The owner controls the project from beginning to end

  • The owner develops a program and has one contract
    with a single entity to design and construct the project

  • The owner and the contractor negotiate a construction
    contract

Question 143 of 200

Medal-premium 1

Which project delivery method defines the
construction manager as an independent advisor to
the owner?

Select one of the following:

  • Design-Build

  • Design-Negotiate-Build

  • Design-Bid-Build

  • Construction Management

Question 144 of 200

Medal-premium 1

During the construction stage, the Contractor shall
maintain record documents:

Select one of the following:

  • In the Architect's office

  • In the field office

  • In the Owner's office

  • With each of the subcontractors

Question 145 of 200

Medal-premium 1

Inspections required by authorities having jurisdiction
shall be obtained by the:

Select one of the following:

  • Owner

  • Contractor

  • Authority requiring the test

  • Subcontractor, when it is the Subcontractor’s
    work being tested

Question 146 of 200

Medal-premium 1

Who is required to have a program for project site
safety?

Select one of the following:

  • Owner

  • A/E

  • Contractor

  • Each Subcontractor

Question 147 of 200

Medal-premium 1

Who is required to protect stored materials?

Select one of the following:

  • A/E

  • Suppliers

  • Contractor

  • Owner

Question 148 of 200

Medal-premium 1

The A/E will:

Select one of the following:

  • Report defects and deficiencies observed in the Work
    to the owner.

  • Be responsible for safety precautions and programs in
    connection with the Work.

  • Be responsible for the Contractor's failure to carry out
    the Work in accordance with the Contract Documents.

  • Maintain record documents during the construction
    stage.

Question 149 of 200

Medal-premium 1

The Contractor shall not contract or be required to
contract with any Subcontractor against whom reasonable
objection has been made by:

Select one of the following:

  • Owner

  • A/E

  • Contractor

  • All of the above

Question 150 of 200

Medal-premium 1

The A/E’s approval of Shop Drawings is:

Select one of the following:

  • For conformance with the design concept and
    design intent indicated in the Contract Documents.

  • To make certain the products actually supplied by
    the Contractor fit in the construction.

  • To determine accuracy and completeness of
    dimensions and quantities.

  • To ensure that contract document requirements
    have been met.

Question 151 of 200

Medal-premium 1

The owner must sign:

Select one of the following:

  • Supplemental instructions.

  • Change orders.

  • Addenda.

  • Proposal requests.

Question 152 of 200

Medal-premium 1

Who can accept non-conforming work?

Select one of the following:

  • A/E

  • AHJ

  • Owner

  • Construction Manager

Question 153 of 200

Medal-premium 1

Who is responsible for evaluating claims?

Select one of the following:

  • Owner.

  • A/E’s error and omissions insurer

  • A/E

  • Arbitrator

Question 154 of 200

Medal-premium 1

What contract document modification allows the
owner to order a change in the work without an
agreement or adjustment to the contract?

Select one of the following:

  • Construction change directive

  • Change order

  • Purchase order

  • Addendum

Question 155 of 200

Medal-premium 1

Under SectionFormat™, the Parts are entitled:

Select one of the following:

  • General, Materials, Installation

  • Scope, Products, Execution

  • General, Products, Execution

  • Scope, Materials, and Installation

  • General, Materials, and Workmanship

Question 156 of 200

Medal-premium 1

In specification writing, the two basic grammatical
sentence moods which can be used to clearly
convey specification requirements are:

Select one of the following:

  • Imperative and Indicative

  • Suggestive and Imperative

  • Prescriptive and Descriptive

  • Performance and Indicative

Question 157 of 200

Medal-premium 1

Quality control activities occur:

Select one of the following:

  • Before or while accomplishing the work or
    service.

  • During the work or service

  • After the quality assurance activities

  • During the fabrication

  • Before fabrication

Question 158 of 200

Medal-premium 1

Quality assurance activities occur:

Select one of the following:

  • Before the work or service is done.

  • Before or while accomplishing the work or
    service.

  • During construction.

  • During design

Question 159 of 200

Medal-premium 1

Marked up or corrected contract drawings that
indicate changes incorporated into the work during
construction are called:

Select one of the following:

  • As built drawings

  • Record drawings

  • Shop drawings

  • Contractor certified drawings

  • Addendum drawings

Question 160 of 200

Medal-premium 1

A particular material may be indicated several times
on the drawings but is specified in how many
locations:

Select one of the following:

  • One

  • Two

  • According to the number of trades
    involved

  • As determined by Division 01

Question 161 of 200

Medal-premium 1

Resource drawings serve what purpose:

Select one of the following:

  • Show existing work that is to be modified

  • Show construction related to the work, but
    which is not indicated in the contract

  • Provide the Owner with a set of
    documents that will facilitate operation

Question 162 of 200

Medal-premium 1

An Allowance is included in the base bid for:

Select one of the following:

  • Cost of an item to be selected

  • Time to extend the work

  • Includes both time and costs of an item

Question 163 of 200

Medal-premium 1

A Unit Price is:

Select one of the following:

  • A cost determined by the A/E

  • Amount determined by number of units
    multiplied by a unit cost in the Agreement

  • A cost listed on the Bid Form

Question 164 of 200

Medal-premium 1

A defined portion of the work that is priced
separately is:

Select one of the following:

  • A Unit Cost

  • Lump Sum

  • Alternate

Question 165 of 200

Medal-premium 1

Section drawings are cut vertically through and
perpendicular to project materials to:

Select one of the following:

  • Show watertight construction

  • Show detailed arrangement

  • Show which surfaces are to be finished

Question 166 of 200

Medal-premium 1

Substitutions should not be considered when:

Select one of the following:

  • Requested by RFI

  • Request is indicated on submittals

  • Request does not include an itemized
    comparison

  • All of the above

  • None of the above

Question 167 of 200

Medal-premium 1

If the contractor installs an item of work in
accordance with the contract documents, knowing it
is in violation of the governing building codes without
first informing the A/E, who is responsible for the
cost of the correction?

Select one of the following:

  • The A/E

  • The Owner

  • Contractor

Question 168 of 200

Medal-premium 1

The specified correction period (typically one year)
and specified extended warranties begin:

Select one of the following:

  • Upon final payment

  • On the date of substantial completion

  • One year from occupancy of the project

Question 169 of 200

Medal-premium 1

Fast-tracking is:

Select one of the following:

  • A scheduling technique

  • A scheduling and design concept

  • A project delivery method

Question 170 of 200

Medal-premium 1

Is the definition of stipulated/lump sum basis of
payment when the owner makes payment to the
contractor for:

Select one of the following:

  • The quantity of work completed based on
    a stipulated rate.

  • The work in place as a percentage of the
    total.

  • The percentage of the total contract time.

Question 171 of 200

Medal-premium 1

Which of the following is the most traditional project
delivery method?

Select one of the following:

  • Construction Management - Contractor

  • Design-Negotiate-Build

  • Owner-Build

  • Design-Build

  • Design-Bid-Build

  • Construction Management - Advisor

Question 172 of 200

Medal-premium 1

Under the Design-Build project delivery method,
there are several benefits to the Owner that include
all of the following except one:

Select one of the following:

  • The A/E represents the owner’s interests

  • The A/E and Contractor comprise the Design-
    Build entity

  • The Design Builder has specialized knowledge
    of design and constructability

  • Single entity is responsible

Question 173 of 200

Medal-premium 1

Which of the following is not an example of a contingency
cost?

Select one of the following:

  • Construction delays

  • Contractor’s overhead

  • Weather, labor and material shortages

  • Regulatory restrictions

Question 174 of 200

Medal-premium 1

The three factors that affect the quality of a project are Cost, Extent, and Time.

Select one of the following:

  • True
  • False

Question 175 of 200

Medal-premium 1

A key factor affecting project delivery is:

Select one of the following:

  • Complexity

  • Time

  • Cost

  • Quality

Question 176 of 200

Medal-premium 1

The four considerations during facility programming
that should be identified in which of the following:

Select one of the following:

  • Time, goals, cost, and function

  • Function, time, economy, and planning

  • Pre-design, goals, form, and cost

  • Function, form, economy, and time

Question 177 of 200

Medal-premium 1

Which of the following is not a method of specifying?

Select one of the following:

  • Procedural.

  • Proprietary.

  • Descriptive.

  • Reference standard.

  • Performance.

Question 178 of 200

Medal-premium 1

Minor changes involve adjustments to:

Select one of the following:

  • The contract sum or time

  • No adjustment to the contract

  • Adjustment to the contract time only

Question 179 of 200

Medal-premium 1

Which of the following is not an estimating technique
during the design stage?

Select one of the following:

  • Unit price

  • Unit of measure

  • Order of magnitude

  • Proprietary

  • Assemblies/systems

Question 180 of 200

Medal-premium 1

Total project commissioning only includes
mechanical and electrical system components

Select one of the following:

  • True
  • False

Question 181 of 200

Medal-premium 1

Product equivalency, effect on the other aspects of the project, and warranty are the major factors to be considered for:

Select one of the following:

  • Alternates

  • Shop drawing submittals

  • Substitution requests

  • Change order request

Question 182 of 200

Medal-premium 1

A requirement set by authority, custom, or general consensus which is established as an accepted criterion is called a:

Select one of the following:

  • Building code

  • Industry standard

  • Quality control requirement

  • Specification master

Question 183 of 200

Medal-premium 1

Lump Sum, Unit Price, or Cost-Plus-Fee constitute the basis of:

Select one of the following:

  • Payment

  • Selection

  • Award

  • Contract

Question 184 of 200

Medal-premium 1

All of the following are Articles in Part 3 Execution EXCEPT:

Select one of the following:

  • Examination

  • Application

  • Fabrication

  • System Startup

Question 185 of 200

Medal-premium 1

Drawings prepared by the contractor, subcontractor, or material/equipment supplier that show how a particular aspect of the work is to be fabricated and installed, are called:

Select one of the following:

  • Record drawings

  • Construction Documents

  • Shop Drawings

  • Details

Question 186 of 200

Medal-premium 1

The correct title for Division 10 is:

Select one of the following:

  • Accessories

  • Specialties

  • Equipment

  • Special Construction

Question 187 of 200

Medal-premium 1

The following are the types of clauses that might be included in Supplementary Conditions EXCEPT:

Select one of the following:

  • Project insurance requirements

  • Liquidated damage amounts

  • Tax exempt status of owner

  • Submittal requirements

Question 188 of 200

Medal-premium 1

Under the AIA A201 and the EJCDC C-700, who has the authority to stop the Work, if nonconforming Work fails to be corrected?

Select one of the following:

  • A/E

  • Owner

  • Contractor

  • Varies - As stated in Division 01 General Requirements

  • None of the above

Question 189 of 200

Medal-premium 1

The document named "Available Information" is part of the:

Select one of the following:

  • Instructions to Bidders

  • Contract Documents

  • Specifications

  • Procurement Requirements

  • All of the above

Question 190 of 200

Medal-premium 1

The following are all advantages gained by using standard agreement forms EXCEPT:

Select one of the following:

  • Parties' familiarity with the forms

  • Uniformity of terminology

  • Legal precedents interpreting the documents

  • Accomodate choice from a wide variety of standard contract conditions

  • Recognized customs resulting from longtime use

Question 191 of 200

Medal-premium 1

What information is found within Division 13 in the MasterFormat System?

Select one of the following:

  • Mechanical Systems

  • Furnishings

  • Equipment

  • Special Construction

Question 192 of 200

Medal-premium 1

The following are true of reference standards, EXCEPT:

Select one of the following:

  • May be relied upon by the specifier to describe quality of work

  • Are consensus documents developed by various industry committees

  • Are frequently incorporated in code requirements

  • Are included in specifications to avoid having to reproduce lengthy requirements

Question 193 of 200

Medal-premium 1

The parties to an owner/design-builder contract are:

Select one of the following:

  • The Owner, the designer, and the builder

  • The Owner, the Architect, and the Contractor

  • The Owner and the construction manager

  • The Owner and the design-builder

Question 194 of 200

Medal-premium 1

Outline Specifications aid in the design process for all of the following EXCEPT:

Select one of the following:

  • revising cost estimates, schedules

  • value engineering studies

  • checklist for selecting products

  • serving as the basis for subcontracts in fast track construction

Question 195 of 200

Medal-premium 1

An affirmation of fact or promise made by the seller to the buyer that relates to the goods and becomes a part of the basis of the bargain creates . . .

Select one of the following:

  • an implied warranty

  • a full warranty

  • an express warranty

  • a guarantee

Question 196 of 200

Medal-premium 1

An information organizing framework for the A/E/C industry that assigns built environment data into 15 discrete, coordinated tables to facilitate the organization of project information and databases is known as:

Select one of the following:

  • Industry foundation classes (IFCs)

  • OmniClass

  • Building Information Model (BIM)

  • Building Information Management (BIM)

Question 197 of 200

Medal-premium 1

Substitution requirements and procedures during bidding

Select one of the following:

  • Are not allowed under most public bidding statutes

  • Are modified by the Supplementary Conditions

  • Are stated in the instructions to bidders

  • Provide for requests by telephone

Question 198 of 200

Medal-premium 1

The dollar amounts of cash allowances are:

Select one of the following:

  • The dollar amounts of cash allowances are:

  • On the Bid Form

  • In Division 01

  • In the specification sections of Division 02 through 49 that specify the product installation

Question 199 of 200

Medal-premium 1

The following are TRUE about closed proprietary specifications EXCEPT:

Select one of the following:

  • Manufacturer and product brand names or unique characteristics are used in the specifications.

  • Several products may be named as options

  • The A/E must coordinate the named product with other specification requirements.

  • Other products are allowed as substitutions upon approval of the owner

Question 200 of 200

Medal-premium 1

Use of master guide specifications:

Select one of the following:

  • Relies upon the quality of their update process

  • Requires knowledge of the conditions of the contract for which they were prepared

  • May be based upon a commercially-produced specification library

  • Requires practice knowledge in order to properly create project specifications

  • All of the above

Icon_fullscreen

CDT Exam - Fall 2015

Annette Scott
Quiz by , created about 1 year ago

CDT Exam - Fall 2015

Eye 12
Pin 0
Balloon-left 0
Tags
Megan Clark0427
Created by Megan Clark0427 about 1 year ago
Annette Scott
Copied by Annette Scott about 1 year ago
Close