120-1057-21: Oracle Project Management Cloud 2021 Implementation Essentials - Full

Questão 1 de 11

1

Your client has implemented Oracle Cloud Applications with their United States business unit and United Kingdom business unit. After six months, they acquired another company in China and added a China business unit.
A project accountant in your organization is authorized to access transactions for
the US, UK, and China business units. The project accountant can see the
transactions for the US and UK business units but not for the China business unit.

Why is he not able to see the transactions for the China business unit?

Selecione uma das seguintes:

  • The application role relevant to the China business unit is not assigned to the project
    accountant.

  • The project accountant is not assigned to the external role that grants access to the
    China business unit.

  • The US and UK business units are linked to different ledgers than the China business
    unit.

  • The China business unit is associated with a different legal entity than the US and UK
    business units.

Explicação

Questão 2 de 11

1

Your customer wants a team member who is assigned to a project to be able to
create and submit a forecast, but not to be able to approve the forecast.

What is the default project role that you should assign to the person in the project
to meet this requirement?

Selecione uma das seguintes:

  • Project Manager

  • Project Administrator

  • Project Application Administrator

  • Project Accountant

Explicação

Questão 3 de 11

1

Your customer wants to see how quantity, cost, and revenue amounts are automatically distributed by using Spread Curve.

Identify two period options that are available for this purpose.

Selecione uma ou mais das seguintes:

  • Calendar Types

  • Project Accounting Periods

  • Accounting Periods

  • PA Calendar

  • PA-GL Periods

Explicação

Questão 4 de 11

1

Your customer wants a project start date to cascade to the project tasks, but does not want the finish date to be cascaded.

Identify the default setup in a project template that can be used to enable this.

Selecione uma das seguintes:

  • Cascade change to the start date.

  • Do not cascade date changes.

  • Cascade change to the finish date.

  • Cascade change to the start date and the finish date.

Explicação

Questão 5 de 11

1

Your customer has a requirement to import and process third-party
transactions that are "costed" and "accounted".

Which configuration option needs to be set satisfy the requirement?

Selecione uma das seguintes:

  • Import Options

  • Document Options

  • Transaction Source Options

  • Document Entry Options

Explicação

Questão 6 de 11

1

You have four resources in your organization: P, Q, R, and S.

Resource P - Project or resource calendar is active.

Resource Q - Project resource request dates are within the project or resource calendar effective dates.

Resource R - Resource calendar is complex, it does not contain seven days, and it contains more than one pattern and shift.

Resource S - Number of working days within the requested date range is not zero on the project or resource calendar.

Selecione uma das seguintes:

  • P

  • Q

  • R

  • S

Explicação

Questão 7 de 11

1

You have defined two expenditure types but they are not available for selection when you enter an expenditure batch.

Identify the reason for this problem.

Selecione uma das seguintes:

  • The two expenditure types are not assigned to the reference data set that is assigned
    to the project unit in which the transaction is performed.

  • The two expenditure types are not assigned to the reference data set that is assigned
    to the project-owning organization in which the transaction is performed.

  • The two expenditure types are not assigned to the reference data set that is assigned
    to the business unit in which the transaction is performed.

Explicação

Questão 8 de 11

1

Your customer wants to automatically allocate unassigned asset lines
and common costs across multiple assets based on the construction-in-process cost
of each asset.

Identify the asset allocation method that you must use as the default method while
configuring project types to meet this requirement.

Selecione uma das seguintes:

  • Standard Unit Cost

  • Actual Unit

  • Current Cost

  • Estimated Cost

  • Spread Evenly

Explicação

Questão 9 de 11

1

Which two statements describe how the Resource Qualification Score
is calculated?

Selecione uma ou mais das seguintes:

  • An individual's score is 100% if the resource request has a qualification with a
    specified proficiency and the resource does not have the qualification.

  • An individual's score is 100% if the resource request has a qualification, but no
    proficiency is specified and the resource has the qualification.

  • An individual's score is 100% if the resource request has a qualification with a
    specified proficiency and the resource has the qualification that meets the specified
    proficiency.

  • An individual's score is 100% if the resource request has a qualification with a
    specified proficiency and the resource has the qualification with a proficiency that is
    lower or higher than specified.

Explicação

Questão 10 de 11

1

Which three tools are available for accessing REST APis?

Selecione uma ou mais das seguintes:

  • Programming Language

  • Web Browser

  • cURL

  • Oracle Transactional Business Intelligence

Explicação

Questão 11 de 11

1

You have a billable project for which the following details are provided:

Associated Inception-To-Date (ITD) Project Actual Cost: USD 60
Associated Project Budgeted Cost: USD 300
Contract Amount: USD 1000
Project Funded Amount: USD 750
Sum of Existing Revenue Events: USD 80

Identify the Associated Project Spent revenue that will get generated based on the
preceding details.

Selecione uma das seguintes:

  • USD 184

  • USD 120

  • USD 134

  • USD 70

Explicação