{"ad_unit_id":"App_Resource_Sidebar_Upper","resource":{"id":1463630,"author_id":761919,"title":"The design team quiz. ","created_at":"2014-10-14T15:28:57Z","updated_at":"2017-01-17T00:31:30Z","sample":false,"description":"Identify members of the construction design team and their roles. ","alerts_enabled":true,"cached_tag_list":"","deleted_at":null,"hidden":false,"average_rating":"3.0","demote":false,"private":false,"copyable":true,"score":150,"artificial_base_score":0,"recalculate_score":true,"profane":false,"hide_summary":false,"tag_list":[],"admin_tag_list":[],"study_aid_type":"Quiz","show_path":"/quizzes/1463630","folder_id":1296946,"public_author":{"id":761919,"profile":{"name":"Tom Jones7007","about":null,"avatar_service":"google","locale":"en-GB","google_author_link":"https://plus.google.com/103174249894966195263","user_type_id":147,"escaped_name":"Tom Jones7007","full_name":"Tom Jones7007","badge_classes":"ubadge ubadge-educator "}}},"width":300,"height":250,"rtype":"Quiz","rmode":"canonical","sizes":"[[[0, 0], [[300, 250]]]]","custom":[{"key":"env","value":"production"},{"key":"rtype","value":"Quiz"},{"key":"rmode","value":"canonical"},{"key":"uauth","value":"f"},{"key":"uadmin","value":"f"},{"key":"ulang","value":"en_us"},{"key":"ucurrency","value":"usd"}]}
{"ad_unit_id":"App_Resource_Sidebar_Lower","resource":{"id":1463630,"author_id":761919,"title":"The design team quiz. ","created_at":"2014-10-14T15:28:57Z","updated_at":"2017-01-17T00:31:30Z","sample":false,"description":"Identify members of the construction design team and their roles. ","alerts_enabled":true,"cached_tag_list":"","deleted_at":null,"hidden":false,"average_rating":"3.0","demote":false,"private":false,"copyable":true,"score":150,"artificial_base_score":0,"recalculate_score":true,"profane":false,"hide_summary":false,"tag_list":[],"admin_tag_list":[],"study_aid_type":"Quiz","show_path":"/quizzes/1463630","folder_id":1296946,"public_author":{"id":761919,"profile":{"name":"Tom Jones7007","about":null,"avatar_service":"google","locale":"en-GB","google_author_link":"https://plus.google.com/103174249894966195263","user_type_id":147,"escaped_name":"Tom Jones7007","full_name":"Tom Jones7007","badge_classes":"ubadge ubadge-educator "}}},"width":300,"height":250,"rtype":"Quiz","rmode":"canonical","sizes":"[[[0, 0], [[300, 250]]]]","custom":[{"key":"env","value":"production"},{"key":"rtype","value":"Quiz"},{"key":"rmode","value":"canonical"},{"key":"uauth","value":"f"},{"key":"uadmin","value":"f"},{"key":"ulang","value":"en_us"},{"key":"ucurrency","value":"usd"}]}
Who is responsible for translating ideas into sound accurate drawings that the contractor can follow?
Answer
Clerk of works
Resident engineer
Architectural technologist
Question 2
Question
Which of the following is employed directly by the client, who will want to assurance that a contractor is producing a building that meets the specification in terms of both materials and workmanship?
Answer
Building services engineer
Facilities manager
Quantity Surveyor
Interior designer
Clerk of works
Question 3
Question
Who is sometimes used on contracts where the internal finish and décor is important or of a prestigious nature?
Answer
Resident engineer
Interior designer
Architect
Client
Question 4
Question
Who will produce precise and accurate details of construction technology since quantity surveyors will need to read these drawings so that the bills of quantities and the specifications can be drawn up?
Answer
Architect
Architectural technologist
Quantity surveyor
Building services engineer
Question 5
Question
Which member of the design team will have an understanding of health, safety and welfare legislation and its implications on design and construction?
Answer
Interior designer
Structural engineer
Architect
Resident engineer
Question 6
Question
Who will be responsible for the effective use of heat, light, acoustics, and other electrical appliances?
Answer
Facilities manager
Clerk of works
Building services engineer
Architect
Question 7
Question
Who will maintain the building once it has been built.
Answer
Landscape architect
Building services engineer
Facilities manager
Interior designer
Question 8
Question
This person will design the load of the building and ensure that each component is designed to safely withstand the loads which are imposed on the building.
Answer
Architect
Resident engineer
Structural engineer
Landscape architect
Question 9
Question
This person does not have the authority to impose variations or changes to the design but is there to inspect and visit the site frequently?
Answer
Structural engineer
Clerk of works
Resident engineer
Architect
Question 10
Question
This person is usually based close to the construction works, or on the site itself.
Answer
Landscape architect
Resident Engineer
Architect
Quantity surveyor
Question 11
Question
Frequently speculative housing projects will benefit from the person who designs open spaces and leisure areas , usually this person is employed as the?
Answer
Architectural technologist
Quantity surveyor
Landscape architect
Facilities manager
Question 12
Question
These people will discuss the design brief and different solutions to produce an agreed design and specification.
Answer
Client / Resident engineer
Architect / Building services engineer
Quantity surveyor / Facilities manager
Architect /client
Question 13
Question
These people will interact about the structural feasibility of the agreed design and come up with any amendments as necessary.
Answer
Quantity surveyor / Client
Architectural Technologist / Structural Engineer
Architect / Structural Engineer
Structural Engineer / Building Services Engineer
Question 14
Question
These people will discuss the clients budget and cost s of the various schemes.
Answer
Architect / Quantity Surveyor / Client
Resident Engineer / Client / Quantity Surveyor
Quantity Surveyor / Client / Facilities Manager
Building Services Engineer / Client / Quantity Surveyor
Question 15
Question
These people will discuss, amend or negotiate tenders and quotations for work.
Answer
Principal Contractor / Quantity Surveyor / Client
Principal Contractor / Quantity Surveyor / Clerk of Works
Principal Contractor / Quantity Surveyor / Architect
Building Services Engineer / Quantity Surveyor / Principal Contractor
Question 16
Question
Which design team members will agree on the final account on completion of the work.
Answer
architect / structural engineer
architect / quantity surveyor / client
Principal contractor / architect / quantity surveyor