What are the three main aspects of the 'systems' approach, or 'systems thinking'?
Answer
Business
Organization
Technology
Financial
Management
Question 2
Question
What are the four 'organizational frames' derived from the 'systems thinking' approach of project management?
Answer
Structural, Human Resources, Political, Symbolic
Human Resources, Financial, Ethical, Technological
Financial, Ethical, Symbolic, Intrinsic
Strength, Weakness, Opportunity, Threat
Question 3
Question
What is the definition of a process within a project?
Answer
An action, or series of actions towards a particular result.
A milestone or deliverable.
A plan measuring the time estimates and resource allocation for the project. Ex. a Work Breakdown Structure.
Completion of the project.
Question 4
Question
List the five [elements/stages/phases] of a project:
Answer
Initiating
Planning
Design
Execution
Monitoring & Controlling
Closing
Analysis
Measurement
Communication
Question 5
Question
Align the following tasks to their associated phase within the project:
Develop the Project Charter: [blank_start]Initiating[blank_end]
Develop the Work Breakdown Structure: [blank_start]Planning[blank_end]
Estimating Costs: [blank_start]Planning[blank_end]
Qualitative Risk Analysis: [blank_start]Planning[blank_end]
Acquire Project Team: [blank_start]Execution[blank_end]
Performing Quality Assurance: [blank_start]Executing[blank_end]
Verifying and Controlling Scope: [blank_start]Monitor/Control[blank_end]
Performing Quality Control: [blank_start]Monitor/Control[blank_end]
Control Costs: [blank_start]Monitor/Control[blank_end]
Close Procurements: [blank_start]Closing[blank_end]
Answer
Initiating
Planning
Initiating
Planning
Execution
Monitor/Control
Closing
Execution
Monitor/Control
Closing
Planning
Initiating
Execution
Monitoring/Controlling
Closing
Planning
Initiating
Execution
Monitoring/Controlling
Closing
Execution
Initiating
Planning
Monitoring/Controlling
Closing
Executing
Initiating
Monitoring/Controlling
Planning
Closing
Monitor/Control
Initiating
Planning
Execution
Closing
Monitor/Control
Execution
Closing
Initiating
Planning
Monitor/Control
Execution
Closing
Planning
Initiating
Closing
Initiating
Monitoring/Controlling
Planning
Execution
Question 6
Question
The three main project constraints are commonly identified as time, scope, and ca$h money
Answer
True
False
Question 7
Question
Am I definitely supposed to memorize the following algorithm for a reason that will become obvious in the next question?
Phone Call Seniors To Collect RRSP Quickly
Answer
True
False
Question 8
Question
I have to pair multiples together because I only have ten fields total, but select all of the correct 'knowledge areas', or components of a Project Plan document:
Make use of that dumb acronym I made on the question previously.