Question 1
Question
The __________ of the project team is a crucial but unstated element of ancillary trade-offs
that the project manager must consider
Question 2
Question
Identify the example that would not usually be considered a project
Answer
-
developing a computer software application program
-
building a house
-
hosting a wedding reception
-
assembly line manufacturing of automobiles
Question 3
Question
Projects often interact with other projects being carried out simultaneously within the
organization and these interactions take the form of competition for scarce resources
between projects. This is an example of project __________.
Answer
-
breakdown
-
malfunctioning
-
interdependencies
-
bottleneck
Question 4
Question
A conventional project life cycle is a(n) __________ curve
Answer
-
low
-
steep
-
s-shaped curve
-
bell-shaped
Question 5
Question
Having only partial or no information about the situation or outcomes is called __________.
Answer
-
effort
-
uncertainty
-
risk
-
cluelessness
Question 6
Question
According to the PMBOK Guidebook, a __________ is a temporary endeavor
undertaken to create a unique product or service.
Answer
-
program
-
sub-process
-
Project
-
task
Question 7
Question
Conflicting expectations among stakeholders related to performance, cost, and time will
require the project manager to make appropriate ____________ in order to balance
competing demands related to these objectives
Answer
-
guidelines
-
weights
-
tasks
-
trade-offs
Question 8
Question
According to the authors, the prime objectives of project management are
Answer
-
customer satisfaction, budget, schedule
-
scope, cost, time
-
cost, quality, customer satisfaction
-
quality, scope, schedule
Question 9
Question
When done properly, project management begins with __________.
Question 10
Question
The “stretched-S” pattern observed during the project lifecycle, for the most part, is a
result of the _________.
Answer
-
changing attitudes of the people who work in the project
-
difficulty in performing the individual activities of a project
-
changing levels of resources used during successive stages of the project lifecycle
-
principle that work expands to fill the allotted time
Question 11
Question
The attributes that characterize a project are __________.
Answer
-
purpose, repetition, interdependencies, consistency, uncertainty, conflict, and
one-time occurrence
-
resources, uniqueness, conflict, interdependencies, one-time occurrence, and
finite duration
-
purpose, lifecycle, conflict, certainty, independence, performance, and finite
duration
-
lifecycle, schedule, cost, uncertainty, independence, uniqueness, and purpose
Question 12
Question
The largest amount of effort applied to a project is during its __________
Answer
-
conception
-
planning, scheduling, monitoring, and control
-
selection
-
evaluation and termination
Question 13
Question
The project to construct a highway is unique because __________.
Answer
-
the characteristics of terrain will be different for different segments
-
different types of laborers will be used to build various segments of the highway
-
different people manage different sections of the highway
-
consistency of the concrete will vary for different segments
Question 14
Question
The military uses the term __________ to refer to an exceptionally large, long-range
objective that is broken down into a set of projects
Answer
-
task
-
program
-
campaign
-
subproject
Question 15
Question
Which of the following is not one of the four dimensions of project success
Answer
-
opening new opportunities for the future
-
business impact on the organization
-
number of people working on the project
-
impact on the customer
Question 16
Question
As sub-elements of a task, these __________ need to be accomplished to achieve the
objectives of the task.
Answer
-
work packages
-
programs
-
subprojects
-
levels of effort
Question 17
Question
Individuals or groups with a special interest in a project are called __________.
Answer
-
project managers
-
leaders
-
directors
-
stakeholder
Question 18
Question
The desired outcomes or results of a project are called ____________.
Answer
-
deliverables
-
work packages
-
subgroups
-
subprojects
Question 19
Question
Numeric project selection models generally focus on
Answer
-
Keeping the workforce numbers stable
-
Profits and profitability
-
Maintaining stock price & ROI
-
Management salary stability
Question 20
Question
If the NPV for a project is > 0, it indicates that the project will __________.
Question 21
Question
Risk is generally believed to focus on profits, but
Answer
-
About 50 percent of projects fail financially
-
Uncertainty plagues all aspects of the work and is present in all stages
of PM
-
Risk in projects is primarily focused on timely completion
-
Very few projects fail financially
Question 22
Question
Strategic benefits of PPM are
Question 23
Question
An “Unweighted 0-1 Factor Model” has the advantage of:
Answer
-
Simplicity.
-
Reducing problems with industry partners
-
Increased understanding & agreement within the organization
-
Greater organizational flexibility
Question 24
Question
Successful Project Management (PM) includes which of the following attributes
Answer
-
Focuses on high risk goals and endeavors
-
Strongly relates to the organization’s strategy, mission & goals.
-
Includes a complex set of methods involving multiple stakeholders.
-
Addresses problems outside the organization’s current mission.
Question 25
Question
The Weighted Factor Scoring Model has the advantage of:
Question 26
Question
The __________ is a widely adopted model when making selection decisions
on all sorts of projects by putting them in groups.
Question 27
Question
Which of the following project selection models focuses strongly on the longterm
success of the firm?
Answer
-
Profitability Index.
-
Sustainability Model
-
Competitive Necessity
-
Product Line Extension
Question 28
Question
Project proposals for outside clients should include all of the following, EXCEPT
__________
Answer
-
a detailed profit and loss calculation of the proposing group
-
a section describing the past experience of the proposing group
-
a general description of the problem
-
a description of the ability of the proposer to supply the facilities, needed
during the project
Question 29
Question
For your project, the average net cash flow is $5,000 per year into the
foreseeable future and the initial project investment will be $100,000. Then the
payback period is [blank_start]20[blank_end]
Question 30
Question
The disadvantage of the __________ model is that the output is strictly a
relative and subjective measure.
Question 31
Question
The __________ can use discounted or not discounted cash flows when being
calculated.
Answer
-
profitability index
-
Q-sort method
-
internal rate of return
-
payback period
Question 32
Question
Which of the following is NOT a type of nonnumeric model
Question 33
Question
Project Portfolio Management (PPM) involves participation by
Answer
-
the entire project management team
-
the organization President
-
only the Project Manager.
-
stockholders in publicly traded organizations
Question 34
Question
Which stages of the Project Management Life Cycle are most likely to experience conflict with Time, Cost & Scope
Answer
-
End of the Project
-
Beginning of the Project
-
All stages
-
Middle stages
Question 35
Question
Most of the conflicts between organizations and outsiders have to do with what?
Question 36
Question
Today outsourcing is growing rapidly, but
Answer
-
Chartering is growing faster
-
The use of partnerships and charters is growing slowly
-
Partnerships are growing faster
-
Many foreign countries discourage it
Question 37
Question
To begin managing conflict what should happen first?
Answer
-
Relevant issues must be listed and described from the two conflicting points of view
-
Both parties should hire lawyers
-
a Contract must be written
-
Stakeholders should be identified
Question 38
Question
Which categories of conflicts are most common throughout the Project Life Cycle
Answer
-
Groups with different goals and expectations
-
Significant uncertainty about who has authority
-
Interpersonal conflicts between the stakeholders
-
Goals, expectations, authority, and interpersonal conflicts.
Question 39
Question
A recommended, effective method of conflict resolution is:
Answer
-
Insistence on 100 percent consensus to move forward
-
Avoidance, or ignoring problem areas
-
Doing what the Project Manager says to do
-
Negotiation involving all concerned parties, and collaborating
Question 40
Question
What is a common goal for partnering among organizations
Answer
-
Collaborations among family members in upper management
-
Making international friendships
-
Avoiding legal issues with interstate trade
-
Diversification of technical risk, avoidance of capital investment, reducing political risk, and pooling of complementary knowledge
Question 41
Question
If a resource conflict arises between two high-priority projects, precedence is typically given to the project with the __________.
Answer
-
fastest completion time
-
earliest due date
-
lowest cost to complete
-
biggest revenue stream
Question 42
Question
Conflicts are satisfied when
Answer
-
the boss says it’s over
-
the level of frustration is lowered to the point where no action is contemplated, by either party, against the other party
-
someone gives up
-
someone wins the argument
Question 43
Question
Common problems in the first stage, Project Formation, are due to
Question 44
Question
A major requirement for conflict resolution is what?
Answer
-
Upper management should agree on the terms of agreement
-
The conflict should be settled without irreparable harm to the project’s objectives
-
There must be no bad publicity
-
Customers should be satisfied with the outcome
Question 45
Question
The use of a cooperating or accommodating strategy where you do not assert your position, is appropriate when?
Answer
-
Everyone is tired of negotiating
-
It is too difficult to get consensus.
-
You are right but the other party needs to “win a few”.
-
You are wrong
Question 46
Question
A recommended stakeholder analysis tool is the
Question 47
Question
The ideal project manager should be __________.
Answer
-
a technical specialist competent in principles of robust design
-
a direct, technical supervisor knowledgeable in the technology of the process being used
-
a facilitator and specialist with technical credibility
-
both generalist/facilitator and have a high level of technical competence in the science of the project
Question 48
Question
During project build-up, the project should move from a general concept to __________.
Question 49
Question
Project success depends upon:
Answer
-
The use of partnerships and charters
-
Both the technical skills of the team and the political and negotiating
skills of the PM are critical
-
Technical skills of the project team members
-
Political and negotiating skill of the PM
Question 50
Question
Because the PM typically has no direct authority over project team members,
s/he should motivate good performance how?
Answer
-
Using cash awards of various types
-
Threatening to expose their faults, errors, and poor performance
-
Posting progress charts with goals and targets for each week
-
Recognition, achievement, challenging assignments, responsibility,
chance to learn new skills, & the work itself
Question 51
Question
This member of the project team is responsible for the efficient production of
the product of the process, including the manufacturing engineering, design
and production of tooling, production scheduling, and other production tasks.
Answer
-
support services manager
-
development engineer
-
project engineer
-
contract administrator
Question 52
Question
In the past decade a new type of organizational structure has become
increasingly popular, It is called the:
Answer
-
Innovative Organization
-
Enterprise.
-
Subsidiary Organization
-
Project Organization
Question 53
Question
What is a major advantage of the Functional Organization for a Project?
Answer
-
It offers maximum flexibility in use of personnel
-
Experts can be taken from their functional departments and
permanently assigned to the project.
-
It can be used to hide secret projects
-
It is very popular in the production industry
Question 54
Question
In a “Projectized” organization:
Answer
-
Relevant issues must be described in the Project Charter
-
A Scope of Work Contract must be written
-
Each Project Manager has full line authority so there is one person in
charge
-
All stakeholders must be identified
Question 55
Question
When a project requires input from several functional areas and uses a
sophisticated technology, the recommended organizational structure is:
Answer
-
Functional.
-
Matrix.
-
Ad hoc
-
Consensus.
Question 56
Question
Common methods to select project forms are:
Question 57
Question
Identify the statement that is NOT a major advantage of placing a project within
a functional department of the parent organization.
Answer
-
The functional division tends to be focused on activities particular to its
function instead of the project.
-
The functional division serves as a base of technological continuity.
-
Expertise is easily shared across multiple projects
-
The flexible use of staff increases
Question 58
Question
Typically when PMs, in large functional organization, are asked how many
people report to them, the reply is what?
Answer
-
Ten to Fifteen
-
Twenty or more
-
Five to ten
-
None
Question 59
Question
Meeting schedule and cost goals without compromising performance is what
type of problem?
Answer
-
Confidential or top secret.
-
A technical problem.
-
A human resource management problem.
d.
-
Both a technical management and human resource management
problem
Question 60
Question
This member of the project team is in charge of product design and
development and is responsible for functional analysis, specifications,
drawings, cost estimates, quality/reliability, engineering changes, and
documentation.
Answer
-
project controller
-
manufacturing engineer
-
systems architect
-
support services manager
Question 61
Question
Most firms eventually adopt which organizational form for running their
projects?
Answer
-
Projectized.
-
Functional.
-
Virtual.
-
Matrix.
Question 62
Question
Where is the location of a project in the “functional structure” within a traditional
large organization?
Answer
-
Spread throughout the organization
-
Where it functions best
-
Within one of the major divisions or departments of the organization
-
In the President’s office
Question 63
Answer
-
Premeditated
Organization.
-
Person of Most Objectivity
-
Personal Management Operational style
-
Project Management Office
Question 64
Question
Common benefits of the Matrixed Organization include
Answer
-
Less political infighting
among PMs because project staff have at least
two or more bosses
-
Greater visibility to upper management & higher wages
-
Rapid response to client needs & less anxiety over next job after project
ends
-
Higher salaries & better promotion potential
Question 65
Question
Composite Organizational designs exist when:
Answer
-
The primary product of the Project is producing Composites
-
Projects in one organization are composed of specific, fixed
departments
-
Several organizations form a partnership project.
-
Both functional and projectized divisions coexist in one firm.
Question 66
Question
In a “Projectized” organization
Answer
-
There is legal protection for each project and project manager
-
The organization is run as one big project
-
Each project includes a full set of the functions (staff, resources, etc)
needed for its operation
-
Each Project is divided into many subprojects
Question 67
Question
A major advantage of using a __________ placement for a project is that
individual experts can be utilized by many different projects.
Answer
-
projectized
-
functional
-
virtual
-
standard
Question 68
Question
Viewing the whole at one time rather than each piece individually describes the
__________ approach.
Answer
-
system
-
encompassing
-
homogeneous
-
enveloping
Question 69
Question
_____ on the Critical Path _______?
Answer
-
The majority of activities; are full of slackers.
-
The majority of activities; have some slack
-
No activities; have zero slack
-
All activities; have zero slack
Question 70
Question
Task F has duration of 10 days and an earliest start date of 20 days. Based on the given
data, determine the early finish duration for task F.
Answer
-
30 days
-
20 days
-
10 days
-
5 days
Question 71
Question
Of the choices below, which tool has the most significant influence on the management
of projects?
Answer
-
PERT chart
-
Organization chart
-
GANTT chart
-
The Schedule
Question 72
Question
What is the impact of increasing the time for completion of a project?
Question 73
Question
A(n) __________ is a specific task or set of tasks that are required by the project, use
up resources, and take time to complete.
Answer
-
path
-
milestone
-
node
-
activity
Question 74
Question
The most popular method for displaying a project schedule is the _______ due to ease
of use and ease of construction:
Answer
-
PERT
-
CPM
-
Network Diagram
-
Gannt Chart
Question 75
Question
Which of the following is NOT an advantage of a Gantt chart?
Answer
-
It provides a good picture of the state of the project
-
Gantt charts are more effective for very large projects than ordinary projects.
-
It is relatively easy to maintain
-
It can be easily understood
Question 76
Question
What is more common in business project management today?
Answer
-
Activity on Node (AON)
-
Activity on Arc (AOA)
-
Activity on Path (AOP)
-
Activity on Arrow (AOA)
Question 77
Question
The difference between the late start and early start for an activity is called its
__________.
Answer
-
task
-
progress
-
float
-
critical path
Question 78
Question
The _________ is the key input for establishing the monitoring and control systems for
the project
Answer
-
budget
-
Organization chart
-
PERT Chart
-
schedule
Question 79
Question
What is Monte Carlo Simulation used for?
Answer
-
Managing the effects of Gamma
-
Evaluating the impact of various management decisions
-
Calculating Alpha
-
It is normally not used in Project Management
Question 80
Question
In PERT networks, assuming a normal distribution about estimates of duration, the
“pessimistic” time would be where there is a _______.
Answer
-
1% chance the actual work time is less
-
1% chance the actual work time is greater.
-
50% chance the actual work time is greater.
-
0% chance the actual work time is less
Question 81
Question
A precedence relationship where the completion of a successor activity depends on the
completion of a predecessor activity is called a __________.
Answer
-
start to start dependency
-
finish to start dependency
-
start to finish dependency
-
finish to finish dependency
Question 82
Question
The series of connected activities or events between any two events in a network is
called
Answer
-
Network
-
Path
-
Event
-
Stream
Question 83
Question
Ambiguities in projects
Answer
-
are overwhelming
-
can be reduced by using probabilities
-
can and must be eliminated
-
can be managed to reduce their impact
Question 84
Question
Project Management, Parkinson’s Law states that
Answer
-
Idle hands are created by slack
-
The early bird gets the worm
-
ET = (a + 4m + b) / 6
-
Work expands to fill the time allotted
Question 85
Question
Which of the following is NOT a software tool commonly used to manage projects,
especially in relation to time and cost budgets?
Answer
-
Microsoft Project
-
Microsoft Word
-
Microsoft Excel
-
Crystal Ball
Question 86
Question
The critical activities in real-world projects typically constitute less than __________% of
the total activities in the project.
Question 87
Question
A task or set of tasks that are required by the project are called
Answer
-
Activities
-
Networks
-
Events
-
Paths
Question 88
Question
In a well-understood projects, such as highway construction, budgeting is:
Answer
-
Estimating by scaling the various cost elements based on historical data
-
Usually very precise and accurate
-
Routine and boring
-
Rarely accurate because each highway is different
Question 89
Question
The pattern of deviations in cost and usage used for exception reporting to management is
called __________.
Answer
-
variances
-
summaries
-
simulations
-
assumptions
Question 90
Question
Learning curves are important for:
Answer
-
Estimating cost improvement as parts become “broken in”.
-
Visualization of curved mechanical parts
-
estimating performance improvement as workers become experienced.
-
Helping new PMs understand the required math.
Question 91
Question
The second (1997) Mars Pathfinder and Sojourner Rover project achieved a 94 percent cost
reduction over the earlier (1976) Mars-lander mission due to:
Answer
-
better-trained engineers
-
deflation of the US dollar
-
design-to-cost method replacing the earlier design-to-performance method
-
Inflation of the US dollar
Question 92
Question
If projects include repetitive tasks with significant human input, the __________ rate should be
factored into the cost estimate.
Answer
-
hurdle
-
inflation
-
learning
-
interest
Question 93
Question
The use of Monte Carlo Simulation
Answer
-
Removes ambiguity in the project parameters
-
Only provides a description of project uncertainties, but does not remove risk
-
Saves time and money
-
Reduces project risk
Question 94
Question
Crystal Ball is a software program that
Answer
-
Allows simulation of precise forecasts, which are most valuable
-
Provides a distribution of potential outcomes with associated probabilities
-
Is useful because it can predict the future
-
as developed by gypsies and is not very useful for Project Management.
Question 95
Question
One key reason for the 1997 Mars Project cost savings was
Answer
-
A project cash reserve was held back for time-phased release
-
Cost overruns were taken out of engineers’ paychecks
-
The cost accountants acted as Project Managers
-
Managers were fired for cost overruns
Question 96
Question
The major responsibility of professional cost estimators is to:
Answer
-
Reduce the level of uncertainty in cost estimates.
-
Add 20 percent to all estimates to avoid cost overruns
-
Eliminate unnecessary steps in the original engineering designs
-
Keep upper management happy & stay employed
Question 97
Question
__________ budgeting allows income and expenditures to be aggregated across projects
Answer
-
Expense-oriented
-
Project-oriented
-
activity-oriented
-
Category-oriented
Question 98
Question
Unknown-unknowns are not part of the baseline budget and are referred to as
Answer
-
PMBOK reserves
-
Buffered reserves
-
management reserves
-
contingency reserves
Question 99
Question
The advantage of the______ process is that it is generally associated with participative
management.
Answer
-
top-down
-
Efficient
-
Murphy’s
-
bottom-up
Question 100
Question
In order to develop a budget, the PM must forecast __________.
Question 101
Question
__________ states that adding manpower to a late software project makes it later
Answer
-
The Rule of Thumb
-
Smith’s Law
-
Murphy’s Law
-
Brooks’ Law
Question 102
Question
Many lower-level managers often treat the entire budgeting process as if it were a __________, a
situation in which any individual’s gain is another individual’s loss. This can make competition
among junior managers quite intense.
Answer
-
Top-down approach
-
zero-sum game
-
Brooks’ Law result
-
pie-chart dilemma
Question 103
Question
The Project Budget is
Answer
-
Not a sufficient measure of a Project’s progress or value to the organization
-
The primary means of obtaining Upper Management approval of a project
-
Generally so inaccurate that it is of little value in decision-making.
-
A sufficient measure of a Project’s progress and value.
Question 104
Question
What is always certain in projects?
Answer
-
They will be difficult but fun.
-
They provide stepping stones to promotion to upper management.
-
The Project Manager (PM) will be respected by the line managers.
-
Things will not go precisely as planned.
Question 105
Question
Another important factor in the 1997 Mars Project cost savings was
Answer
-
Upper management was very strict on paying bills
-
The 1997 Mars Lander never left the ground. It only simulated landing.
-
70 percent of major procurements contracts were fixed-price rather than cost-plus.
-
Subcontractors were fired if they sent bills greater than original estimates
Question 106
Question
___________ costs are not associated with any specific produc
Question 107
Question
Unless the project manager is familiar with the firm’s __________ it will be very difficult to exercise
budget control.
Answer
-
cost accounting
-
marketing procedures
-
budget plans
-
accounting system
Question 108
Question
The process of managing risk in a project is
Answer
-
a dynamic process throughout the project life cycle
-
not part of the PMBOK
-
selected by the management team
-
done at the beginning of the project planning cycle.
Question 109
Question
Common problems in managing projects include which of the following?
Question 110
Question
During project formation, the organizational structure selected will have a major impact
on the ways in which conflicts are handled. Lack of clarity about the relative
power/influence/authority of the PM and the functional managers is a major component
of all conflicts involving __________.
Question 111
Question
One of the challenges project managers face is to ensure that managers do not mix
__________.
Answer
-
outcomes with the specific tasks needed to produce them
-
outside interests’ requirements with organizational expectations
-
control limits with specifications
-
project milestones with their respective completion dates
Question 112
Question
Risk management’s primary focus is on what type of activities?
Answer
-
Keeping the organization’s problems from appearing in the local newspapers.
-
Complex coordination of planning, risk identification, risk analysis, response
planning, monitoring & control, and recording of incidents
-
Minimizing workforce injuries.
-
Protecting the firm’s money/profitability
Question 113
Question
Finding a solution to a conflict in which no party can be made better off without making
another party worse off by the same amount or more is called what?
Question 114
Question
A major purpose of the project management office should be to serve as __________.
Answer
-
maintenance for the project management library
-
the central location for all clerical support
-
the critical disaster recovery support
-
a link between strategic management and project management
Question 115
Question
A formalized method for transforming the opinions of a group of individuals into
quantitative measures that can be aggregated for use in decision-making is referred to
as the __________.
Answer
-
Delphi system
-
portfolio
-
simulation
-
expert system
Question 116
Question
This element of the project plan contains a brief description of the procedure to be
followed in monitoring, collecting, storing, and evaluating the history of the project
Answer
-
evaluation methods
-
resources
-
personnel
-
schedule
Question 117
Question
The process of coordinating the work and timing of the different groups working on
multidisciplinary teams is called __________.
Answer
-
vertical management
-
integration management
-
matrix management
-
procurement management
Question 118
Question
The process of dealing with uncertainties in projects that may affect the project for better
or for worse has come to be known as __________.
Answer
-
risk management
-
scope management
-
quality management
-
procurement management
Question 119
Question
The most difficult aspect of coordinating a complex project is…
Answer
-
Coordinating the various elements of the project to meet overall project goals.
-
Determining the needed skill sets of project workers
-
Political disputes between managers involved in the project
-
Determining appropriate costs and budget allocations for groups
Question 120
Question
Personality conflicts during project phase-out are often caused by __________.
Answer
-
the absence of deadlines
-
distribution of expenses charged to the project
-
pressure to complete the project and anxiety about leaving the project
-
the influx of newer technology
Question 121
Question
Firms usually have two or more projects and this collection of projects is referred to as
__________.
Answer
-
an initiation
-
a program
-
a portfolio
-
a stochastic model
Question 122
Question
A universal characteristic of all projects is that projects are:
Answer
-
unique
-
over budget
-
difficult
-
short on time
Question 123
Question
If a system is being updated due to operating necessity, the project was selected
because __________.
Answer
-
the system is worth saving at any cost
-
the dimension of cost is not relevant to execution of the project
-
the system is worth saving at the estimated cost of the project
-
the cost overruns can be hidden in someone else's budget
Question 124
Question
This project plan element lists all milestone events. It identifies the estimated time for
each task and is used to construct the master project schedule.
Answer
-
budget
-
schedule
-
personnel plan
-
evaluation methods
Question 125
Question
A characteristic of __________ projects is that the work on these projects can cross
time, space, organizational, and cultural boundaries
Answer
-
matrix
-
virtual
-
standard
-
projectized
Question 126
Question
When dealing with conflict between parties, it is recommended that one __________ in order to avoid the conflict becoming interpersonal.
Question 127
Question
A common problem in conflict resolution for new product or facility development is:
Answer
-
Stakeholder analysis tools are not relevant
-
Stakeholders cannot be identified.
-
Conflict is intense
-
The employees have not all been hired
Question 128
Question
Contracts are legal documents that
Answer
-
Ensure problems will not arise in projects
-
Prevent companies from going to court to solve their problems
-
May provide legal protection after problems arise
-
Ensure legal protection if problems arise
Question 129
Question
Finding a solution to a conflict in which no party can be made better off without making another party worse off by the same amount or more is
called what?
Question 130
Question
Projects are conducted in four important environments. They are __________.
Answer
-
economic, political, legal, and sociotechnical
-
routine, unique, fast-paced, and complex
-
profit, not for profit, government, and industry
-
internal, external, transitional, and multicultural
Question 131
Question
Effective, longtime Project Managers expect which of the following regarding their
Project Teams (PTs)?
Answer
-
Initial PT conflict, then cohesiveness & teamwork, finally disbanding when project
is complete.
-
Consistent good attitudes and hard work toward project goals, with successful
on-time finish.
-
Teamwork, following orders from PM, working overtime to complete tasks per
schedule, strong support from Functional Managers.
-
From the start the PT will be in harmony and work together to finish on time
Question 132
Question
When managing a project, the project manager is responsible for __________.
Answer
-
auditing the project
-
budgeting the project
-
designing the project
-
executing the project
Question 133
Question
As compared to the functional manager, the project manager should more often use
what approach to solving problems?
Question 134
Question
Acquiring and focusing personnel for work on the Project Team (PT) is generally difficult
because of:
Answer
-
lazy workers
-
the high visibility of the Project
-
team members’ dual responsibility to the Project and their Functional
Departments
-
lack of top management commitment to the Project
Question 135
Question
Resources initially budgeted for a project are frequently __________ for the task, partly
because of natural optimism by the proposer about how many resources are needed.
Answer
-
delayed
-
sufficient
-
hindrances
-
insufficient
Question 136
Question
Successful Project Managers (PMs) must have which of the following skills?
Question 137
Question
The project manager needs ________ credibility
Question 138
Question
The Project Manager’s job includes which of the following
Answer
-
Learning about foreign people and their national customs
-
Reducing conflict and stress between different types of Project Team members by
promoting understanding and appreciation
-
Keeping employees from different cultures and backgrounds off important project
teams to reduce friction and internal team conflict
-
Taking team members to cultural events to increase appreciation of each other
Question 139
Question
Attributes of successful project managers generally include which of the following?
Answer
-
Good technical skills, tough manager, good terms with senior management, broad
background including mostly success & few failures, works well under
pressure/stress, positive attitude & consensus builder.
-
Flexible, friendly, good with schedules, friends at top of organization
-
Strong management background, friends in upper management, little technical
skills, good negotiator
-
Prior successes, no failures, honesty, pride in their work, connections at top levels
of organization.
Question 140
Question
Which of the following choices represent the best mix of skills and attributes for Project
Team Members (PTMs)?
Answer
-
High technical skills, willingness to take orders from PM, self-control
-
Problem-solving ability, technical skills, modest opinion of self
-
Ability to take orders, good work habits, individual contributor
-
High technical skills, problem-solving ability, political sensitivity, goal orientation,
high self-esteem
Question 141
Question
The project manager must make trade-offs between project progress and process.
Conceptually, this involves trade-offs between the __________ functions.
Answer
-
technical and managerial
-
performance and schedule
-
schedule and cost
-
cost and performance
Question 142
Question
Which of the following is the most important for success of the project
Question 143
Question
How can effective, lasting business relationships be built across different cultures?
Answer
-
When disagreements occur, meeting together in an atmosphere of trust and
negotiation to resolve problems
-
lawsuits when people do not perform as expected
-
Selecting business partners only if they have proof of existing strong national ties.
-
Threatening to cancel contracts if multinationals will not agree to terms.
Question 144
Question
Identify the attribute that is NOT normally associated with the job of functional manager.
Answer
-
The functional manager is responsible for deciding what resources will be
devoted to accomplishing the task
-
The functional manager is responsible for deciding who will do the work.
-
The functional manager is usually a generalist in the area being managed.
Refer to the section: Project Management and the Project Manager.
-
The functional manager is administratively responsible for deciding how
something will be done
Question 145
Question
During the buildup phase, the project goals, in order of importance, are __________.
Answer
-
schedule, cost, scope
-
cost, scope, schedule
-
cost, schedule, scope
-
schedule, scope, cost
Question 146
Question
Under normal business conditions, when the functional manager takes over control of
important details of the Project, this is …...?
Question 147
Question
If deterministic time estimates are used, and if project deadlines are firm, there is a high
likelihood that it will __________.
Answer
-
be completed as per schedule
-
be completed on time and within budget
-
be necessary to crash the last few activities of most projects
-
not be necessary to crash any activities in projects
Question 148
Question
The __________ approach to constrained resource scheduling problems is the only feasible
method of attacking large, nonlinear, complex problems that tend to occur in the real world of
project management.
Answer
-
linear programming
-
optimization modeling
-
goal programming
-
heuristic
Question 149
Question
If all three critical resources are fixed, the system is
Answer
-
Fixed for a long time
-
Over-determined
-
On the Critical Path
-
Guaranteed to succeed
Question 150
Question
In some situations, two activities are scheduled to be carried out in parallel and using the same
scarce resource. If the supply of the scarce resource is not sufficient to allow both activities to be
carried out simultaneously, then whichever of the two is given priority immediately lengthens the
other activity’s path but not its actual __________.
Answer
-
buffer
-
slack
-
float
-
duration
Question 151
Question
Economically speaking, crashing a project creates a technology change in the __________ for an
activity.
Question 152
Question
Goldratt’s Critical Chain (1997) addresses what common PM problems?
Answer
-
Too much slack
-
Constrained resource scheduling
-
Not enough top management support
-
Lack of training for project team
Question 153
Question
Work situations that disrupt a Project Manager’s Schedule typically occur:
Answer
-
quarterly
-
rarely
-
annually
-
unexpectedly
Question 154
Question
When a project is crashed it
Question 155
Question
Most heuristic solution methods start with the __________ and analyze resource usage period by
period, resource by resource.
Answer
-
Master schedule
-
PERT/CPM schedule
-
Gantt chart
-
GERT schedule
Question 156
Question
Which of the following effects will be observed in a network if a date-constrained project is
scheduled from the ending date constraint using the “as late as possible” heuristic?
Answer
-
The network will not have any critical activities
-
Each activity will make use of all the slack available to it.
-
It would never be possible to override the “as late as possible” heuristic with a “must start
no later than” date constraint.
-
Many of the activities will be scheduled prior to the start date of the project.
Question 157
Question
The use of heuristics for project scheduling
Answer
-
Has built-in routines to optimize outcomes and seek the best solutions.
-
Employs rules of thumb that have been found to work well for similar situations
-
Is not recommended
-
Requires use of computers due to complexity of algorithms
Question 158
Question
Goldratt illustrates that overly optimistic Project Managers are:
Answer
-
generally rare and in great de
-
in high demand in industry
-
most likely to get large raises and promotions
-
very common and cause problems in scheduling
Question 159
Question
When a project is expedited it will often
Question 160
Question
The ___________ priority rule is the best overall and generally results in minimum schedule
slippage, minimum resource idle time, and minimum in-process inventory
Answer
-
last in, first out
-
minimum slack first
-
maximum cost first
-
first in, first out
Question 161
Question
Resource Leveling aims to minimize variations in resource usage by:
Answer
-
Signing fixed-cost contracts
-
Shifting tasks within their slack allowances
-
Keep resources on the same experience levels
-
Eliminating slack
Question 162
Question
In CPM, __________ are specified.
Answer
-
three costs
-
exact levels of uncertainty associated with activities
-
two activity times and two costs
-
n expected time, a crash time, and the standard deviation time
Question 163
Question
Which of the following describes the amount of resources a schedule requires during specific
time periods?
Question 164
Question
For Projects, time is always
Question 165
Question
The typical reasons for lack of necessary resources where and/or when needed are
Answer
-
Supplier failure to deliver on time, or loss or theft of a required resources
-
Poor planning by upper management.
-
Incompetence or laziness of staff.
-
Management failure to act in a timely manner
Question 166
Question
If the resources for a project are increased, the outputs usually:
Answer
-
Decrease in predictable ways
-
Remain constant
-
Increase in predictable ways
-
Change, but not in predictable patterns
Question 167
Question
Monitoring, as an activity, should be kept distinct from __________, which uses
data supplied by monitoring to bring actual performance into approximate
congruence with planned performance
Answer
-
reporting
-
recording
-
controlling
-
collecting
Question 168
Question
Effective reporting systems focus on
Answer
-
Providing the appropriate level of detail in reports to satisfy different
levels of managers
-
Following the original scope of the Project Plan.
-
Providing complete sets of available data.
-
Managing tradeoffs & eliminating risks
Question 169
Question
In earned value analysis, the 5050
rule assumes that __________.
Answer
-
50 percent is earned when the task begins and 50 percent is earned at
completion
-
50 percent is earned when the task begins and 50 percent is earned at
the halfway stage
-
50 percent is earned when the project is planned and 50 percent is
earned when the project is over
-
50 percent is earned when the task is half done and 50 percent is
earned at completion
Question 170
Question
For each factor to be measured during monitoring; performance criteria,
standards, and __________ should be established
Question 171
Question
Successful Project Monitoring Systems (PMS) plan, monitor, and facilitate
control of:
Answer
-
Time vs Schedule, Cost vs Budget, and Performance vs Planned Scope.
-
Budgets vs Expenses
-
Project Activities on PERTCPM
diagrams
-
Ontime
Delivery of products
Question 172
Question
The first step in setting up a monitoring system is to __________.
Answer
-
identify the key factors to be controlled
-
collect every available piece of information so it can be analyzed
-
use whatever information is available
-
collect existing data to see what data is relevant and available
Question 173
Question
According to the authors, in the planning monitoring
controlling
cycle, the
directions of the flows indicate that __________.
Select one:
Answer
-
information flows from the top to the bottom
-
information flows from the bottom to the top and authority flows from the
top to the bottom
-
authority flows from the bottom to the top
-
information flows from the top to bottom and authority flows from the
bottom to the top
Question 174
Question
Today, Project Managers generally use _______ to build schedules and track
progress for large, complex projects.
Answer
-
Mainframe computers
-
Sliderules.
-
Large, sophisticated computer programs.
-
Handheld
electronic devices, such as cellphones.
Question 175
Question
__________ is when individuals are overwhelmed with too many reports, too
much detail, and too much data.
Answer
-
Project isolation
-
Information overload
-
PMIS verification
-
Computer paralysis
Question 176
Question
Measuring characteristics such as “quality of team member cooperation” and
“morale of team members” generally takes the form of
__________characterizations
Answer
-
verbal
-
raw number
-
indicative
-
all of the above
Question 177
Question
Which of the following is NOT a common difficulty in the design of project
reports?
Answer
-
Providing too much detail
-
Having too many interface modules
-
Poor correspondence between the planning and monitoring systems
-
Poor correspondence to the parent firm’s reporting system
Question 178
Question
In earned value analysis, if the cost variance is ($
10,000), __________.
Answer
-
the cost variance is favorable
-
the scheduled variance is favorable
-
the scheduled cost avoidance is unfavorable
-
the cost variance is unfavorable
Question 179
Question
Variances are generally calculated so that
Answer
-
Variances of zero are always the favorable
-
Positive variances are favorable
-
Variances of zero indicate project is totally out of control
-
Negative variances are good
Question 180
Question
Reports for __________ have a need for detailed information about individual
tasks and the factors affecting such tasks.
Answer
-
project managers
-
all the stakeholders
-
top executives
-
lowerlevel
personnel
Question 181
Question
A good project monitoring system will require _________ as compared to
commonly used informal method:
Answer
-
Greater upfront
planning time & investment
-
Less cost
-
Outside consultants to manage them.
-
More time & money, but reduce risk to zero.
Question 182
Question
The most common mistake made when monitoring data is to gather
information that is clearly related to project performance but __________.
Answer
-
is so volatile that trends cannot be detected
-
cannot be captured in the mechanized PMIS
-
has little or no probability of changing significantly between collection
periods
-
is too unusual to use
Question 183
Question
A large proportion of all data collected takes one of the following forms
EXCEPT __________.
Answer
-
indicators
-
verbal measures
-
raw numbers
-
individual perceptions
Question 184
Question
An appropriate and common secondary use for monitoring and reports
includes
Answer
-
fixing the blame when things go wrong
-
grading the current status of the project
-
exercising total control over the project
-
auditing, learning from mistakes, and reporting progress and status
Question 185
Question
The project plan must be designed in such a way that the project outcome meets
__________.
Answer
-
unauthorized requests for change in the project outcome
-
the objectives of the parent organization
-
only the expressed warranties identified in the contract
-
the requirements associated with scope creep
Question 186
Question
The Project Launch Meeting occurs when?
Answer
-
Prior to beginning the project to show management commitment
-
When the Project is completed and ready to send to the client.
-
When the client has accepted the Project and is ready to finalize payment
-
When the project is fully designed and ready to begin implementation.
Question 187
Question
Managing complex projects often involves use of multidisciplinary teams (MTs)
including personnel from
Answer
-
various combinations of college majors, work units, subcontractors, and
industry partners
-
different organizations including subcontractors.
-
different work units within the organization
-
different college majors.
Question 188
Question
The __________ is a specialized view of the action plan that focuses on who has what
responsibility for each project task
Question 189
Question
Agile project planning and management methods should be used when?
Answer
-
Project managers are well-qualified for many types of projects
-
Project team members are cross-trained and therefore are agile.
-
The project scope and costs are undefined.
-
Projects have a high degree of uncertainty
Question 190
Question
Risk management’s primary focus is on what type of activities?
Answer
-
Minimizing workforce injuries
-
Protecting the firm’s money/profitability
-
Keeping the organization’s problems from appearing in the local newspapers
-
Complex coordination of planning, risk identification, risk analysis, response
planning, monitoring & control, and recording of incidents.
Question 191
Question
According to the authors, any project must contain all of the following EXCEPT
Answer
-
evaluation methods
-
contractual aspects
-
resources
-
a ‘ballpark’ estimate
Question 192
Question
This project plan element describes both the managerial and the technical approaches
to the work as a whole.
Answer
-
schedule
-
overview
-
objectives
-
contractual aspects
Question 193
Question
Risk management today is
Answer
-
involves only simple steps to minimize uncertainty
-
relatively uncommon in project management
-
reported to be practiced by over 71% of organizations.
-
practiced only by a few very large corporations
Question 194
Question
Agile IT project teams are typically __________ and located at __________.
Answer
-
small, a single site
-
large, a single site
-
small, multiple sites
-
large, multiple sites
Question 195
Question
This project plan element should include profit and competitive goals as well as
technical goals.
Answer
-
overview
-
contractual aspects
-
objectives
-
general approach
Question 196
Question
The success of the project launch meeting is dependent on the existence of
Answer
-
project planning templates
-
the project's scope statement
-
a well-defined set of objectives for the project
-
Presence of the client
Question 197
Question
In a WBS each hierarchical level should have about how many interrelated tasks?
Answer
-
2 to 20
-
10 to 20
-
5 to 10
-
About 3 to 5
Question 198
Question
Project success is judged by what criteria?
Answer
-
On-time & on budget
-
On budget & to scope
-
On time, within budget, to scope, and project impact on the organization.
-
To scope & impact on the organization
Question 199
Question
What is the RACI Matrix?
Answer
-
Recently Added Control Incident reporting matrix.
-
Matrix of Responsible and Certified Individuals
-
Resource Allocation & Cost Inventory matrix
-
Responsible, Accountable, Consult & Inform matrix
Question 200
Question
The __________is a list of the project activities with major activities broken down into
subactivities.