Suggested BIM uses for tender phase (for contractor) are:
Answer
  • Cost Estimation

  • Site Planning (Logistic Planning)

Question 2

Question
Suggested BIM uses for Pre-Construction phase (for contractor) are:
Answer
  • Reviewing Consultant Models

  • Model-based Project Planning and Scheduling

Question 3

Question
Suggested BIM uses for Construction phase (for contractor) are:
Answer
  • Construction Coordination

  • Modelling and Shop Drawings

  • Sequence Complex Construction
  • Setting Out and Verification on Site
  • Prefabrication
 Proposal
  • As-Built models

  • Model for Facility Management

Question 4

Question
The contractor use site model to
Answer
  • Model the site topography
  • Add hoardings along the boundary 
with site access (gates)
  • Plan and model construction access and 
pedestrian access inside the site
  • Model the site offices, storage areas and utilities
  • Plan the vehicle movements and mobile crane movements
  • Plan locations of Tower Cranes

Question 5

Question
Once the site plan model is developed, the main contractor could communicate the site plan to his sub-contractors/workers using: 3D model walk-through 4D simulations or animation videos
Answer
  • True
  • False
Show full summary Hide full summary

Similar

'Of Mice and Men' - John Steinbeck
cian.buckley
Blood Brothers (Characters)
nuhaheza
Memory Key words
Sammy :P
The Cone-Gatherers Quotes
shona.doyle10
CHEMISTRY C1 6
x_clairey_x
Themes in Macbeth
annasc0tt
Physical Description
Mónica Rodríguez
Edexcel Additional Science Chemistry Topics 1+2
Amy Lashkari
Chemistry revision
Jordyn Niu
Système circulatoire sanguin
Martin Fortier
GCSE Computer Science (AQA)
Wolfie Ruth