Chapter 2 Joseph Study Guide

. 25 Fragen

Quiz starten

Fragen in diesem Quiz (25)

  1. 11. You are the project manager for the application deployment project. This project will deploy software to 450 sites throughout North America and in Europe. You’re working with several stakeholders to define the phases of the project life cycle, but some of the stakeholders are confused with the concept of the project life cycle. The project life cycle comprises which of the following?
    1. AA. Phases
    2. BB. Milestones
    3. CC. Estimates
    4. DD. Activities
  2. 2 2. Marcy, the project manager for the ERP Project, is about to complete the project phase review. The completion of a project phase is also known as which of the following?
    1. AA. A lesson learned
    2. BB. A kill point
    3. CC. Earned value management
    4. DD. Conditional advancement
  3. 3 3. You are the project manager of the NHQ Project. Your project team consists of experts from different companies and contractors from around the world. What type of project team is this?
    1. AA. Virtual
    2. BB. Partnership
    3. CC. Noncollocated
    4. DD. Dedicated
  4. 4 4. Beth is a new project manager for her company and she’s working with her project team to develop the project management plan. Beth knows that she must rely on several different skills to make her first project successful. Of the following management skills, which will a project manager use most?
    1. AA. Leading
    2. BB. Communicating
    3. CC. Influencing the organization
    4. DD. Negotiating
  5. 5 5. Harold is the manager of the manufacturing unit for your company, and he’ll be a key stakeholder on your upcoming project. To get to know Harold better, you’re having lunch with him and discussing some of the goals of the upcoming project. Harold doesn’t quite understand what you do as a project manager, so you explain the concept to him. Managing a project is best described as which one of the following?
    1. AA. Establishing direction
    2. BB. Functionally controlling the project team and stakeholders
    3. CC. Consistently producing key results expected by stakeholders
    4. DD. Motivating and inspiring the project team to produce results that are expected by project stakeholders
  6. 6 6. You are the project manager of the Server Deployment Project for your company. You’re meeting with the key stakeholders to gather the requirements and review the intent of the project. You know that you’ll have to meet with the stakeholders throughout the project and their influence can help or hinder the project’s success. When will stakeholders have the most influence over a project’s product?
    1. AA. At the end of the project
    2. BB. During scope verification
    3. CC. At the start of a project
    4. DD. At the start of each phase
  7. 7 7. A construction project is allowing the multiple phases of the project to overlap to save time and money, and to allow for better resource utilization. What type of phase relationships are being employed in this scenario?
    1. AA. Overlapping phase relationships
    2. BB. Sequential phase relationships
    3. CC. Start-to-start phase relationships
    4. DD. Finish-to-start phase relationships
  8. 8 8. You are the project manager for your organization. Influencing your organization requires which of the following?
    1. AA. An understanding of the organizational budget
    2. BB. Research and documentation of proven business cases
    3. CC. An understanding of formal and informal organizational structures
    4. DD. Positional power
  9. 9 9. Your global project is sabotaged by rumors and gossip about the project deliverable. This is an example of which of the following?
    1. AA. Cultural achievability
    2. BB. Cultural influences within the project team
    3. CC. Project team mutiny
    4. DD. Ineffective planning
  10. 1010. Bob is the project manager of a project for a company that manufactures pharmaceuticals. In Bob’s industry, many standards and regulations affect his projects. What is the difference between a standard and a regulation?
    1. AA. Standards are mandatory; regulations are not.
    2. BB. Standards are optional; regulations are not.
    3. CC. Regulations and standards are essentially the same.
    4. DD. Regulations are usually mandatory; standards may be seen as guidelines.

Informationen

Beschreibung
CIS 4375 Quiz am Chapter 2 Joseph Study Guide, erstellt von . . am 13/09/2017.
Autor
. .
Sprache
English
Aufrufe
13
Schlagwörter
cis 4375
Bewertung
Noch keine Bewertungen
Bewerte dieses Quiz
Bewerte dieses Quiz

Feedback

Worum geht es?

Wie gefällt dir das neue Design?

Dein Eindruck