  1. 1In a two pipe central heating system:
    1. Aa. The flow and return water mixes
    2. Bb. The flow and return water is kept separate
    3. Cc. The flow and return water is at the same temperature
    4. Dd. The flow water is at a lower temperature than the return water.
  2. 2The boiler position can be higher than the hot water cylinder in a:
    1. Aa. System with microbore heating with gravity primaries
    2. Bb. Combined hot water and heating system with vented primaries
    3. Cc. One pipe gravity system
    4. Dd. Fully pumped sealed system.
  3. 3This symbol from BS 1192 indicates a central heating component. Where in a central heating system would this be found?Bild zu Frage 3
    1. Aa. Cold feed from the feed and expansion cistern
    2. Bb. The primary flow to the hot water cylinder
    3. Cc. Immediately after the circulator and before the zone valve
    4. Dd.On a sealed system filling loop.
  4. 4Which of the following components could be fitted with a remote sensor?
    1. Aa. A thermostatic radiator valve
    2. Bb.A kickboard convector heater
    3. Cc. A diverter valve
    4. Dd.A two port zone valve.
  5. 5Which one of the following components allows the customer independent control of
    the hot water and central heating system?
    1. Aa. Room thermostat
    2. Bb. Cylinder thermostat
    3. Cc.Programmer
    4. Dd. Three port mid-position valve.
  6. 6Which of the following assists in the removal of flux from central heating pipework?
    1. Aa.Adding an inhibitor to the system after commissioning
    2. Bb.Setting the working temperature of the system to a maximum of 650 oC
    3. Cc. Flushing the system out prior to the handover
    4. Dd.Setting the circulator to maximum for 1 hour after soundness testing.
  7. 7The steps to take prior to temporarily decommissioning a central heating system,
    so that an additional radiator can be installed, would include:
    1. Aa. Check for safe isolation of central heating system, then drain down
    2. Bb.Switch off programmer so there is no call for heat, then drain down
    3. Cc. Apply temporary continuity bonding to system, then drain down
    4. Dd.Bung F&E and apply temporary continuity bonding to flow and return pipework.
  8. 8The customer complains that the downstairs radiators are cold and the upstairs
    radiators are only lukewarm. This is likely to be caused by a faulty:
    1. Aa.Boiler
    2. Bb. Three port mid-position valve
    3. Cc. Room thermostat
    4. Dd.Circulator.
  9. 9. Hot water circulates to each radiator by gravity in which of the following systems?
    1. Aa. One pipe system
    2. Bb. Fully pumped system
    3. Cc. Microbore system
    4. Dd. Two pipe reverse system.
  10. 10A zone valve in an S plan central heating system is designed to:
    1. Aa.Allow the central heating system never to reach 1000 oC
    2. Bb.Stop the circulator noise from entering the central heating system
    3. Cc. Isolate the central heating circuit when there is no demand
    4. Dd.Prevent the flow and return waters from mixing.

Informationen

Beschreibung
Unit 208: Central heating systems Sample questions
Sprache
English
Aufrufe
3.933
Bewertung
Noch keine Bewertungen
Bewerte dieses Quiz
Bewerte dieses Quiz

Feedback

Worum geht es?

Wie gefällt dir das neue Design?

Dein Eindruck