  1. 1You are the project manager for a system upgrade project. The practice at your company is to estimate project cost based on historical data and statistical analysis. This cost estimation technique is called?
    1. Aa. Analogous estimating.
    2. Bb. Button-up estimating.
    3. Cc. Parametric estimating.
    4. Dd. Risk based estimating.
  2. 2Which of the following represents processes concerned with establishing and controlling the cost baseline??
    1. Aa. Plan Resource and Contain cost.
    2. Bb. Estimate Costs, Develop Budget and Adhere to Baseline.
    3. Cc. Determine Budget and Control Costs.
    4. Dd. Resource Planning, Cost Estimating, and Cost Control
  3. 3The Cost Performance Baseline is a time phased budget and is used as a basis to measure, monitor and control overall cost performance of the project. It is usually displayed in the form of:?
    1. Aa. A Z curve
    2. Bb. An inverted S curve
    3. Cc. Pie-chart
    4. Dd. An S-curve
  4. 4Which of the following process sequences is correct?:?
    1. Aa. Create WBS, then Determine Budget, then Estimate Costs
    2. Bb. Create WBS, then Estimate Costs, then Determine Budget
    3. Cc. Determine Budget, then Estimate Costs, then Create WBS.
    4. Dd. Estimate Costs, then Determine Budget, then Create WBS.
  5. 5The project planning is progressing. The team is using historical data and expert opinion to attempt to get a total price for the project. This process is known as what?
    1. Aa. Analogous estimating
    2. Bb. Determine Budget
    3. Cc. Estimate Costs
    4. Dd. Control Cost
  6. 6The value of all work that has been completed so far is:?
    1. Aa. Earned value.
    2. Bb. Estimate at complete.
    3. Cc. Actual cost.
    4. Dd. Planned value.
  7. 7Which of the following metrics would tell the Project Manager the status of the schedule on a project??
    1. Aa. Cost Variance (CV)
    2. Bb. Budget at Completion (BAC)
    3. Cc. Schedule Performance Index (SPI)
    4. Dd. Cost Performance Index (CPI)
  8. 8You are managing a project that is part of a large construction program. During the execution of your project you are alerted that the construction of a foundation is expected to experience a serious cost overrun. What would be your FIRST course of action?
    1. Aa. Evaluate the cause and size of the overrun.
    2. Bb. Stop execution until the problem is solved.
    3. Cc. Contact the program manager to see if additional funds may be released.
    4. Dd. Determine if you have sufficient budget reserves to cover the cost overrun.
  9. 9Your schedule analysis has shown that your project has a high likelihood of experiencing a schedule overrun. You know this because the cumulative EV is much:?
    1. Aa. Higher than the cumulative AC.
    2. Bb. Higher than the cumulative PV.
    3. Cc. Lower than the cumulative PV.
    4. Dd. Lower than the cumulative CPI.
  10. 10The warehouse expansion project is in the middle of planning when the Project Manager presents a status reporting method to the team. It’s called Earned Value Technique. To attain buy-in from the team, the Project Manager begins to explain what Earned Value status reporting can do for the project, explaining that it will measure which of the following:
    1. Aa. Time and Cost
    2. Bb. Scope, Time, and Cost
    3. Cc. Scope and Cost
    4. Dd. Scope and Time

Informationen

Beschreibung
Cos 2
Sprache
Español
Aufrufe
45
Schlagwörter
cos 2avza
Bewertung
Noch keine Bewertungen
Bewerte dieses Quiz
Bewerte dieses Quiz

Feedback

Worum geht es?

Wie gefällt dir das neue Design?

Dein Eindruck