PMP exam 1

Lê Hiếu 100 Fragen

Quiz starten

Fragen in diesem Quiz (100)

  1. 1A project manager is assigned to a new marketing campaign The sponsor gives the project manager an approved project management plan for review and explains the scope, business requirements, deliverables and stakeholders The project manager asks to see the project charter to gain a better understanding of the project.
    The sponsor says the project is small and simple so there is no need for a project charter. What should the project manager do?
    1. ASpeak with peers about the need for a project charter
    2. BDevelop the project charter and send it for approval
    3. CExplain that a project charter is necessary to ensure agreement on scope and deliverables and to define the project manager's responsibilities
    4. DAgree that the project does not require a project charter, especially since the deliverables and milestones are included in the project management plan
  2. 2A company is transitioning from a predictive to an agile approach. During the last two sprint reviews, the product owner complained about the development team, indicating that the increments do not meet the acceptance criteria defined in the user stories. The development team complained about the product owner, who is defining sprint backlog items, because the backlog items cannot be delivered during the 2-week sprints agreed to at the beginning of the project.
    How should the project manager resolve this situation in their new role as servant leader?
    1. AReview the organizational process assets (OPAs) to find similar situations and review the resolution actions taken
    2. BRequest that the team use the next sprint to complete all technical debt remaining from the previous sprints
    3. CExtend the sprints to 3 weeks to allow the work requested by the product owner to be completed
    4. DEncourage the whole team to be empowered and accountable for the decisions made according to their roles
  3. 3project manager for a defense software application has a culturally and gender-diverse team with a short project time line Considering the project will be stressful what skill should the project manager use to monitor the team's performance?
    1. ACoercion
    2. BConflict resolution
    3. CEmotional intelligence
    4. DNegotiating
  4. 4During the execution of a project the project manager notices that only one team member has one of the technical skills needed to build the product The project manager is afraid this might have a future impact on the quality and schedule because most of the upcoming activities will require at least three people with this specific skill.
    What two actions should the project manager take to prevent the team from being unqualified? (Choose two)
    1. AExclude the activities from the roadmap
    2. BEncourage working in pairs and knowledge sharing
    3. CTeach the entire team the new skill.
    4. DFacilitate a training event with an external trainer
    5. EIncrease the time estimates on the activities that require such abilities
  5. 5A project manager has been selected to deliver one of an organization's key flagship solutions Critical success factors include agility, market adaptation, and a quick response to market offerings What is one of the key activities that the project manager should undertake to ensure company success?
    1. AReview the project objectives with the project sponsor to agree on more realistic and achievable project plans and deliverables
    2. BRequest more funding from the project sponsor to hire additional skilled resources and to incorporate additional quality in the project delivery approach and outcome
    3. CConduct periodical reviews of the project plans, objectives, and deliverables to ensure all relevant data are captured to continue making informed project decisions
    4. DCreate a business case after performing a market review, and then submit it to the sponsor to modify the project deliverable to meet the newly defined objectives
  6. 6A labor union contract negotiation is delaying the completion of a project to build a new manufacturing plant. Because the labor contract was due for renewal this year, the project manager documented the negotiation process as a risk to the project. The project was about to start the first phase of equipment installation at the plant when the negotiation began.
    How should the project manager address the situation?
    1. AMeet with the project team to determine options for risk mitigation.
    2. BLog the issue and follow the planned actions in the risk response plan.
    3. CAcquire contract resources and submit a change request for the cost impact.
    4. DEscalate the issue to the steering committee to ask for mitigation support.
  7. 7A project manager has just finished initiating a project. While planning the project manager notes that several essential team members do not have the required skills for key tasks later in the project.
    What should the project manager do first?
    1. ADevelop the resource management plan and ensure adequate training
    2. BReplace the current project team members
    3. COutsource the task to be completed by a specialized vendor
    4. DUpdate the issue log to account for the lack of team member qualifications
  8. 8During the implementation phase of a construction project, a key supplier went bankrupt and cannot supply the contracted material. This issue could affect the project schedule What should the project manager do first?
    1. AUpdate the issue log and act to minimize the impact
    2. BUpdate the schedule to include the delay
    3. CAdd the risk and the delay to the risk register
    4. DEscalate to the management team for delay approval
  9. 9A software project using an agile approach is facing quality issues with every release, generating many production problems. What should the project manager do to fix the problem and improve the quality?
    1. ASeek extra funding approval with the sponsor to replace junior team members for more experienced ones
    2. BCreate a reward system granting incentives to the team members who are able to catch more defects
    3. CHire an external company to add an additional layer of testing, making sure that the final product is well inspected before releasing.
    4. DUse the retrospective meeting to better understand the root cause of the quality problems and put together a plan with the team to address the problems
  10. 10During the execution phase of a healthcare IT project, the project manager finds one stakeholder is very difficult to communicate with and obtain feedback from on project deliverables. What should the project manager do?
    1. AShare a template the stakeholder to receive feedback on deliverables.
    2. BAsk the project sponsor to arrange a meeting the stakeholder.
    3. CUse networking skills to approach the stakeholder.
    4. DUpdate the stakeholder engagement plan for the stakeholder.

Informationen

Beschreibung
Công nghệ số Quiz am PMP exam 1, erstellt von Lê Hiếu am 12/07/2022.
Sprache
English
Aufrufe
98
Schlagwörter
công nghệ số
Bewertung
Noch keine Bewertungen
Bewerte dieses Quiz
Bewerte dieses Quiz

Feedback

Worum geht es?

Was sollen wir als Nächstes hinzufügen?