- 15.9.1 concrete shall be ____ from mixer to place of final deposit by methods that will prevent _____ or loss of materials.Conveyed, separation
- 25.10 concreting shall be carried on at such a rate that concrete is at all times ____ and flows readily into spaces between ______.plastic,reinforcement
- 35.11 concrete shall be maintained above ____ and in a moist condition for at least the first ____ after placement.50ºf, 7 days