MAN 241; CHAPTER 4

Peggy Torres Englisch 35 Karten

Karten in diesem Stapel (35)

  1. 1What is a project charter?An informal contract between the project team and the sponsor (who represents senior mgmt. and the customer)
  2. 2How is charter like a contract?An agreement entered into freely by two or more parties; one party cannot arbitrarily change it; something of value for each party, a living document
  3. 3Explain a living document?This can evolve with changing conditions if both parties agree and receive value from the change
  4. 4The project charter is a deliverable that grants the project team...The right to a detailed planning stage of a project
  5. 5Like a contract, the people who sign a charter are wise to ensure...They understand & agree to every detail within it
  6. 6Unlike a contract, both parties feel...Obligated to the spirit of the charter regardless of change
  7. 7Name the 4 major purposes for a charter?Authorize the PM to proceed; Help the project team & sponsor develop a common understanding; to commit, to screen out poor projects
  8. 8What additional benefits can occur once a common understanding is achieved?Teamwork, Agreement, Trust, Commitment, Communication, No worry over Mgmt accepting decisions, Sponsor less likely to unilaterally change original agreement
  9. 9What is another name for project charter?Project request; project submission form; project preplanning form
  10. 10The scope overview is also considered the...Elevator speech; to describe their project
  11. 11What is the product scope?The features & functions that characterize a product, service or result
  12. 12What is requirements?A condition or capability that must be met to satisfy needs, wants & expectations of the stakeholder
  13. 13What is project scope?How the work is performed to deliver a product, service or result
  14. 14What is scope creep?Adding features & functionality w/o addressing the effects of time, costs, resources or w/o customer approval
  15. 15What does the business case answer?The question "why" & helps all parties understand the purpose of the project
  16. 16What is background?More details about the project
  17. 17What is a milestone schedule?A summary level schedule that identifies the major milestones or significant points in a project
  18. 18What is a deliverable?Any unique & verifiable product, result or capability used to perform a service that must be produced to complete a phase, process or project
  19. 19What is acceptance criteria?Criteria, including performance requirements & acceptable conditions that must be met before project deliverables are accepted
  20. 20Acceptance criteria are like...The project's vital signs
  21. 21What is a risk?An uncertain event or condition that has a positive or negative effect on a project's objectives
  22. 22What are assumptions?Factors for planning purposes that are true, real or certain w/o proof or demonstration
  23. 23What is a constraint?An applicable restriction or limitation, either internal or external, that will affect the performance of the project
  24. 24Name 3 reasons managers should look at risks1. May inhibit successful completion; a plan is developed to overcome it
  25. 25Name 3 reasons why managers look at risks2. One that creates a positive effect; a plan is made to capitalize upon it
  26. 26Name 3 reasons why managers look at risks3. Would there be more risk to the organization for not completing the project?
  27. 27Why are team operating principles established?To enhance team functioning
  28. 28What is "lessons learned"?The learning gained from the process of performing the project
  29. 29What type of commitment do the signatures signify on a charter?Formal
  30. 30Name the 6 steps in constructing a milestone schedule1. Briefly describe the current situation that requires the project in 3-4 words; in the first row of the column
  31. 31Name the 6 steps in constructing a milestone schedule2. Describe the project at its successful completion in 3-4 words; in last row of column
  32. 32Name the 6 steps in constructing a milestone schedule3. Describe the acceptance criteria for the final deliverable; in the bottom row of the 3rd & 4th column
  33. 33Name the 6 steps in constructing a milestone schedule4. Determine key points where quality needs verification
  34. 34Name the 6 steps in constructing a milestone schedule5. Determine who the primary stakeholder is for each milestone and how they will judge the deliverable
  35. 35Name the 6 steps in constructing a milestone schedule6. Determine expected completion dates for each milestone

Informationen

Beschreibung
Karteikarten am MAN 241; CHAPTER 4, erstellt von Peggy Torres am 05/12/2013.
Erstellt von
Peggy Torres
Aufrufe
33
Tags
steven rothenberg
Bewertung

Mehr zu Project Selection and Initiation

Feedback

Worum geht es?

Wie gefällt dir das neue Design?

Dein Eindruck