- 1COLUMN FORMWORK Check starter bars length and position Clear and scabble concrete surface
Remove debris
Mark and check grid line
Check position of column, note orientation and offsets
Formwork joiner positions formwork for kicker accurately
Height of kicker formwork between 40 – 60 mm up-stand
Pour and cast kicker
Following day, strike kicker formwork
Check kicker position
Tie reinforcement cage to starter bars
Position spacers
Crane formwork into position
Locate around reinforcement and kicker
Ensure face of formwork is properly butted up to kicker without obstruction
Bolt formwork together Clamp and tie in position, Prop, adjust props and recheck structure and line
Releasing agent
Pour and vibrate concrete
Adjust props if necessary
Allow to cure and set for 1-3 days depending on concrete design
and structural engineers advice
Strike formwork
Clean formwork
- 2TABLE FORMWORK Unload table formwork. Assemble on site so that the table formwork is at the desired height and suits the proposed
construction (approximate height and position)
Position tables correctly and butt up ready for joining together
Adjust the secondary bearers and supports to enable the tables to be joined together with overlapping decking
Adjust the height of the tables
Use marine or similar quality plywood as decking material
Fit the decking material to the locating timber within the secondary bearers
Fit tables and decking up to and around columns and walls, seal any gaps with compressible tap (draft seal). Tape and seal joints as necessary & edge formwork
Apply mould oil or release agent
Assemble two layers of reinforcement matting with spacers and attach starter bars to reinforcement matt
Pour and vibrate the concrete
Adjust props
Pour and vibrate concrete
Allow to cure for 7-14 days
Strike formwork
Leave secondary props and drop head props in position to allow
for concrete to achieve its 14 or 28 days design strength.
Informationen
- Beschreibung
- Level 5 NDC (NDC) Karteikarten am NDC Formwork / Concrete, erstellt von Mathew Morgan am 05/01/2020.
- Erstellt von
- Mathew Morgan · Jan 2020
- Aktualisiert
- 5 Jan 2020
- Aufrufe
- 4
- Bewertung