Planning Cost

cesarau.garcia.c Spanisch

Inhalt der Mindmap

Planning Cost

  1. Plan Cost Management

    • IP:3, I:4, T&T:3
    • M: Guidence and direction
    • Input
      • Project Management Plan (Scope and Schedule Baselines)
      • Project Charter (Summary Budget, Approval Rrequirements)
      • EEF/OPA: Structure, market conditions, exchange rates, PMIS, financial database, control procedures
    • Output: Cost Management Plan
      • 1. Units of measure
      • 2. Level of precision
      • 3. Level of accuracy
      • 4. Organizational procedures links (control account)
      • 5. Control thresholds (percentage deviations)
      • 6. Rules of performance measurement (EVM)
      • 7. Reporting formats
      • 8. Process descriptions
      • 9. Additional details (fluctuations)
  2. Estimate Cost

    • Input
      • CMP: method and level of accuracy
      • Scope Baseline
        • PSS: Indirect vs Direct Costs
        • Limited Budget
        • Contractual, legal
          • health
          • safety
          • Security
          • Environmental
          • license
          • permits
      • Human resource management plan (Rates)
      • Project Schedule (resource and their durations
      • Risk Register (negative risk event/potential opportunities
      • EEF/OPA: market conditions, published commercial information, standar costs
    • Output: Activity cost estimates (qualitative assessments of probable for all resources)
    • Output: Basis of estimates (how the costs estimates was derived)
      • Base
      • Assumptions
      • Constrains
      • Range
    • Output: Project documents updates
      • Risk register
    • M: Prediction of amount of cost
    • IP:6, I:7 T&T: 10
  3. Determine Budget

    • IP:8, I:9, T&T:5
    • M: Aggregating to establish an authorized cost baseline
    • Input
      • CMP: Manage & Control
      • Scope Baseline (funding constrains)
      • PS: activities, milestones, workpackages and control accounts to aggregate costs to the calendar periods
      • Resource calendars (resources costs ocer the duration)
      • OPA: budgeting, tools, reporting
      • Agreements (procurements products, services or results)
    • Output: Cost Baseline
      • Without Management reserves
    • Output: Project Funding Requirements
      • May include the source (s) of funding
    • Output: Project documents updates
      • Risk Register
      • Activity cost estimates
      • Project schedule

Informationen

Beschreibung
Mindmap am Planning Cost, erstellt von cesarau.garcia.c am 17/03/2015.
Erstellt von
cesarau.garcia.c
Aufrufe
0
Bewertung

Feedback

Worum geht es?

Wie gefällt dir das neue Design?

Dein Eindruck