SAB7#61 Schedule Types

Inhalt der Mindmap
SAB7#61 Schedule Types
Network Diagram
- Used to identify activity relations
- Aid to effectively planning, organizing and controlling the project
- Shows interdependencies
Milestones
- Shows only major events
- Have no duration
- Better for executive reports
Bar Chart (Gantt)
- Effective for tracking progress
- Effective for reporting and control
- Used to control detailed team work