GoConqr hat ein neues Design! Sag uns, wie es dir gefällt.

Mindmap

070_Control Costs

Alejandro Becerra Taller PMP PMP Credential Spanisch

070_Control Costs

Inhalt der Mindmap

070_Control Costs

  • In the exam, assume that the project manager is measuring, measuring, measuring on the project 
  1. It is all about knowing how you are doing compared to your plan and making adjustments when necessary

  2. Project funding requirements

  3. Project Management Plan

  4. Work Performance Data

  5. Orginizational Process Assets

  6. Earned value management

  7. Project Management Software

  8. Reserve Analysis

  9. To-complete performance index (TCPI)

  10. Performance Reviews

    • Earned Value Management
      • Integrates COST, TIME and the WORK DONE
      • PV - Planned Value
      • EV - Erned Value
      • AC - Actual Cost (total cost)
      • BAC - Budget at Completion
      • EAC - Estimate at Completion
      • ETC - Estimate to Complete
      • VAC - Variance at Completion
      • Formulas
        • CV -Cost Variance EV - AC
        • SV - Schedule Variance EV - PV
        • CPI - Cost Performance Index EV/AC
          • The CPI is a cumulative because it is using costs to date. It could be written as CPI(c)=EV(c)/AC(c)
        • SPI - Schedule Performance Index EV/PV
        • EAC Estimate at Completion
          • AC + Bottom-up ETC
          • BAC/CPI
          • AC+(BAC-EV)
          • AC+(bac-EV)/CPI(c)XSPI(c))
        • TCPI - To-Complete Performance Index (BAC-EV)/(BAC-AC)
        • ETC - Estimate to Complete EAC-AC
        • ETC - Estimate to Complete BAC-BAC
  11. Forecasting

  12. Work Performance Information

    • CV - Cost Variance
    • SV - Schedule Variance
    • CPI - Cost Performance Index
    • SPI - Schedule Performance Index
    • TCPI - To-Complete Performance Index
    • ETC - Estimate to Complete
    • ETC - Estimate to Complete
  13. Cost Forecast

  14. Change request

  15. Update Management Plan

  16. Update Project Documents

  17. Update OPA´s

  18. Progess Reporting

Bilder und Dateien der Mindmap

  • 070_Control Costs
  • 070_Control Costs
  • 070_Control Costs
  • 070_Control Costs

Informationen

Beschreibung
PMP Credential Taller PMP Mindmap am 070_Control Costs, erstellt von Alejandro Becerra am 05/03/2016.
Erstellt von
Alejandro Becerra · Mär 2016
Aktualisiert
6 Mär 2016
Aufrufe
0
Verlauf
  • Erstellt von Salvador Rueda · 5 Mär 2016
  • Kopiert von Alejandro Becerra · 5 Mär 2016
Bewertung

Feedback

Worum geht es?

Wie gefällt dir das neue Design?

Dein Eindruck