Mindmap
PRACTICE STANDARD FOR EARNED VALUE MANAGEMENT

Inhalt der Mindmap
PRACTICE STANDARD FOR EARNED VALUE MANAGEMENT
ANALYZE PROJECT PERFORMANCE
- INPUTS
- PROJECT MANAGEMENT PLAN
- WORK PERFORMANCE INFORMATION
- KEY DATA POINTS
- Planned Value
- Earned Value
- Actual Cost
- Budget At Completion
- KEY DATA POINTS
- DESCRIPTION
- IHIUGPU
- PERFORMANCE ANALYSIS
- Common variances
- SV
- CV
- Common indices
- SPI
- CVI
- TCPI
- SCHEDULE ANALYSIS
- Project is ahead of or behind schedule
- COST ANALYSIS
- Project is in an over-budget or under-budget
- Common variances
- FORECASTING
- Estimate to Complete
- The expected cost needed to complete all of the remaining work
- Estimate at Completion
- The expected total cost of a control account, work package, or the project
- Variance at Completion
- Shows whether the project is forecasted to fi nish under or over budget.
- To-Complete Performance Index
- It compares work completed to date with budget required to complete the remaining work
- Estimate to Complete
- PERCENTAGE COMPARISIONS
- Comparing
- the percent complete
- to the percent spent
- Comparing
- TREND ANALYSIS
- Can decipher or anticipate a potential performance problem
- OUTPUTS
- PERFORMANCE MEASUREMENT METHOD
- FUNDING FORECASTS AND TRENDS
- CORRECTIVE AND PREVENTIVE ACTIONS
- THE BICYCLE CASE STUDY
- ANALYZING OF DATA
- GRAPHICAL ANALYSIS OF DATA
- Graphical Display of PV, EV, and AC
- Graphical Display of At Completion Data and Forecasts
- Graphical Display Project Variances
- Graphical Display of Project Indices
- MAMNAGEMENT BY EXCEPTION AND VARIANCE ANALYSIS
- CONSIDERATIONS
- MANAGEMENT BY EXPECTION
- COMMUNICATION WITH EARN VALUE DATA
- TABLES
- BAR CHARTS
- CURBS
- DEFINITION
- THE PROCESS OF COMPARING ACTUAL PROJECT COST AND SCHEDULE PERFORMANCE TO THE PERFORMANCE MEASUREMENT BASELINE
- INPUTS
DETERMINE MEASUREMENT METHOD
- INPUTS
- STATEMENT OF WORK
- Description of products
- REQUIREMENTS DOCUMENTATION
- SCOPE BASELINE
- Approved version of a scope statement
- INTEGRATED MASTER SCHEDULE
- Planned dates for performing activities
- PROJECT BUDGET
- The time-phased distribution of funds for the planned work
- STATEMENT OF WORK
- DESCRIPTION
- DISCRETE EFFORT
- Methods
- FIXED FORMULA
- WEIGHTED MILESTONE
- PERCENT COMPLETE
- PHYSICAL MEASUREMENT
- Can be planned and measured and that yields a specific output.
- Methods
- APPORTIONED EFFORT
- Is estimated as a percentage of the referenced discrete work effort
- LEVEL OF EFFORT
- Activities do not directly produce defi nitive end products measureablies
- DISCRETE EFFORT
- OUTPUTS
- PERFORMANCE MEASUREMENT METHODS
- CONTROL ACCOUNT PLAN UPDATES
- CONSIDERATIONS
- SELECT THE METHOD
- Characteristics of work
- Duration and measurability
- Requirements
- Measurement units
- Hours, currency, and other measurable units
- Level of accuracy to measure
- Cost, schedule, and performance
- Risk
- Characteristics of work
- RULES OF MEASUREMENT
- MEASUREMENT OF PROCUREMENTS
- SELECT THE METHOD
- DEFINITION
- THE PROCESS TO SELECT THE APPROPRIATE METHOD OF PROGRESS EVALUATION FOR EACH WORK PACKAGE
- INPUTS
Bilder und Dateien der Mindmap
Informationen
- Beschreibung
- Mindmap am PRACTICE STANDARD FOR EARNED VALUE MANAGEMENT, erstellt von Carla Sotil Chauca am 09/06/2018.
- Erstellt von
- Carla Sotil Chauca
- Aufrufe
- 2
- Bewertung

















