GoConqr hat ein neues Design! Sag uns, wie es dir gefällt.

Mindmap

Project Governance and Scope Change Management

Ana Laura Salazar Englisch

Inhalt der Mindmap

Project Governance and Scope Change Management

  1. General Concepts

    • Project Scope Management
      • Defines project boundaries of what is included in the project deliverables required, and what is excluded
      • Required process that helps to ensure that the project includes all the work required to complete the project successfully.
      • Scope Management Plan
        • Documents the validation of the project scope and describes a definition of each aspect of the scope and how it will be controlled.
        • It is measured in order to identify deficiencies in performance which may occur in the execution of work
        • Determines and clarifies the deliverables of the project and provides a focused direction to allow the project manager to work towards the predefined goal and objectives.
      • Relationship
        • Three key areas need to be considered a properly governed scope management
          • Appropriate project organization structure is in place and formally documented
          • Decision-making body to be defined within the governance arrangements
          • Regulation of the quality of outputs
    • Project Governance
      • Use of systems, structures of authority, and processes to allocate resources and coordinate or control activity in a project
      • Good governance systems include
        • Aligning project goals with current strategic plan
        • Modifying strategic plan in response to changing circumstances
        • Monitoring performance of projects
        • Communicating these assurances as appropriate to external stakeholder
  2. KLIA 2

    • Main issues
      • Lack of project governance structure
        • No appropriate governance structure established to address the needs of the project and to oversee the performance of the project activities
      • Blurred Authority and Responsibilities
        • Lack of clarity of roles and responsibilities, as well as ownership of decision making within the project team and project setting, resulted in confusion.
      • Inadequate Assurance System
        • KLICS failed to exercise the optimum level of project oversight, leading to the failure of progress monitoring which subsequently caused project delays.
        • No clear guidelines on the statement of need, employer's requirements and concept drawings.

Informationen

Beschreibung
Mindmap am Project Governance and Scope Change Management, erstellt von Ana Laura Salazar am 01/08/2018.
Erstellt von
Ana Laura Salazar
Aufrufe
0
Bewertung

Mehr zu Control Scope

Feedback

Worum geht es?

Wie gefällt dir das neue Design?

Dein Eindruck