APC Q&A

  1. what documents would you include in a tender Doc?

    • http://www.designingbuildings.co.uk/wiki/tender_documentation_for_construction_projects
    • Specification & drawings
    • Form of tender
    • contact details
    • programme
    • return date
    • pricing document
    • codes of conduct for tendering
    • contents list
    • surveys and results
    • project background
  2. what constitutes a set of contract documents under D&B ?

    • http://www.designingbuildings.co.uk/wiki/contract_documents_for_construction
    • Employers requirements
    • project scope
      • schedule of work
    • client brief
    • type of contract
    • contract amendments
    • conditions of contract
    • pricing document
    • specification
  3. What documents would you include to safeguard clients interests?

    • insruances
    • bonds
      • performance
      • retention
    • collateral warranties
      • what are collateral warranties?
        • contract between third parties
        • standard transfer of risk
        • client - main contractor - sub-contractor
    • public liability
    • employers liability
  4. what amendments would you advise your client to make to a contract for a standard form and why?

    • to ensure both parties have their interests covered
    • retention
    • insurance particulars
    • contract particulars for the project
  5. What is the difference between fitness for purpose and reasonable skill and care?

    • FFP (FITTNESS FOR PURPOSE)
      • implied into construction contracts
        • Within a D&B contract stating the product will suit the purpose for the client needs
      • does the product do what is asked of it
    • RSC (REASONABLE SKILL AND CARE)
      • implied into professional services contracts
      • Bollum Test
      • a professional designer will have a duty to act with reasonable skill and care
  6. What is a RICS Guidance note?

    • a document that represents best practice
    • documents that provide users with recommendation towards reasonable skill and care
      • why are they important?
        • protect against an allegations of negligence
          • a member conforming to a guidance note shows works towards reasonable skill and care for best practice
  7. what are minimal requirements from a QS with tendering

    • take initial brief from employer to understand requirements
    • choose suitable tendering statergy
    • produce and issue invites to tender in appropriate manner
    • deal with tender queries and answer them in timely manner
    • analysis tenders- collate queries from design team
    • produce tender report with recommendations of preferred contractor
  8. What is procurement?

    • Overall act of obtaining good and services from an external source
    • Time
      • programme, key dates, time line, critical path
    • cost
      • budget, value engineering, added value
    • quality
      • performance, FFP, risks
    • Traditional
    • Design and build
    • Construction Management
    • Management Contracting
  9. What is tendering?

    • the bidding process to obtain a price
    • how the contractor is appointed
    • Single stage tendering
      • most common type where competing contractors all given chance to bid on identical tender docs
    • Two Stage tendering
      • enables design and tendering to be overlapped
      • contractor can input to the technical design
      • used for early appointment of the contractor
      • tendered on prelims, OH&P, reputation, design and relevant experiance
      • RIBA stage 2 or 3
  10. What is meant by time at large

    • no date fixed by the contract for completion
    • contractor is required to complete the work in a reasonable time
    • no provision for EOT in contract when employer has caused delay
  11. what is force majeure

    • where act of god, strikes and breakdowns amount to force majeure
    • in absence of definition in contract, there is no formal meaning

Informationen

Beschreibung
Mindmap am APC Q&A, erstellt von Fred Fulford am 16/02/2015.
Erstellt von
Fred Fulford
Aufrufe
64
Bewertung
Durchschnittliche Bewertung 2,0 von 5 (1 Bewertung)

Feedback

Worum geht es?

Wie gefällt dir das neue Design?

Dein Eindruck