SAB4#63_Network Diagram Analysis

Beschreibung

Mindmap am SAB4#63_Network Diagram Analysis, erstellt von pmpcertificacion am 21/02/2015.
pmpcertificacion
Mindmap von pmpcertificacion, aktualisiert more than 1 year ago
pmpcertificacion
Erstellt von pmpcertificacion vor etwa 9 Jahre
17
0

Zusammenfassung der Ressource

SAB4#63_Network Diagram Analysis
  1. Critical path metod

    Anmerkungen:

    • Involves determining the longest path through the network diagram, the earliest and latest activity can star, and the earliest and latest it can be completed.
    1. Critical path

      Anmerkungen:

      • Is the longest duration path through a network diagram an determines the shortest time it could take to complete the project.
      • The aesiest way to find the critical path is to identify all paths through the network and add the activity durations along each path.  The path with the longest duration is the critical path.
      1. Near critical path

        Anmerkungen:

        • This path is close in duration to the critical path.  Something could happen that shortnes the critical path or lengthens the near-critial path to the point where the near-critical path becomes critical.
        • The closer in length the near-critical an critical paths are, the more risk the project has.
      2. Float (slack)
        1. Total float

          Anmerkungen:

          • Is the amount of time an activity can be delayed without delaying the project end date or an intermediary milestone.
          1. Free float

            Anmerkungen:

            • This is the amount of time an activity can be delayed without delating the early start date of its succesor 
            1. Project float

              Anmerkungen:

              • Is the amount of time a project can be delayed without delaying the externally imposed project completion date required by the customer or management.
              1. Start formula

                Anmerkungen:

                • Float=LS-ES
                1. Finish formula

                  Anmerkungen:

                  • LF-EF
              2. Schedule compresion

                Anmerkungen:

                • During project planning, schedule compresion can help a project manager determine if the desired completion date can be met and, if not, what can de changed to meet the requested date.
                1. Fast tracking

                  Anmerkungen:

                  • Involves taking critical path activities that were originally planned in a series and doing them instead in parallel for some or all of their duration.
                  1. Crashing

                    Anmerkungen:

                    • Involves adding or adjunting resources in order to compress the schedule while mantaining the original project scope.
                    • Crashing, by definition, always results in increased costs and may increase risk.
                  2. Modeling

                    Anmerkungen:

                    • In creating a finalized, realistic schedule, it is helpful to ask "what if a particular factor changed on the project?  Would thah produce a shorter schedule?
                    • The assumptions for each activity can change and, therefore, the activity durations can also change.
                    1. Monte Carlo Analysis

                      Anmerkungen:

                      • This technique uses computer software to simulate the outcome of a project, based on the three-point estimates (optimistic, pessimistic, and most likely) for each activity and the network diagram.
                      • The simulation can tell you: 1.- The probability of completing the project on any specific day. 2.- The probabilty of completing the project for any specific cost. 3.- The probability of any activity actually being on the critical path. 4.- The overall project riks.
                    2. Resource optimiaztion

                      Anmerkungen:

                      • Refers to finding ways to adjust the use of resources.
                      1. Resource leveling

                        Anmerkungen:

                        • Is used to produce a resource-limited schedule.
                        1. Resource Smoothing

                          Anmerkungen:

                          • Is a modified form of resource leveling, where resources are leveled only within the limits of the float of ther activities.
                        2. Critical chain method

                          Anmerkungen:

                          • Uses a network diagram and critical path to develop a schedule by assigning each activity to occur as late as posible to still meet the end date.
                          • You add resource dependencies to the schedule and then calculate the critical chain. Starting at the end date, you buid buffers for ersource limitations and risks into the chain at critical milestones (risk response planning).
                          • These reserves, spread throughout the project, provide cushions for delays in the scheduled activities.  You manage these buffers so thah you meet each individual milestone date and thus the project milestone completion date as well.
                          Zusammenfassung anzeigen Zusammenfassung ausblenden

                          ähnlicher Inhalt

                          Proteinbiosynthese
                          Cornelius Ges
                          BKF C95 (Fragen der Ziffern 1a, 1b)
                          Harald Koenig
                          LB F, Kapitel 2, Grundbegriffe der Kosten- und Leistungsrechnung
                          Stefan Kurtenbach
                          Wortschatz Französisch 3. Gesundheit und Medizin
                          l_u_n_a_19
                          Lernplan Analysis
                          Hanna Marie Hock
                          Eriksons Modell psychosexueller und psychosozialer Entwicklung im Kindes-, Jugend- und Erwachsenenalter
                          Lena S.
                          KORRE - Megaprüfungsfragen
                          Martina Brunner
                          PuKW STEP6 - Hummel (Sofort überprüfbar)
                          Tim Schröder
                          SQ3- Sei dabei! :)
                          B G
                          GPSY ALPS (Lösung während dem bearbeiten sichtbar)
                          Mischa Kräutli
                          Veti Pharma 2013
                          Anna Leps