Mindmap
MMC vs Traditional

Mind map: MMC vs traditional construction
Inhalt der Mindmap
MMC vs Traditional
Value
- Not a question of lowest cost
- Need to maintain and increase quality
- Durability
- Life-time running costs
- Sustainability
- Speed (government requirements)
Labour savings
- Volumetric approach allows a quarter of on-site labour
- Greater saving available with different cladding
- Factory based production not the same labour pull as on-site construction
- Not competing for the same skills
- Volumetric approach allows a quarter of on-site labour
Time savings
- Can half the time on site
- Time to achieve water-tightness quartered
- Quality protected as no weather damage
- Improved working condidtions
- These saving are only available with the use of process plans tailored to match the method of construction and followed appropriately
Relationship with planning authorities
- Good relationship required to keep off-sire production off the critical path
- Otherwise on-site savings are replaced with off-site time
- Nullifies benefits of MMC
- Otherwise on-site savings are replaced with off-site time
- Manufacture needs to take place at point of outline planning permission
- During process required regardless of method
- Discussion before initial planning application, not after submission
- "Recommendation of approval" before formal approval
- Allows works to continue
- "Recommendation of approval" before formal approval
- Good relationship required to keep off-sire production off the critical path
Costs
- Baker Report (2004)
- "The time savings available do not currently provide a compelling financial reason to switch production"
- Generally MMC is more expensive
- Open panels are the exeption
- Cost competitive with traditional
- Open panels are the exeption
- Time benefits bridge a third of the gap
- Rent quicker
- Less snagging
- Higher quality control on factory
- More off-site construction means less on-site inspection
- Aim to build homes for £60 000
- £784 per square meter
- Achievable by MMC
- £784 per square meter
- For/Against MMC
- Favour MMC
- Poor soil conditions
- Restricted working space
- More storeys
- Rooms in roof
- Against MMC
- Late design changes
- No standard design
- Late appointment of contractor/supplier
- Need to suspend operations
- Favour MMC
- Baker Report (2004)
Capacity
- Most suppliers could cope with a doubling demand by using spare capacity
- Increase in demand would cause an increase in price
- Until more capacity became available
- Price would then go back down
- Until more capacity became available
Quality Issues
- Durability
- 60 years as standard
- Degradation same for all methods
- Off-site manufacture doesn't enhance duarbility
- Factory production should reduce risk of non-conformities
- Whole Life Costs
- The same for all methods
- May be less components failing early dud to factory production
- Perfmorance
- Will meet the standards
- Durability
Risk Management
- Different risks
- Not price fluctuations during construction
- Not delays due to bad weather
- Unpredictable planning
- Non-suitable design for MMC
- Risk higher earlier on
- Specific risks
- Late design changes
- Additional factory work is costly and causes delays
- Early involvement of supplier is vital
- Loss of factory production slot
- Finding a new slot can cause major delays
- Caused by
- Underestimating lead in times
- Drifting start dates
- Effective communication of key
- Suppliers failing to deliver on time
- Construction is stopped, other processes cannot proceed
- Therefore increase in time and money
- Effective supply chain managementrequired
- Ensure orders places in plenty of time
- Construction is stopped, other processes cannot proceed
- Late design changes
- Different risks
Informationen
- Beschreibung
- MMC v Traditional Construction
- Erstellt von
- ebrodie94
- Aufrufe
- 310
- Tags
- Bewertung