- The right order is: Make the Work Breakdown Structure first, and make the Activity List second
Identify deliverables and related work
- Organize the project based on how you work
- Make sure the team has enough information about the work package to get the job done
- Each work package has to be compact enough to make it easy to organize
- At the end of decomposition, you end up with a bunch of work packages that add up to the major deliverable.
- So you need to talk to the team. Are they satisfied that you’ve given them enough detail to do the job?
- Each work package has to be compact enough to make it easy to organize
- Then begin breaking down the project into smaller and smaller pieces.
- Make sure the team has enough information about the work package to get the job done
- Start with a major deliverable.
- Organize the project based on how you work
A WBS is a list of the components of the deliverable
An Activity List is a list of the activities we will engage in during the project.
The WBS has to do with WHAT the project, while the schedule has to do with HOW and WHEN
Bilder und Dateien der Mindmap
Informationen
- Beschreibung
- Mindmap am SAB8#57_List_Activities_vs_WBS, erstellt von Aldo Martínez Barret am 25/11/2015.
- Erstellt von
- Aldo Martínez Barret · Nov 2015
- Aktualisiert
- 11 Mai 2016
- Aufrufe
- 24
- Bewertung
Mehr zu Work Breakdown Structure