TC#68#69_Estimate_Cost_Determinate_Budget

Paulino Valladar Spanisch

Inhalt der Mindmap

TC#68#69_Estimate_Cost_Determinate_Budget

  1. Estimate cost

    • Involded all the efrorts needed to complete the projet
      • Costo of quality effort
      • Costo of Risk effort
      • Costo of project manager time
      • Cost of Project manager activities
      • Cost directly associated with the Project: labor, material, training, et.
      • Expenses of physical office space
      • profit
      • Overhead cost: management salaries, general offices
    • Types
      • Fixed
        • No change_ set up, rent etc.
      • Variable
        • Depende of amount of work or amount of production
      • Direct
        • Attributable to the work of project
      • indirect
        • overhead ítems or costs incurred for the benefit of more that one project
    • Cost Management Plan
    • Scope base line
    • Project Schedule
    • Human Resource Management Plan
    • Risk Register
    • OPAs
      • Policies and historical records related to stimating: templates,process, procedures, lessons learned, and historical information
    • EEFs
      • Company culture or Systems that the Project will be have to deal or can use
    • Project Management Cost
    • Buttom up
    • PMBOK
      • Knowledge Area: Cost Management
      • Process Group: Planning
      • Process: Estimate Cost
    • one point
    • Analogous
    • Parametric
    • three point
    • Using ...
      • Project Management Software
      • Resource cost rate
      • Reserve Analysis
        • Reserve
          • For unknown risks
        • Contingence
          • for knows risks
      • Cost of quality
      • Group desition Making
        • most likely to understand what`s involved in the efforts
      • Accuracy to Estimates
    • Ranges ***
      • Rough Order of Mafnitude (ROM)
        • On Project Initiating
        • -25% to 75%
      • Budget Estimate
        • During project planing
        • -10% to 25%
      • Definitive Estimate
        • +/-10% or -5 +10%
    • Plan Management Cost
      • Cost estimates
      • Delivery cost plan
  2. Determinate budget

    • PMBOK
      • Knowledge Area: Cost Management
      • Process Group: Planning
      • Process: Detrminate budget
    • Cost Managment Plan
    • Is total of cost needed to complete the project
    • Cost Base line
      • budget portion that the PM will have control over Include de funding requirements
    • Scope base line
    • Project Schedule
    • Risk Register
    • Cost Estimates
    • Basis of estimates
    • prerequisites ***
      • perform Risk Management activities
      • include reserves
      • include managment reserve
        • Additional funds to unforeseen risk
    • rollup cost package cost = Cost aggregation
      • 1. Totalize Cost Activity by Work Packagen= Work Package Estimate
      • 2. Totalize Work Package Cost by Control Account = Cotrol Account Estimate
      • 3. Totalize Control Accounts = Project Estimate
      • 4. Add Contingency Reserves = Cost Base line
      • 5. Add mangement reserves = Cost Budget
      • 6. Comparate to Parametric Estimate, Espert Judgment, historica record, etc. to sanity check
        • 7. Check constraint of project.

Informationen

Beschreibung
Mindmap am TC#68#69_Estimate_Cost_Determinate_Budget, erstellt von Paulino Valladar am 05/02/2016.
Erstellt von
Paulino Valladar
Aufrufe
4
Bewertung

Mehr zu Cost Estimation

Feedback

Worum geht es?

Wie gefällt dir das neue Design?

Dein Eindruck