- If you have to make a change to your project’s scope
2. Create a change request
3. Get the change approved.
1. Someone identifies that a change is needed
- Beacuse someone realizes that if the project sticks with the plan, then the outcome will lead to problems
Project Management Plan
Requirements traceability matrix
Requirements Documentation
Work Performance Data
Variance Analysis
- Analyzing the difference between the baseline and the actual work to figure out if the plan needs to be corrected
Work performance information
Updates to organizational process assets
Project document updates
Updates to the Project Management plan
4. Do variance analysis.
5 Replan the work
- Updates: Project Management Plan, WBS and Project Scope Statement
6. Create a new baseline