Prince 2 - Management Products
Folien in diesem Satz (8)
-
Management Products - Strategies
- Communication Management Strategy
- Outlines how the project will communicate with internal & external stakeholders
- Contains stakeholder analysis to identify who needs to be updated, when & how
- Project Manager completes during the Initiation Stage
- Forms part of the Project Initiation Documentation and may be updated at the end of each stage boundary
- Configuration Management Strategy
- Outlines how areas of the project will be managed including: changes to products, exceptions, issues and carrying out configuration management
- How the project will manage versions, storage & reporting status of products
- Quality Management Strategy
- Outlines how Project Management Team approach quality planning, control and assurance
- Ensures products are fit for purpose
- Project Manager creates during Initiation Stage and updates at the end of each stage during Managing a Stage Boundary
- Forms part of the Project Initiation Documentation
- Risk Management Strategy
- How the project will manage threats and opportunities
- Project Manager creates during Initiation Stage and forms part of Project Initiation Documentation
-
- Highlight Report
- Provides the Project Board with updates on stage progress
- Communication Management Strategy defines who should receive and how often
- Project Manager creates during Controlling a Stage
- Project Board reviews during Directing a Project
- Checkpoint Report
- Updates the Project Manager on the progress of the Work Package
- Work Package details how often these reports should be sent
- Team Manager creates report during Managing Product Delivery
- Project Manager reviews during Controlling a Stage
- Exception Report
- Report details the problem, options to resolve and recommendations
- Project Manager sends to Project Board if a breach is forecast
- Project Manager creates during Controlling a Stage
- Project Board during Directing a Project
- End Project Report
- Reviews project performance against its objectives outlined in the Project Initiation Documentation
- Project Manager create during Controlling a Project
- Project Board reviews when considering whether to authorise closure during Directing a Project
-
- End Stage Report
- Reviews the performance of a stage
- Project Manager creates during the Managing a Stage Boundary
- Project Board reviews when considering to authorise the next stage during Directing a Project
- Issue Report
- Details formal issues & contains description, impact assessment and recommendations
- Project Manager creates during Controlling a Stage
- Updated throughout the life of the issue
-
- Project Plan
- Shows the major products to be delivered for the entire project
- Project Manager creates during Initiation Stage and updates at the end of each stage
- Project Board monitors the progress during Directing a Project
- Stage Plan
- Details products to be delivered in a stage, activities & resources required with more detail in the Project Plan
- Project Manager creates Managing a Stage Boundary
- Project Board reviews when considering authorisation
- Project Manager monitors progress during Managing Product Delivery
-
Management Products - Logs & Registers
- Daily Log
- Records personal actions and informal issues
- Acts as a temporary register until Risk & Issue Registers are created during Initiation Stage
- Project Manager creates during Starting up a Project
- Issue Register
- Records issues throughout the project including:
- Request for Change
- Off-Specifications
- Problems or Concerns
- Project Manager creates during Initiation Stage and is responsible for monitoring and updating the register
- Lessons Log
- Records experiences from previous projects that may be useful
- Acts as a repository for current experiences which may be useful for future projects
- Project Manager creates during Starting up a Project and updates throughout the project
- Quality Register
- Quality activities that will take place. Registers show when checks happened, what was checked and results
- Work packages detail who completes checks
- Project Manager creates during Initiation Stage
- Updated with results during Managing Product Delivery
-
Management Products - Logs & Registers
- Configuration Item Record
- Status of a product: owner, who has copies, other products that need to be create or considered
- A new record is created for every product, component or group
- Can be created during project, stage, team or exception plans
- Project Manager creates and uses to track progress
- Product Status Account
- Current status on all or a sub-set of products
- Sourced from Configuration Item Records
- Project Manager creates throughout the project and feeds into the Highlight Report and End Stage Reports
- Risk Register
- Details threats and opportunities the project faces
- Records description, likelihood, impact and counter-measure
- Project Manager creates during Initiation Stage and is updated throughout the project
-
Management Products - Documents
- Business Case
- Business justification for the project
- Executive creates outline during Starting up a Project
- Project Manager adds detail during Initiation Stage
- Updated at each stage of Managing a Stage Boundary
- Key input to Project Board decisions
- Project Brief
- Defines and scopes the project (high level)
- Answers who, what, why, when, where, how
- Outlines business case and Project Product Description added
- Project Manager creates during Starting up a Project
- Project Board reviews when deciding whether to authorise Initiation Stage during Directing a Project
- Project Initiation Documentation
- Builds on the Project Brief to further define and scope
- Contains strategies to show how the project will be managed
- Project Manager creates during Initiation Stage and updates at the end of each stage
- Project Board reviews when authorising the next stage
- Product Descriptions
- Specifications for a product and shows measurable criteria that the product must conform to, quality methods, roles and responsibilities
- Project Manager liaises with end users to create
- Project Manager creates during the creation of an plan
-
Management Products - Documents
- Project Product Description
- Describes main output of the project and contains: customer quality expectations & measurable acceptance criteria
- Used when handing over deliverables at the end of each stage or project
- Project Manager, Senior User & Exec create during Starting up a Project
- Work Package
- Agreement between the Project Manager and Project Management Team delivering the specialist products
- Describes time and cost that products must be delivered to and details any tolerances
- Project Manager creates during Controlling a Project (authorisation)
- Team Manager accepts during Managing Product Delivery
Informationen
- Beschreibung
- Professional Prince 2 (Prince 2 Study Cards) Folienset am Prince 2 - Management Products, erstellt von Lynsey Dalgleish am 01/07/2016.
- Erstellt von
- Lynsey Dalgleish · Jul 2016
- Aktualisiert
- 9 Dez 2016
- Aufrufe
- 3
- Bewertung
Mehr zu PRINCE2 Framework and Structure