Chapter 3: Business Case Theme

Lynsey Dalgleish Prince 2 Professional Englisch 4 Folien

Folien in diesem Satz (4)

  1. Chapter 3: Business Case Theme

    • Theme sets up a series of mechanisms to ensure the project remains viable and achievable
    • Relationships between outputs, benefits & dis-benefit
    • Activities involved in developing, justification for the project, driving decision making and measuring returns
    • Management products include:
    • Business Case: Justification for the project
    • Benefits Review Plan: How to measure returns
    • "A project output is any of the projects specialist products. An outcome is the result of the change derived from using the projects outputs. A benefit is the measurable improvement resulting from an outcome that is perceived as an advantage. A dis-benefit is an outcome perceived as a negative by one or more stakeholders."
    • Outputs:
    • Things the project produces
    • Can be a number of specialist/management products e.g. BC/BRP
    • Outcomes:
    • The result of the change derived from using the projects outputs
    • Benefits:
    • A measurable improvement that results from the outcome
  2. Using the Business Case Theme

    • 1. Developing
    • Happens both before the project starts and during initiation stage
    • CPM creates project mandate which shows rationale for the project
    • Starting up a Project begins once the mandate is in place
    • Exec creates outline business case
    • Project Manager creates project plan in Initiation Stage
    • 2. Maintaining
    • Business case is reviewed and updated regularly
    • Project Manager updates at the end of each stage under Managing a Stage Boundary
    • Project Manager updates when creating an Exception Plan
    • 3. Verifying
    • Project Manager goes to Project Board for authorisation to move on to the next stage
    • Business case is the main item reviewed
    • 4. Confirming Benefits
    • Were the benefits achieved?
    • Benefits Review Plan shows planned reviews and is created during Initiation Stage and is updated at the end of each stage
    • Exec is responsible for creating and CPM manages post project benefit reviews
    • Senior user confirms benefits have happened
  3. Business Case - Contents

    • 1. Executive Summary
    • High level summary, aimed at snr stakeholders
    • 2. Reasons
    • Reason - something that has happened
    • Benefit - a forecast of something that will happen
    • 3. Business Options
    • How will meet the business challenge
    • Project approach details how the options will be delivered
    • 4. Expected Benefits
    • Ultimate aim of the project and measurable benefit
    • 5. Expected Dis-benefits
    • "an outcome that is perceived as negative by one or more project stakeholders"
    • Dis-benefits that have happened or will happen
    • Definite consequences of the project that will impact something or someone negatively
    • 6. Timescales
    • Period the project will run, when benefits will occur, what period benefits will be tracked etc
    • 7. Costs
    • Benefits need to be weighed against the cost of the project - project funding
    • 8. Major Risks
    • Evaluation of risks that will be taken on including major risks & risk exposure
    • 9. Investment Appraisal
    • Compares expected benefits with the project & costs
  4. Business Case Responsibilities

    • 1. Corporate or Programme Management (CPM)
    • Uses the project mandate to instigate the project
    • Appoints Exec who is responsible for Business Case
    • After project ends CPM is responsible for the BRP
    • 2. Executive
    • Responsible for the Business Case throughout the project
    • Ensures it demonstrates justification for project
    • Ensures benefits are delivered as specified in BRP
    • Once project ends role is complete
    • 3. Senior User
    • Forecasts benefits from project & demonstrating that the occur
    • 4. Project Manager
    • Creates & updates BC on behalf of exec
    • Manages risks and issues
    • 5. Senior Supplier
    • Focuses on supplier BC (if applicable)
    • Raises issues relating to delivery of products
    • 6. Project Assurance
    • Checks project is on track to deliver products
    • 7. Project Support
    • Admin, updating and tracking versions of BC

Informationen

Beschreibung
Professional Prince 2 (Prince 2 Study Cards) Folienset am Chapter 3: Business Case Theme , erstellt von Lynsey Dalgleish am 03/07/2016.
Erstellt von
Lynsey Dalgleish · Jul 2016
Aktualisiert
20 Dez 2016
Aufrufe
6
Bewertung

Feedback

Worum geht es?

Was sollen wir als Nächstes hinzufügen?