16. A likely result of fast tracking, in addition to hoped-for shortening of the project schedule, is:
- Aa. Fewer resources.
- Bb. Increased risk.
- Cc. Lower costs.
- Dd. Greater control.
25. PMBOK@ Guide states that the Estimate Resource process is 'closely coordinated with' the Estimate Costs process. The Course states that resource estimating cannot be done independently from a still different process. Which one is that?
- Aa. Sequence Activities.
- Bb. Estimate Durations.
- Cc. Plan Quality.
- Dd. Identify Risks.