Fragen in diesem Quiz (100)
1A project manager is assigned to a digital transformation project for a bank. The company culture is conservative and resistant to transformation or innovation. What should the project manager do first to support the transformation
- AProvide a digital transformation guide and explain that the change is unavoidable
- BAsk the bank executives to officially announce that the project manager is leading the project
- CProvide proper training sessions to the stakeholders so they understand the purpose of the change
- DHire an expert in digital transformation and assign that person as the champion for the change
2A project manager is establishing a project management office (PMO) for a company-wide program to implement a software based on artificial intelligence (AI). As part of the PMO tasks, some stakeholders need help understanding how to deal with difficult situations.
Which activity should the project manager use to help train the stakeholders?- AContract negotiation
- BTeam assessment
- CMentoring and coaching
- DOn-the-job training
3A project manager is managing a hybrid project A stakeholder has directly contacted a team member and has requested a change Due to the request, the team member was distracted from their work, which caused a loss in productivity.
What should the team member do?- AInform the stakeholder that the correct procedure for new requirements is to provide it directly to the project manager.
- BInform the scrum master regarding the stakeholder's request for a change and the impact this has had on productivity.
- CInform the stakeholder that the correct procedure for new requirements is to provide it directly to the change control board (CCB).
- DInform the scrum master so that the change can be discussed directly with the stakeholder.
4A project manager has recently been assigned to an agile project and discovers that a contractor for the project does not have any experience with agile. What should the project manager do?
- AAsk the project sponsor to replace the contractor since they do not have agile experience
- BIssue a formal notice to the contractor to obtain an agile certification
- CConsult the project team to understand the extent of the training needs for the contractor
- DInstruct the contractor to receive agile training since the project has already started
5A government agency is developing a new connectivity policy. The assigned project manager is a famous economist with international recognition. The team is eager to work with the project manager, but feels intimidated. The project manager realizes that a junior economist, whose tasks are behind schedule, is especially intimidated by the situation.
What should the project manager do first?- AEvaluate the performance of the junior economist in the upcoming months.
- BReassign some of the junior economist's tasks to other economists.
- CRequest to replace the junior economist with a more experienced economist.
- DConsider organizing paired work sessions for the junior and senior economists.
6In a construction project for a new building, the project manager decides to apply agile principles for the building foundation phase While evaluating the project schedule with the team, the project manager believes that the estimates are inaccurate. How should the project manager address this issue?
- ACreate a product backlog
- BPerform sprint reviews with the team
- CAssess the previous project velocity
- DReduce the story size by splitting stories
7A project manager has team members around the world in many different time zones Project work frequently stalls because people in one office need to wait until another office is awake to have questions answered.
What should the project manager have done to avoid this?- AUsed communication tools, such as video conferencing so different offices could communicate.
- BLearned more about how each team member prefers to communicate before assigning project work
- CPlanned and scheduled tasks and work packages to overcome geographical and time zone challenges
- DEnsured that the project would be the highest priority for all team members
8A project manager is planning a project with multiple work packages. Each work package has its own defined scope, but funding will be at the project level.
How should the project manager determine if the allocated resource budget is sufficient to cover the resource costs of the project?- ADivide the allocated budget by the number of work packages and verify that each work package can be completed within the allocated budget.
- BEstimate the costs at the work package level and add those costs to calculate the total cost of the project and compare it to the allocated budget.
- CCreate a budget burndown and a scope burnup and then verify that the project scope is completed before the allocated budget is depleted.
- DFund each work package in the order of its importance and shift any remaining scope from nonfunded work packages to funded work packages.
9A project is designed to provide local community members with health facilities that will support improved sanitation practices. What should the project manager do to ensure the community members are up to date on project progress?
- AShare project updates when requested by the stakeholders.
- BShare project updates through regular community meetings.
- CShare the annual reports virtually and in the local newspapers.
- DShare the project reports with the sponsor to inform community members.
10A new project has been kicked off following a planning session. The project is under direct oversight of an executive in the organization After a review meeting, the project manager overhears an executive request a dashboard from one of the team members to show the overall project status What should the project manager do?
- AUpdate the stakeholder engagement assessment matrix
- BUpdate the communications management plan to include informal requests
- CAsk the team member to develop a dashboard to fulfiII the request.
- DTell the team member to route the request through the project manager
11A customer is meeting with an agile team at regular intervals and keeps changing priorities for the team members. What should the project manager do to remove this impediment?
- AEscalate the situation to the customer management team.
- BAsk the customer to discuss these changes with the product owner.
- CRequest that the customer to meet with the team only at the weekly meeting.
- DAsk the customer to discuss these changes with the management team.
12A company that is heavily focused on delivering projects using predictive approaches on- boards a new project manager who uses hybrid approaches The scope of the project contains a number of unclear requirements.
How should the project manager plan the delivery of the project?- AWait for the requirements to be more clear before any further action is taken on the project
- BIgnore the unclear requirements and focus on the delivery plan of the project
- CEscalate the issue of unclear requirements to the management team and wait for final authorization
- DBreak down the requirements and prioritize the requirements into iterative work packages
13In a project management team meeting, one of the team members always argues with the project manager about the objective, timeline, and deliverable of any assigned task.
What should the project manager do to manage this conflict?- ASchedule a meeting with the team member and their manager to discuss the issue.
- BTalk to the project sponsor about the team member's attitude.
- CSchedule a one-on-one meeting with the team member to talk about it and get their cooperation.
- DFind another person to replace this team member.
14A project manager Is working on the initial phases of a highly technical project that employs the "first of its kind" technology. Many of the key project stakeholders are unaware of the project objectives and their participation levels are poor. At every meeting, there are a lot of objections and queries raised that are taking the discussions to a different level, and a great deal of time is wasted What should the project manager do?
- ARequest stakeholders who understand the technology.
- BRecommend a change in technology to senior management.
- CPlan to conduct informal sessions with the stakeholders.
- DInclude the issue in the Issue log and escalate to senior management.
15A project manager for a factory construction project in a small town is evaluating the necessary actions to engage stakeholders The local community is speculating the impact of the facility. There are rumors of job opportunities and environmental impacts which are listed on the project risk matrix What should the project manager do with regard to community engagement in this situation"
- AInclude the local union representative in the high-power, high-impact stakeholder group
- BFocus on the sideward stakeholders only and let the organization manage the community.
- CBuild channels to extend communication efforts to the local community
- DUse the city administration to address communication with the community
16A company is implementing a project with team members located in different countries and time zones.
Individual performance is satisfactory, but the team's performance as a whole is low, especially in terms of group activities.
What should the project manager do?- ANegotiate for new team members.
- BReview and update the communications management plan.
- CReview and reassign team assignments.
- DFacilitate communication and team building.
17Eight people have been working on a project for an extended period of time. The scope has changed significantly and the product owner has been replaced multiple times. The team members are feeling disassociated from the project.
What should the project manager do to ensure team alignment with the goals?- AAsk the new product owner to explain the importance of the project.
- BEmail the team a detailed outline of the business requirements.
- CReview the project charter with the team.
- DFacilitate a discussion of the vision for the project.
18As part of the strategic plan, a company decides to implement a new software platform to manage a centralized document repository. Some requirements are clear and some need more detail.
What should the project manager do first to decide how to manage this project?- ASelect a predictive development life cycle based on the team's experience
- BDetermine the most appropriate life cycle approach for the project
- CRegister all requirements into a backlog for further detailed analysis.
- DSplit the requirements, put them into two separate projects, and apply different approaches
19During the execution phase, the project manager discovered that the deliverables are not meeting the quality specifications requested by the main stakeholder. This has caused the schedule performance index (SPI) to deteriorate from 0.98 to 0.72 and the cost performance index (CPI) from 1.5 to 1.1.
What action should the project manager take to mitigate the issue of the deliverables being rejected during the next iteration?- ASubmit a change request to prioritize resolutions for the quality issue to minimize the impact on the rest of the deliverables.
- BReinforce the definition of done (DoD) during sprint planning so that the team has a common understanding of expectations.
- CAssure that the product backlog is properly prioritized to avoid dependencies that cause rejection.
- DCreate a dedicated sprint to complete all of the pending specifications from previous sprints.
20A project manager meets with external stakeholders to explain the objectives and outline expectations for a new project. A key stakeholder appears to support the project, with the condition that other unrelated projects will receive financial support Due to cultural sensitivities the project manager is reluctant to be direct with the key stakeholder on this matter The project cannot proceed without the support of this stakeholder.
What should the project manager do?- AProceed with the project without allowing scope creep to occur
- BUse the contingency funds to provide support for the requested projects
- CCancel the project since the stakeholder's request is out of scope
- DInform the sponsor and document the request in the stakeholder engagement plan
21A team has just adopted an agile approach. During daily standup meetings, the team expressed concerns about task delays. The project leader worked with the product owner to get clarity on the features. The project leader asked the team to fast-track all product features to ensure delivery. Sprints are being completed but with either fewer features or low quality. What should the project leader have done to ensure success?
- ADirected teams to possible solutions that help in removing the impediments and contribute to a timely delivery
- BSuggested to the team to add impediments as work items in the product backlog to be fixed in the next sprints
- CAsked the team to create an impediment log and keep it updated for use in the next sprint planning
- DEmpowered the team to improve their processes, tools, and interactions to be more effective in delivery and removing impediments
22An experienced project manager is managing a multi-million dollar agile project The project manager communicates the ground rules to the team but after 12 iterations, the project manager starts noticing that some team members are not following the ground rules.
What should the project manager do first to ensure team adherence to the ground rules?- ASchedule a meeting with the project team to reinforce the ground rules.
- BNotify the project sponsor about this behavior and ask the sponsor to take disciplinary action
- CContact human resources to request a written warning letter be sent to team members not following the ground rules.
- DAsk the functional manager to replace team members not following the ground rules
23A team is using an agile approach to maintain the project backlog. A new project obstacle was identified as a blocker and added to the backlog list. The team is facing challenges to remove this obstacle What should the project manager do next?
- AEscalate the obstacle to a servant leader for resolution.
- BIgnore the obstacle and present the partial solution to the customer
- CFocus on generating business value despite the obstacle
- DMake changes to reprioritize the backlog because of the obstacle.
24One of the team members is always late to the daily standup meeting. What should the project manager do?
- ASchedule the meeting at the end of the day to accommodate everyone.
- BIgnore the situation since the team member is accomplishing their deliverables.
- CReinforce the ground rules for standup meetings with the entire team.
- DSpeak with the team member directly to reinforce the ground rules.
25A product owner Goes not regularly attend demonstration ceremonies. As a result, the demonstration ceremonies are constantly rescheduled and the work is impacted in multiple ways. The project manager believes the product owner Is not committed to the project.
What should the project manager have done to avoid this situation?- ADefined a set of external audits that can expose this situation to the project sponsor
- BAgreed with the product owner on appropriate project governance levels
- CSet a definition of done (DoD) that considers the work as done if not otherwise specified
- DAsked another product owner to attend the demonstrations on behalf of the product owner
26A learn member has a sudden emergency that may last for several days. There are no other team members who can cover their tasks and job duties. What should the project manager do to address this concern?
- AHold an emergency project team meeting to discuss the situation.
- BAsk the human resources (HR) manager for an external replacement.
- CLog the situation in the issue log.
- DUpdate the key stakeholders on the issue.
27In a hybrid project, the customer has issued a contract that specifies the deliverables for each quarter The customer wants to show their stakeholders a tangible outcome in the first quarter and wants to move the second milestone to the first quarter The project manager explains to the customer that it is not feasible unless the requirements for the second milestone are changed Which two actions should the project manager take? (Choose two)
- AConvince the customer to leave the second milestone in place and not change it.
- BEscalate the issue to upper management to resolve the problem and suggest a plan.
- CGo back to the development team and discuss which second milestone requirements can be performed in the first quarter.
- DAsk the customer for their priorities regarding the requirements for the second milestone
- ETell the customer that moving the milestone has a very high impact on the cost of the project
28For the purposes of quality assurance a quality audit was conducted on the processes being used in the project execution plan. One of the nonconformance issues raised by the auditor was that attendance lists for the project risk review meetings were not available Why is an attendance list important?
- AIt is standard practice on projects to conduct risk review meetings which should have records on meeting attendance
- BThe attendance list is evidence that risk review meetings were held with the appropriate project team members
- CIt is a record that shows the number of attendees in the meeting
- DIt is a document that is registered within the lessons learned register
29A key project stakeholder has started to escalate all issues and main requirements to the project sponsor. The project manager is concerned about the team not receiving direct communications from this stakeholder.
Which two actions should the project manager take to improve the relationship with the stakeholder? (Choose two)- ASchedule regular meetings with the key stakeholder to provide updates and receive feedback
- BShare weekly status reports with detailed information about the project and team performance.
- CSubmit performance reports and task assignments to keep the stakeholder informed.
- DPromote an adaptive and transparent environment where the team can easily communicate with the stakeholders.
- EProvide training to the team on emotional intelligence and status reporting techniques.
30for a project has reported the potential for a delivery delay due to a technical issue with the sub-supplier To stay on schedule, the vendor proposed replacing the sub- supplier's component with a similar part that is different from the one that is stipulated in the project specifications.
What should the project manager do next?- AAccept the proposed replacement in order to keep procurement activities on track
- BInsist on using the component per the project specifications and air freight the equipment to mitigate the delay
- CInstruct the vendor to use the part that is compliant with the project specifications and update the schedule
- DConsult with a subject matter expert (SME) to see if the proposed change is acceptable
31A project manager is closing a project and preparing to hand it over to the operations team. During handover, a delayed invoice was submitted with a higher-than-planned cost against the project work. Consequently, project handover was delayed and the project's reported completion costs were increased.
What should the project manager have done to avoid this situation?- ACaptured and reviewed all of the project work and related costs regularly
- BNotified all vendors about the invoicing and nonpayment deadlines
- CReviewed the total committed cost against the cost invoiced at project closing
- DInvolved the finance team and discussed the issue with the vendor
32The sponsor is supportive in leveraging agile approaches The project manager is contemplating how to roll out the agile approach and gam buy-in from both project team members and stakeholders What should the project manager do first?
- ADetermine which agile software tools will be required to support agile delivery within the organization
- BSelect a current predictive project define the approach, and provide agile training to execute the remainder of the project
- CStart with a pilot project of appropriate complexity and provide agile training to those who are impacted
- DDetermine how to transform the organization using agile techniques, including organizational training and communications
33A large project is affecting the neighborhood in which it is located The neighbors are not satisfied with the project and their resistance to the project may affect the project deadline What two actions should the project manager take'? (Choose two)
- ASend letters to the neighbors and ask them kindly not to disturb the project.
- BSet up a meeting with neighborhood representatives to win their cooperation
- CAnalyze the situation and find out what is causing the neighborhood's negative attitude.
- DAsk the customer to extend the project deadline to allow time for conflict resolution
- EAsk the mayor of the city to use their authority to stop neighborhood resistance
34A new project manager is assigned to an ongoing agile innovation project that started 2 weeks ago. After reviewing the project, the new project manager discovered that the previous project manager was planning to use a predictive approach. The previous project manager planned to present the first major deliverable to the client when the project was completely finished in 8 months.
What should the new project manager do?- AMeet with the team to review the backlog and create small iterations that can deliver incremental value to the client
- BContinue working with the predictive approach to deliver the value at the end of the project.
- CUse a hybrid approach in which agile practices are used but the value is provided to the client at the end of the project.
- DSubmit a change request to the project board to adjust the delivery date to 2 months earlier than planned.
35A project manager has a team of shared resources from other projects who are working on a client project Three days before the project is due. The team informs the project manager that the project will be delayed because a component was not delivered on time Competing priorities of the shared resources are delaying delivery of the component What should the project manager have done to prevent this delay from happening?
- AUpdated the risk management plan and registered lessons learned for the project
- BReorganized the team for the project based on the work breakdown structure (WBS)
- CMaintained constant communication with the stakeholders of the other projects
- DUsed the resource management plan to identify the impacts of the other projects
36A project manager is assigned to a new project and is allocated with virtual team members. Later, two more members from a recently acquired company join as additional resources to the project team.
In order to ensure that there are no potential misunderstandings, what should the project manager do?- ASend an email update to existing team members about the addition of the new team members.
- BSet up a weekly meeting with the new team members for a couple of months.
- CRequest the transfer of the new members to another project, citing a risk of confusion.
- DUpdate and share the guideline document dealing with team communication.
37During a project status meeting with senior managers, the project manager gives an update about the status of a deliverable. Some of the senior managers claim not to Know about the deliverable.
What should the project manager do next?- AValidate if the project charter changed from the original one.
- BMeet with these stakeholders to review the project charter.
- CCheck if these stakeholders attend regular project meetings.
- DReview the project charter to validate this claim.
38An agile project is in the seventh iteration with multiple changes being accommodated from the project start due such as regulatory changes technological innovations market competition and other changes What should the project manager do to manage these continuous changes coming into the project?
- AAsk the product owner to stop accommodating further changes to the scope
- BLeverage the product owner to monitor the external environment
- CAccommodate the critical and urgent changes in the current iteration
- DSuggest to the product owner to execute the changes in a separate project
39A company's CEO complains about the frequency of project communications. The CEO receives five project reports each week by email but does not have enough time to review them. In addition, the information that the CEO receives is not relevant in that it does not explain the project status, What should the project manager do first?
- AReview the stakeholder engagement plan.
- BReview the communications management plan.
- CSend the CEO one executive summary per week instead of five reports per week.
- DMeet with the team and decide the type and frequency of the reports to send to the CEO.
40A project team is reviewing solved project issues from the last phase of a project. The lead risk analyst points out that the next phase of the project includes a critical element with some reserves needed What should the project manager do to successfully complete the next phase?
- ARequest a reserve analysis and update the risk management plan
- BUpdate the risk response plan to include the needed reserve
- CPerform a schedule network analysis to avoid any critical path delays
- DReview the risk response plan to verify inclusion of the needed reserve
41A project has issues arising where the data integration team and the data migration team have areas that overlap It is not clear who would be responsible for delivery on these areas What should the project manager do next?
- AReview the project scope to align the project teams
- BReview the resource management plan to align the project teams
- CReview the project integration plan to align the project teams
- DReview the work breakdown structure (WBS) to align the project teams
42The project sponsor recently requested that a vendor begins working toward adopting a hybrid approach. In response, the vendor hired a project manager experienced in agile for the project.
What does that project manager need to do to make the team work in a collaborative way?- ARequest the project management office (PMO) for a team of mentors.
- BAllocate time to mentor the team.
- CUpdate the issue log.
- DIdentify any training gaps
43A project manager is assigned to a building construction project. The project manager has taken an agile course and wants to use agile practices in the project.
What should the project manager do?- AHire a consultant to provide a second opinion about whether agile can be applied to a construction project.
- BChoose the agile practices that can be implemented in this type of construction project and apply them.
- CReview the stages of the project to allocate additional budget for agile resources.
- DAssign a scrum master to the project to implement agile practices in the project.
44A state-of-the-art product was delivered at the end of a project life cycle. However, the customer claims the product was not designed to specifications.
What should the project manager have done to avoid this issue?- AThe customer's requirements should have been captured in order to meet the customer's standards.
- BThe iteration review planning meeting should have been planned accordingly.
- CThe sprint retrospective meeting should have included necessary stakeholders.
- DThe customer's requirements should have been captured and modified to meet the supplier's standards.
45At a meeting to receive approval for the project management plan, a project manager realizes that there is so much detail in the presentation that many of the stakeholders are not actively engaged in the process. The stakeholders are agreeing to the scope, goals, and timelines without giving them substantial thought.
How should the project manager proceed?- AStop the meeting and reschedule for another time with a more concise presentation.
- BSet up information review sessions before reconvening another approval session.
- CGet approval and promise to email more information to the stakeholders to clarify the technical details.
- DObtain approval as fast as possible and close the meeting.
46A project manager is managing a hybrid project. During project execution, the project manager was informed that over half of the project budget was reallocated to a project that is handling an emergency that recently occurred.
What should the project manager do?- AMeet with the project sponsor to explain that the project cannot be completed as planned
- BMeet with the technical lead to review the sprint plan
- CMeet with the product owner to confirm the minimum viable product (MVP) option
- DMeet with the project team and reprioritize the backlog
47A client is structured as a matrix organization for an agile project The project manager is working on-site with key stakeholders from different parts of the organization How should the project manager handle the different stakeholders?
- AAll stakeholders are important, so the project manager should follow directions provided by management and key stakeholders
- BBecause there are different perspectives perform a stakeholder analysis and act based on the outcome.
- CThe project manager is working on the client's premises, so follow the directions of all the key stakeholders
- DThis is an agile project, so listen only to the directions of the project manager's supervisor and the functional managers of the organization
48The project manager has recently received funding approval for a training program for the entire project team but has not yet defined the most effective training course. One team member submitted a request for specialized training that is required for the project.
How should the project manager handle this request?- ASend this change request to the change control board (CCB) for approval.
- BApprove the request for the specialized training.
- CReject the request as it does not impact the project deliverables.
- DValidate if the training is within scope and budget.
49One phase of a project took much longer than initially anticipated The key stakeholders expressed their concern regarding a potential project delay. What should the project manager do?
- AExpedite the next phase to reduce slippage
- BAdd more float to the overall project schedule
- CRequest additional contingency from the sponsor.
- DOrganize a root cause analysis (RCA) workshop.
50A project manager collects various pieces of information and consolidates metrics in an agile project. The project manager finds that there is slack in the team in terms of productivity. The number of items sent to development per person has decreased by 10%, and the project manager used a root cause analysis (RCA) and discovered the reason is a lack of knowledge in one of the frameworks used for modeling.
What should the project manager do next?- AFoster knowledge sharing and coaching among team members.
- BArrange for external training amid the tight project schedule.
- CAdd new members for the underperforming team.
- DSeek an external expert to review the framework.
51During project execution, an important stakeholder threatens to withdraw support for the project, citing a lack of transparency and accountability in the way the project is being executed. What should the project manager do to handle this situation?
- AApproach the stakeholder to address the concerns.
- BConsult the risk management plan.
- CEscalate the issue to the project management office (PMO).
- DRefer the stakeholder to the project sponsor.
52A project manager was replaced in the early phases of a new project. The new project manager discovers that the business team is not supporting the project. After discussing these concerns with the team, it is determined that the project does not have the full support of senior management.
What should the new project manager do next?- ASend out a status report describing the situation to the stakeholders and request general assistance.
- BRequest the business team to clearly define their issues with the project work completed to date.
- CStudy the stakeholder analysis to understand which stakeholder holds the most influence and seek their assistance.
- DAsk senior management to be more involved with the project and to provide their full support.
53Two learn members are consistently having misunderstandings and find it difficult to work together. How should the project manager handle this situation?
- ARemove one of the team members
- BIdentify the issues between the team members and guide them toward a resolution
- CWarn the team members about their behavior
- DTrain the team members on communication techniques and interpersonal behavior
54An intern is replacing a critical resource midway through a sprint To help the intern get up to speed, the project manager assigns a senior engineer in the team as the intern's mentor Two months later, the project goes into critical status, delaying the release milestone by a month. What should the project manager have done to avoid this scenario?
- AConvinced the critical resource to remain on the project.
- BRequested an experienced resource as a replacement
- CAllocated additional time for mentoring
- DNegotiated additional time to complete the project
55A project manager is working with a customer's team on a new project. Some product definitions and requirements are still not clear, but the customer wants to start activities as soon as possible. The organization is also expecting product delivery for a specific date due to a regulatory requirement. Due to the nature of the project, the project manager has decided to use a hybrid approach.
Why did the project manager choose a hybrid approach?- AA hybrid approach will ensure the delivery date is accomplished and will eliminate product uncertainties.
- BA hybrid approach will enable project activities to start immediately and allow for a plan for the requirements definitions.
- CA hybrid approach will allow the project manager to revise the product specifications.
- DA hybrid approach will allow for management of the requirement uncertainties as well as the date restriction.
56A project for a new product launch is in a very initial stage and the requirements are evolving Due to stiff competition in the market, the customer would like to launch the product keeping the scope flexible. The project team intends to start the work based on the forecast of a similar project delivered last year Which project approach suits the scenario?
- AExecute it as a Scrum project
- BExecute it as a predictive project
- CExecute it using the same approach as the reference project
- DExecute it as a project with stage gates
57An agile project is in its sixth iteration out of 10 After the iteration review, the team receives feedback from the stakeholders that could result in a change in the product What two actions should the project manager take? (Choose two)
- AAsk the stakeholders about the priority of this change
- BAsk the product owner to review the product backlog
- CAsk the team members to analyze the impact of this change
- DAsk the sponsor to approve the change request
- EAsk the team members to include the change in the next iteration
58During the execution of a project to develop a prototype, the customer asks the project manager to stop the prototype line and purge a specific component based on recent reliability tests that have deemed the component to be deficient. The project manager checked the quality management plan and there is no reference to this component.
What should the project manager do next?- AInform the project sponsor of the situation and wait for the sponsor to provide further directions.
- BCall a technical meeting with the customer to agree on a specification for the component and document it in the quality management plan.
- CSubmit a change request to proceed with the replacement of the component and wait for further customer instructions.
- DKeep running the manufacturing line because there are no quality specifications for this component.
59A project manager and a stakeholder have different opinions on the budget estimates for a project that is being initiated based on a new consumer privacy law. What would be a reason for this difference in opinion?
- AThe communications management plan was not used by all stakeholders.
- BOrganizational assets were not available to back the rationale.
- CRelative estimation by the team resulted in two estimates.
- DThe use of the Monte Carlo method can result in different estimations.
60A project is delayed due to multiple problems discovered during the quality review. Every time the team addresses one problem, additional problems are encountered. This is frustrating for both the project team and the project sponsor, who are driven to meet the dates and results expected by the organization.
What should the project manager do?- ARequest that the team identifies, documents, and registers the issues to locate the source of the problems.
- BEvaluate the cost and schedule variance in order to determine how much the project is off track.
- CAsk the team to commit to a new bate to lx all the problems and proceed with a change request to adjust the baseline.
- DRequest that a senior subject matter expert (SME) be hired to analyze and solve the problems.
61During a project planning phase, the project manager realizes that project performance win be measured based on budget deviation and revenue, but without consideration for the overall project schedule What should the project manager do?
- AReview and update the project schedule according to performance
- BReview the schedule baseline and consider adopting a schedule performance indicator
- CDevelop a lime. cost, and scope tracking method exclusively for this project.
- DAdopt a formal change management process for the project
62A project manager has just taken over a project that is in the requirements gathering phase. A stakeholder indicates that they have not received any progress updates even though reports have been sent on a weekly basis.
What should the project manager do to ensure all stakeholders are receiving proper information about the project?- AHold a steering committee meeting with all stakeholders to provide a comprehensive update on the project progress.
- BCreate daily progress reports and send them to all stakeholders.
- CInclude stakeholders in the weekly status meetings with the team.
- DAssess all of the project stakeholders and document their preferred communication method and frequency.
63A project team's performance is being impacted by impeding internal procedures that are affecting the progress of activities and team autonomy. What should the project manager do first to address this situation?
- ATry to remove the barriers and empower team members.
- BAsk the organization to improve the internal procedures.
- CTrain the team members on the organization's procedures.
- DDiscuss the issue in the next sprint review meeting.
64A large multi-year project requires highly skilled staff for successful deployment The management team and the project sponsor have analyzed the resource requirements and agreed to have permanent staff hired for the project to avoid potential budget overrun However there is a risk of staff turnover during the course of the project, which may have an impact on the delivery Which two actions should the project manager take to mitigate this risk? (Choose two)
- AIntroduce a recognition program to motivate and reward resource performance
- BEnhance the competencies of the project team through training, mentoring and coaching.
- CIncrease the trained staff to create back-up for resources
- DMeet with management to discuss dividing the project into smaller projects
- EConvince senior management to hire third-party staff
65A key stakeholder for a construction project has been spending a lot of time at the site and interrupting the team's efforts What should the project manager do in this situation?
- AWork to understand the key stakeholder's concerns and provide feedback in regular project status reports
- BArrange an ad hoc meeting to address the key stakeholder's concerns with team members
- CReinforce with the key stakeholder that the project is performing on scheduled
- DEscalate the situation to the project sponsor because the key stakeholder's behavior is impacting progress
66A company is moving to a hybrid approach and conducted capacity activities for all of the project managers.
During these capacity-building activities, the focus was on agile approaches and team facilitation skills. When starting the implementation phase, the project managers faced issues motivating the newly hired agile staff.
Why are the project managers having issues motivating the agile staff?- AThe capacity building activities missed the servant leadership concept transfer.
- BTransitional periods normally cause this type of problem.
- CThe agile staff is not used to being led by a project manager.
- DProject managers are expected to become coaches in agile teams.
67A project manager is leading an agile team. The daily standups and iteration meetings are currently facilitated by the product owner. A team member contacts the project manager and mentions that they are looking to improve their facilitation skills.
How should the project manager respond to this request?- AAsk the team member to review the lessons learned on facilitation from previous projects.
- BSuggest that the team member facilitate an upcoming iteration and review the outcomes in the iteration retrospective.
- CEngage their functional manager to determine if there is alignment to their development plan before agreeing.
- DAdd new elements to the project backlog to account for the training needs of the team member.
68A project manager is tasked with large deliverables that require work by several top developers over the next few weeks Because of the size and complexity of the deliverables the work cannot be assigned to a single person What should the project manager do first?
- ARequest additional developers to join the project team through the change cannot process
- BBreak down the deliverable by using the work breakdown structure (WBS) process to make it more manageable for task assignment
- CAssign the entire deliverable to the first available developer to lead and have them assign the work to the remaining developers
- DInclude the situation as a risk in the risk register identify risk impacts and possible mitigations, and monitor closely
69During a retrospective meeting a project manager hears that stakeholders have been constantly complaining at iteration demos about product features not being delivered as requested. What advice should the project manager give to the Product owner to ensure that product features are always delivered as requested?
- AInclude stakeholders during daily standup meetings to monitor progress.
- BValidate acceptance criteria with stakeholders prior to backlog refinement
- CAvoid including stakeholders in iteration reviews.
- DCreate a requirements traceability matrix and distribute it accordingly
70A company is implementing a project with team members who are located in different countries and lime zones Performance assessments show that team performance is low because the team doesn't have a common understanding about task distribution What should the project manager do?
- AColocate the team members
- BPerform team-building activities
- CReview and reassign tasks
- DRevisit the communications management plan
71An operations manager continuously raises concerns about a project's benefits to the company While some concerns are valid most of the time these concerns have caused delays in project meetings How should the project manager handle this’?
- ADiscuss the meeting delays with the director of operations and ask for support with the concerns.
- BReview the operations manager's concerns and ensure these concerns are addressed
- CEscalate the concerns to the project sponsor and discuss options to address them
- DInclude the operations manager's concerns in the risk register and assign actions to mitigate the risks.
72A project team member informs the project manager that a stakeholder is contacting the team member to request status updates. The team member is being distracted by these repeated requests, which are interfering with the completion of assigned tasks.
What should the project manager do?- AIncrease the frequency of updates given to this stakeholder.
- BInform the team member to stop sending any further updates to the stakeholder.
- CRaise this issue to the project sponsor in the next project status review meeting.
- DReview this stakeholder's communication requirements.
73During a project review meeting, several project team members expressed that they did not have an understanding of the benefits of certain features for the project What should the project manager do next?
- AReview the project scope statement
- BConfirm ownership for ongoing value realization
- CEscalate the issue to the project sponsor
- DAppraise the stakeholders of value gain progress
74A project manager is assigned to oversee the deployment of a new product that will be used by the entire organization. A key success factor for the project is the timely and successful adoption of the new solution by all entities.
What should the project manager do to ensure the success of this critical project?- AConsidering the project scope and the multiple entities impacted by the solution, communicate with the stakeholders and ask them to adhere to the date.
- BAsk the project sponsor to issue a directive requesting all business entities to accept the date set for the new solution launch.
- CGiven the size of the organization and the multiple parties involved, discuss the launch date with the CEO and then communicate it to all entities.
- DEngage in creative and iterative negotiations with the leaders of each entity to agree on the launch date.
75A human resources (HR) cost report was disclosed, by error, to all members of the project team. This situation generated a conflict between the team members about differences in their salaries.
What should the project manager have done to avoid this situation?- AEnsured reports with significant information were not included in the communications management plan
- BDefined the appropriate recipients for the report in the communications management plan
- CIncluded noncompliance punishment measures in the communications management plan
- DValidated the information and the appropriate recipients per the communications management plan
76The customer's project manager changes during the final stage of a project How can the project manager avoid a project closure delay'
- AUpdate the stakeholder engagement plan
- BReview the latest project status report and update the stakeholders
- CEscalate the case to the customer's management team
- DIssue the project payment invoice to the customer in advance
77A company wants to increase the commercial value of one of its products in a highly competitive market In order to do this, the company commissions a project to create a prototype The team constructs the prototype incrementally Which action should the project manager take as a priority?
- AEmphasize the use of Kanban methodology.
- BEnsure the project sponsor is aware of the go-to market date
- CDeliver business value as soon as possible
- DImplement a plan-do-check-act (PDCA) cycle
78A project manager for a strategic initiative realizes a new stakeholder is interested in the project and wants to ensure the stakeholder is fully aware of the goals, objectives, benefits, and risks of the project. What should the project manager do to enhance the success of the project?
- AAdd the new stakeholder to the communications management plan
- BShare the project status reports with the new stakeholder.
- CUpdate the stakeholder engagement plan
- DSchedule a meeting with the new stakeholder
79A typically high-performing team member has started to demonstrate a performance drop as well as some aggressive behaviors toward other team members in meetings.
The project manager has worked with this individual for many months on this project and has not seen this type of behavior before.
What should the project manager do?- ADiscuss the project manager's observations with the individual to determine why they are behaving this way.
- BDiscuss the individual's behavior with the other team members to determine if they have noticed and know what is going on.
- CAttend more team meetings to observe the team more closely to determine the root cause.
- DDiscuss their performance with the team member's functional manager as well as human resources (HR) and discuss next steps.
80A project manager for an iterative project noticed that retrospective items indicate that the team is not fully conversant with the principles of iterative development. The team meets to analyze the gaps in the training that recently concluded with a third-party trainer.
What should the project manager do next?- AInitiate hybrid development as an interim approach.
- BLet the project team self-organize and develop their skills.
- CMentor and coach the team to meet the project needs.
- DReview the training contract to determine the next steps,
81A project manager is managing a few innovation projects with a high level of uncertainty. The project manager is experiencing challenges with the large number of change requests issued due to the nature of the project.
What should the project manager do?- AAdd a fixed number of change requests allowed by the client on the project baseline.
- BRequest sponsor approval for all change requests to reduce the number of changes.
- CInitiate the number of iterations to reduce the number of change requests.
- DReduce the number of approvers required to implement a change request.
82A project manager is leading a meeting with key stakeholders, the project sponsor and the product owner to define the features that will be released after the next iteration. The purpose of the meeting is to review the product backlog prioritization, considering that during the past iteration some deliverables were not completed.
Which two items should be taken into account first to review and update the product backlog priorities during the meeting? (Choose two)- AComplexity and the cost of development
- BIndustry trends and the technical approach
- CCost of delaying some features against business value
- DReusing components from another product
- ELength of time each feature has been on the backlog
83In the planning phase of a software implementation project, two of the team members disagree on how to approach end-user training. The discussion has intensified and the team members are not able to agree.
What should the project manager do next?- ARemove one of the team members from the project to improve team dynamics.
- BMake a decision based on expert judgment as a project manager.
- CConsider the view of each team member about the issue in order to reach consensus.
- DRemove both team members since they are not productively adding to the team.
84A project is being executed The project's life cycle is defined as predictive however, a major deliverable will be handed over incrementally to the customer The assigned resources are experienced and reliable and are willing to make decisions that the project manager used to make after each incremental delivery on other projects What should the project manager do?
- ASchedule a steering committee meeting and obtain their approval on the request
- BSupport the decisions of the team and transfer the decision making responsibility to them.
- CInform the team that although this is a hybrid environment, the project manager must still be responsible for making decisions
- DConsult the product owner about letting the resources make decisions
85Five agile teams working together on a product recently performed release planning Midway through the project, each team showed that their progress was on track When all of the teams integrated at the product level, many integration issues were observed The overall product release progress declined with predictions showing the committed content will not be able to be accomplished What should the project manager have done differently?
- AFormed a separate quality assurance team to test all items coming from each team at the end of each sprint
- BPerformed a Scrum of Scrums on a regular basis to help the teams remove impediments
- CEnsured frequent and continuous integration of work to obtain early feedback and continuous learning
- DArranged an online session on the integration concept and suggested tools to the teams
86During the early phases of a project, mitigation actions were not executed in a timely manner; therefore, the project schedule was impacted. Several project stakeholders are now frustrated with the delays.
What should the project manager have done to manage the issue?- AIdentified and reported the issue
- BMonitored and controlled the issue
- CIdentified the appropriate response and had it implemented
- DCommunicated any identified action to impacted stakeholders
87A company is transitioning their projects to utilize hybrid project management approaches While putting together their project team, the project manager discovers the requirements from the customer are unclear and also realizes that the team members are lacking critical technical stalls needed for project success. However the customer will not accept any changes to the requirements What should the project manager do to resolve this issue?
- ASubmit a change request to adapt the objectives of the project to the current situation
- BAsk the scrum master to refine the user stones to improve the team members' understanding
- CFind and provide training to the project team members who do not have the required skills
- DExtend the duration of standup meetings to include skill transference from trained to untrained members
88A project manager is planning a project and identifies that legislation requirements for specific project tasks will be changing. This will occur half way through the project execution phase and will affect a few key workers' licenses, which will become noncompliant.
What should the project manager do?- AStart scheduling the training for key workers now to ensure compliance.
- BMaintain the current key workers since the project has already started.
- CUpdate the project charter to ensure the new legislation is addressed,
- DStart a recruitment drive for new workers with the licenses required.
89A project learn member identified a defect in the initial solution design for a project The stakeholders are not sure whether to deploy the system or not. What should the project manager do?
- APropose a solution redesign for the project
- BPerform risk analysis against the issue.
- CRevise the project's quality control measurements
- DDevelop a mitigation based on the solution design
90After reviewing the lessons learned database, a project manager realizes that the current team may not be knowledgeable enough about organizational processes for the needs of a new project. What should the project manager do?
- ADevelop the team members to work as a cross-functional team.
- BAsk a functional manager to provide the right team members.
- CReview the project charter to see if the scope can be modified.
- DAsk the portfolio manager to reassign the project to another team.
91A hospital is running a project for one of their internal critical systems to manage billing patient data and record management along with consultation reports and input from physicians The project manager now needs to categorize the identified risks Drag each risk type on the left to its correct example on the right

- AĐáp án

- BĐáp án ở trên
- AĐáp án
92After gathering all the requirements for a project with dependencies on external stakeholders, the project team is finishing the second iteration At this point, the project manager learns about a possible change in regulations that would prevent the product launch What should the project manager do to realize benefits?
- AAdd an entry in the risk log
- BImplement the changes
- CReview target benefits.
- DImprove the team's velocity
93In an agile project, the learn planned to complete 40 story points in an iteration, but only completed 30 story points. What is the schedule performance index (SPI)?
- A30/40
- B40/70
- C30/70
- D40/30
94A project manager is acting as a scrum master in a hybrid project and is dealing with a conflict between team members What strategy should be used to handle this conflict?
- ASort conflicts into two groups: positive and negative
- BPlace conflicts into categories: structural and interpersonal.
- CPlace conflicts on a shared conflict list and ensure it is visible
- DReview conflicts during daily Scrum so they are handled in a timely manner
95The project sponsor requested technical specifications for a project-related component. The project sponsor does not have the authorization to see the specifications, but insists on seeing them.
What should the project manager do first in this situation?- AMeet with the project sponsor as soon as possible to discuss the matter further
- BUpdate the issue log to make the project team aware and to develop a strategy
- CCreate a stakeholder engagement plan to help the team formulate a response
- DProvide the specifications to the project sponsor with some information removed
96A new manufacturing line project is planned to be delivered in iterations tor the equipment installation phase.
During one of the iterations the vendor communicates to the project manager that they will not be able to deliver some of the equipment at the agreed dates.
What should the project manager do next?- AReplan the remaining iterations according to the new installation dates
- BUpdate the product backlog m order to address the delays
- CReview the procurement agreements to address the situation
- DFind another vendor who can fulfill the delivery dates
97A project manager writes to the receiving organization to inform them that all acceptance activities are completed with success and it is time to initiate handover. The receiving manager replies that the team will not be ready for the handover procedure for another two weeks.
What should the project manager do?- ADeliver to the receiving manager on time, who can then make a knowledge transfer to their team.
- BInform the project sponsor of the two-week delay and replan activities to minimize delays.
- CRequest that the receiving manager issue a change request to prolong the project by two week
- DIssue an internal change request to secure the resources for an additional two weeks.
98A project manager recently joined the company. At the interview, the project manager demonstrated experience with agile delivery, and the project management office (PMO) manager asked for assistance in implementing agile.
What should the project manager do to initiate the adoption of agile within the company?- AOrganize agile workshops with the developers and testers to gain their support in using agile approaches for their projects.
- BRequest that all the project managers and business managers receive training in the agile framework used previously by the project manager.
- CAdvise the PMO manager to continue with the company's current predictive approaches until all the projects in execution are closed.
- DAssess the organization's culture to determine if agile can be used in project delivery and determine the practices to be used.
99A newly assigned project manager is reviewing the project management plan and realizes that the project is running behind schedule. What should the new project manager do to address this situation?
- AModify the project management plan and get approval from relevant stakeholders
- BAdd more resources to recover the schedule without making changes to the baseline.
- CIssue a change order to the change control board (CCB) and rebaseline the schedule.
- DNegotiate with the project sponsor immediately and establish a new project charter.
100A project manager finds that there are knowledge gaps in the project team relating to the core competencies required to deliver the desired results. What should the project manager do to achieve the desired results?
- ACommunicate the situation to the team and plan for the necessary training and coaching arrangements
- BReport the situation back to upper management and request to have the scope changed
- CPlan to hire more experienced team members and lay off a few of the existing team members.
- DCommunicate the situation to the customer and inform them about potential delays in delivery.
Informationen
- Beschreibung
- Công nghệ số Quiz am PMP exam 11, erstellt von Lê Hiếu am 14/08/2022.
- Autor
- Lê Hiếu
- Sprache
- English
- Aufrufe
- 25
- Schlagwörter
- Bewertung
- Noch keine Bewertungen Bewerte dieses Quiz