  1. 11.¿The timebox for a daily Scrum is?
    1. AThe same time of day every day
    2. BTwo minutes per person
    3. C4 hours
    4. D15 minutes
    5. E15 minutes for a 4 week sprint, proportionally less for shorter sprints.
  2. 2Which statement best describes Scrum?
    1. AA complete methodology that defines how to develop software
    2. BA cookbook that defines best practices for a software development
    3. CA framework within which complex products in complex environments are developed
    4. DA defines and predictive process that conforms to the principles of Scientific Management
  3. 33. What is the primary way a Scrum Master keeps a Development Team working at its highest level of productivity?
    1. ABy facilitating Development Team Decisions and removing impediments
    2. BBy ensuring the meetings start and end at the proper time
    3. CBy preventing changes to the Backlog once the Sprint begins
    4. DBy keeping high value features high in the Product Backlog
  4. 4The CEO asks the Development Team to add a ""very important"" item to the current Sprint.
    What should the development team do?"
    1. AAdd the item to the current Sprint without any adjustments
    2. BAdd the items to the current Sprint and drop an item of equal size
    3. CAdd the item to the next Sprint
    4. DInform the product Owner so he/she can work with the CEO.
  5. 5Who should know the most about the progress toward a business objective or a release, and be able to explain the alternatives most clearly?
    1. AThe Product Owner
    2. BThe Development Team
    3. CThe Scrum Master
    4. DThe Project Manager
  6. 6What does it mean to say that an event has a timebox?
    1. AThe event mus happen at a set time.
    2. BThe event must happen by a given time
    3. CThe event must take at least a minimum amount of time
    4. DThe event can take no more than a maximun amount of time
  7. 7Which two (2) things does the Development Team do during the first Sprint?
    1. ADeliver an increment of potentially shippable functionality
    2. BNail down the complete architecture and infraestructure
    3. CDevelop and deliver at least one piece of functionality
    4. DDevelop a plan for the rest of the project
  8. 8Development Team members volunteer to own a Sprint Backlog item:
    1. AAt the Sprint planning meeting.
    2. BNever. All Sprint Backlog Items are "Owned" by the entire Development Team, even though each one may be done by an individual team member.
    3. CWhenever a team can accommodate more work
    4. DDuring the Daily Scrum
  9. 9Scrum Master is a "management" position?
    1. ARichtig
    2. BFalsch
  10. 10The reason the Scrum Master is at the Daily Scrum is:
    1. ATo make sure everyone answers the three questions in order of seniority
    2. BHe or she does not have to be there; he or she only has to ensure the Development Team has a Daily Scrum.
    3. CTo write any changes to the sprint Backlog, including adding new items, and tracking progress on the burndown.
    4. DSo he or she knows what to report to management

Informationen

Beschreibung
Test Exam Quiz am ExamTest, erstellt von jameslimon Lim am 21/03/2016.
Sprache
Español
Aufrufe
14
Schlagwörter
examtest
Bewertung
Noch keine Bewertungen
Bewerte dieses Quiz
Bewerte dieses Quiz

Mehr zu Scrum Framework and Principles

Feedback

Worum geht es?

Was sollen wir als Nächstes hinzufügen?