Om Ch 14- Final

Shelby Reitz 25 Fragen

Quiz starten

Fragen in diesem Quiz (25)

  1. 1Wheeled Coach insists all of the following tasks are key to successful MRP use except
    1. Astringent quality control.
    2. Bmaterials plan must meet both schedule requirements and facility capabilities.
    3. Cplan must be executed as designed.
    4. Dinventory investment must be minimized.
    5. Eexcellent record integrity must be maintained.
  2. 2Demand for a given item is said to be dependent if
    1. Athere is a clearly identifiable parent.
    2. Bthere is a deep bill of material.
    3. Cit originates from the external customer.
    4. Dthe finished products are mostly services​ (rather than​ goods).
    5. Ethe item has several children.
  3. 3The phrase​ "demand related to the demand for other​ products" describes
    1. Adependent demand.
    2. Ba dependent variable.
    3. Cindependent demand.
    4. Drecursive demand.
    5. Eregression analysis.
  4. 4Dependent demand and independent demand items differ in that
    1. AAll of the above are true.
    2. BNone of the above is true.
    3. Cthe need for​ dependent-demand items is calculated.
    4. Dfor any​ product, all components are​ dependent-demand items.
    5. Ethe need for​ independent-demand items is forecast.
  5. 5Which of the following is not a key benefit of​ MRP?
    1. Aquality increases
    2. Bfaster response to market changes
    3. Creduced inventory levels
    4. Dbetter response times to customer orders
    5. Eimproved utilization of facilities
  6. 6Effective use of MRP and other dependent demand models does not require which of the​ following?
    1. Acost of individual components
    2. Binventory availability
    3. Clead times
    4. Dbill of materials
    5. Emaster production schedule
  7. 7A master production schedule specifies
    1. Awhat product is to be​ made, and when.
    2. Bthe financial resources required for production.
    3. Cthe raw materials required to complete the product.
    4. Dwhat component is to be​ made, and when.
    5. Ethe labor hours required for production.
  8. 8The​ __________ is​ (are) the MRP input detailing which end items are to be​ produced, when they are​ needed, and in what quantities.
    1. Amaster production schedule
    2. Binventory records
    3. Cassembly time chart
    4. Dload report
    5. Ebill of material
  9. 9A master production schedule contains information about
    1. Aquantities and required delivery dates of final products.
    2. Bscheduled receipts for each final product.
    3. Cinventory on hand for each final product.
    4. Dquantities and required delivery dates of all subassemblies.
    5. Einventory on hand for each subassembly.
  10. 10The aggregate plan gets input or feedback from which of the following​ areas?
    1. AAll of the above.
    2. Bengineering
    3. Cfinance, marketing, and human resources
    4. Dprocurement, production, and general management
    5. Ethe master production schedule

Informationen

Beschreibung
OM- Final Quiz am Om Ch 14- Final, erstellt von Shelby Reitz am 22/04/2018.
Sprache
English
Aufrufe
0
Schlagwörter
om- final
Bewertung
Noch keine Bewertungen
Bewerte dieses Quiz
Bewerte dieses Quiz

Mehr zu Production Planning and Scheduling

Feedback

Worum geht es?

Wie gefällt dir das neue Design?

Dein Eindruck