Gestalte GoConqr mit. Was sollen wir als Nächstes hinzufügen?

Quiz

Construction 2 Exam Revision

Isaac Mont 17 Fragen

Quiz starten

Dieses Quiz enthält Fragetypen, die sich im gewohnten Player öffnen.

Fragen in diesem Quiz (17)

  1. 1Match the member name with the drawingBild zu Frage 1
    1. AApex Haunch
    2. BEaves Haunch
    3. CBase Plate
    4. DSlab Floor
    5. ERafter
    6. FColumn
    7. GKnee Cleat/Connection
    8. HApex Cleat/Connection
    9. IZ-Purlins
  2. 2The manufacture of Tilt-up walling involves many activities. The sequence of these activities is as follows:

    1. [blank_start]Produce fabrication/workshop drawings[blank_end]
    2. [blank_start]Provide casting beds[blank_end]
    3. [blank_start]Construct formwork[blank_end]
    4. [blank_start]Fit mouldings[blank_end]
    5. [blank_start]Place reinforcing[blank_end]
    6. [blank_start]Fit cast ins[blank_end]
    7. [blank_start]Apply bond breaker[blank_end]
    8. [blank_start]Pour & finish concrete[blank_end]
    9. [blank_start]Cure concrete[blank_end]
    10. [blank_start]Place further panels on top[blank_end]
    11. [blank_start]Prepare & repeat operations[blank_end]
    1. AProduce fabrication/workshop drawings
    2. BProvide casting beds
    3. CConstruct formwork
    4. DFit mouldings
    5. EPlace reinforcing
    6. FFit cast ins
    7. GApply bond breaker
    8. HPour & finish concrete
    9. ICure concrete
    10. JPlace further panels on top
    11. KPrepare & repeat operations
  3. 3Select the three types of concrete walls:
    1. AIn-Situ
    2. BTilt-Up
    3. CPre-Situ
    4. DPre-Cast
    5. ETilt-Cast
  4. 4What are the 3 s's?
    1. ASimplicity - Number of members kept to a minimum
    2. BStandardisation - As many members of the same size
    3. CServiceability - Design must feel comfortable
    4. DSustainable - Members must focus on meeting the needs of the present
    5. ESymmetry - Of structural members and grid layout
  5. 5Match the description with the concrete wall:

    1. [blank_start]Tilt Up[blank_end] = Where the building's walls are poured on the job site in large slabs and then raised into position around the buildings perimeter, forming external walls.

    2. [blank_start]Pre-Cast[blank_end] = A construction product produced by casting concrete in a reusable mold or "form" which is then cured in a controlled environment, transported to the construction site and lifted into place.

    3. [blank_start]Pre-Situ[blank_end] = Not a type of concrete walling


    4. [blank_start]Tilt-Cast[blank_end] = Not a type of concrete walling


    5. [blank_start]In-Situ[blank_end] = Where formwork is installed around the area where the wall is going to be. Reinforcement and concrete is then placed into the formwork to create a wall. It is generally used when there is no space or when the other two methods can't be used
    1. AIn-Situ
    2. BTilt-Cast
    3. CPre-Situ
    4. DPre-Cast
    5. ETilt Up
  6. 6The erection of tilt up walls involves the following sequence after footing placement and panel curing:

    1. [blank_start]Strip away the formwork[blank_end]
    2. [blank_start]Provide prop supports[blank_end]
    3. [blank_start]Arrange suitable cranes[blank_end]
    4. [blank_start]Prepare final levals[blank_end]
    5. [blank_start]Attach Props[blank_end]
    6. [blank_start]Lifting Operations[blank_end]
    7. [blank_start]Fix panels in place[blank_end]
    8. [blank_start]Remove props[blank_end]
    9. [blank_start]Patch panels[blank_end]
    10. [blank_start]Grout beneath panels[blank_end]
    11. [blank_start]Seal between panels[blank_end]
    1. AStrip away the formwork
    2. BProvide prop supports
    3. CArrange suitable cranes
    4. DPrepare final levals
    5. EAttach Props
    6. FLifting Operations
    7. GFix panels in place
    8. HRemove props
    9. IPatch panels
    10. JGrout beneath panels
    11. KSeal between panels
  7. 7The erection of tilt up walls involves the following sequence after footing placement and panel curing:

    1. [blank_start]Strip away the formwork[blank_end]
    2. [blank_start]Provide prop supports[blank_end]
    3. [blank_start]Arrange suitable cranes[blank_end]
    4. [blank_start]Prepare final levels[blank_end]
    5. [blank_start]Attach Props[blank_end]
    6. [blank_start]Lifting Operations[blank_end]
    7. [blank_start]Fix panels in place[blank_end]
    8. [blank_start]Remove props[blank_end]
    9. [blank_start]Patch panels[blank_end]
    10. [blank_start]Grout beneath panels[blank_end]
    11. [blank_start]Seal between panels[blank_end]
    12. [blank_start]Apply any finishes[blank_end]
    1. AStrip away the formwork
    2. BProvide prop supports
    3. CArrange suitable cranes
    4. DPrepare final levels
    5. EAttach Props
    6. FLifting Operations
    7. GFix panels in place
    8. HRemove props
    9. IPatch panels
    10. JGrout beneath panels
    11. KSeal between panels
    12. LApply any finishes
  8. 8Answer the correct statement for LVL:

    Laminated Veneer Lumber is a [blank_start]high-strength[blank_end] engineered wood product made from [blank_start]veneers[blank_end] bonded together under [blank_start]heat and pressure[blank_end].
    It is used for [blank_start]permanent[blank_end] structural applications including [blank_start]beams and rafters[blank_end].
    1. Ahigh-strength
    2. Blow-strength
    3. Cmedium-strength
    4. Dveneers
    5. Eglue
    6. Fmetal
    7. Gheat and pressure
    8. Hheat and glue
    9. Iheat and timber
    10. Jpressure
    11. Kheat
    12. Lpermanent
    13. Mtemporary
    14. Nbeams and rafters
    15. Oapex joints
    16. Pstruts and purlins
    17. Qaesthetics
  9. 9When fabricating industrial building frames the subcontracted company will typically carry out the following duties in sequence:

    1. [blank_start]Prepare workshop drawings[blank_end]
    2. [blank_start]Provide holding down bolts[blank_end]
    3. [blank_start]Buy in "raw" steel products[blank_end]
    4. [blank_start]Manufacture components[blank_end]
    5. [blank_start]Prepare & prime steelwork[blank_end]
    6. [blank_start]Arrange purlins & girts[blank_end]
    7. [blank_start]Arrange site delivery[blank_end]
    8. [blank_start]Organise riggers & crane[blank_end]
    1. APrepare workshop drawings
    2. BProvide holding down bolts
    3. CBuy in "raw" steel products
    4. DManufacture components
    5. EPrepare & prime steelwork
    6. FArrange purlins & girts
    7. GArrange site delivery
    8. HOrganise riggers & crane
  10. 10Select advantages of tilt-up wall from the options below:
    1. ASafety
    2. BFast-track delivery
    3. CCost containment
    4. DDurability
    5. EManufactured off site
    6. FArchitectural aesthetics

Informationen

Beschreibung
Quiz am Construction 2 Exam Revision, erstellt von Isaac Mont am 17/06/2019.
Sprache
English
Aufrufe
10
Bewertung
Noch keine Bewertungen
Bewerte dieses Quiz
Bewerte dieses Quiz

Feedback

Worum geht es?

Was sollen wir als Nächstes hinzufügen?