  1. 1Which one is not a basic element of Project Management?
    1. ADefining the overall project
    2. BFormulating time estimates for each task
    3. CEstimating project costs
    4. DNone of the others
  2. 2A project organization consists of?
    1. AProject manager
    2. BAll of the others
    3. CProject team
    4. DProject management system
  3. 3Which project application best illustrates the need for multiple time estimates?
    1. AFinancial audit
    2. BCommercial building construction
    3. CRobotic vacuum cleaner development
    4. DRefinery maintenance
  4. 4Which one of the following statements regarding the Gantt chart is true?
    1. AEvolved from the PERT chart
    2. BShows a plot of budget versus time
    3. CDeveloped during World War II
    4. DShows the scheduling of individual project tasks over time
  5. 5Which graph shows the sequencing of tasks over time?
    1. ADecision tree
    2. BGantt chart
    3. CFlow chart
    4. DHistogram
  6. 6Typically, crash time is defined as the?
    1. ADifference between earliest and latest starting times
    2. BMinimum time a task can be completed
    3. CMaximum tine a task can be completed
    4. DAverage time a task can be completed
  7. 7Which analytical process is used to determine the optimal way to reduce overall project time?
    1. APERT
    2. BSlack Management
    3. CCrashing
    4. DPERT-Cost
  8. 8The distribution of a project task with the time estimates of 2, 6, 10 is?
    1. ASkewed right
    2. BSkewed left
    3. CUniformly distributed
    4. DNormally distributed
  9. 9In an AOA network diagram the nodes represent _____ and the arcs represent ______ ?
    1. ASlack, Tasks
    2. BCritical time, Slack
    3. CTasks, Events
    4. DEvents, Tasks
  10. 10The Critical path is?
    1. ASet of tasks with zero slack
    2. BBased on the most likely time a task will take to complete
    3. CSet of tasks with positive slack
    4. DSet of tasks with negative slack

Informationen

Beschreibung
Quiz am Final Exam Review, erstellt von lseyer436 am 07/04/2015.
Sprache
English
Aufrufe
8
Bewertung
Noch keine Bewertungen
Bewerte dieses Quiz
Bewerte dieses Quiz

Mehr zu Project Scheduling and Network Analysis

Feedback

Worum geht es?

Wie gefällt dir das neue Design?

Dein Eindruck