Fragen in diesem Quiz (10)
1which ONE is a team member of the theatre?
- Aproducer
- Bfood seller
- Csecurity
- Dactor
2A gant chart is
- Ais a representation of an overall project schedule as a bar chart displaying all the tasks and activities involved.
- Ba table whch shows time scales used for a food company
- Ca chart which displays every task and what to do and when to do it
3what is project planning
- Ais used to help with the planning
- Bscheduling and management of complex projects.
- Chelps woth the production of tickets
4milestones are used to indicate the end of key tasks within a project
- ARichtig
- BFalsch
5A deadline is the date by which a milestone must be completed.
- ARichtig
- BFalsch
6this is an advantage of a gannt chart: Gantt charts give an easy-to-understand graphical view of all the project tasks.
- ARichtig
- BFalsch
7this is a disadvantage of gannt charts: The Gantt chart becomes cluttered and difficult to understand where many dependencies between the various tasks are shown.
- ARichtig
- BFalsch
8which is the correct steps to project management
- AInitialisation-Planning and Design-Implementation-Closure
- BImplementation-Initialisation-Planning and Design-Closure
- CPlanning and Design-Implementation-Initialisation-Closure
9Planning is the first duty that the project management
- ARichtig
- BFalsch
10this is apart of the progress part of project planning: Team members enter their overall progress and time consumed on a task into the project software
- ARichtig
- BFalsch
Informationen
- Beschreibung
- Quiz am Ohne Titel, erstellt von m-a-t-t-y- am 18/05/2015.
- Autor
- m-a-t-t-y-
- Sprache
- English
- Aufrufe
- 0
- Bewertung
- Noch keine Bewertungen Bewerte dieses Quiz